A framework to estimate the risk-based shutdown interval for a processing plant

被引:33
|
作者
Hameed, Abdul [1 ]
Khan, Faisal [1 ]
机构
[1] Mem Univ, Fac Engn & Appl Sci, St John, NF, Canada
基金
加拿大自然科学与工程研究理事会;
关键词
Shutdown; Maintenance and inspection; Criticality ranking; Risk-based equipment selection; Shutdown interval estimation; MAINTENANCE OPTIMIZATION; RBM; INSPECTION;
D O I
10.1016/j.jlp.2014.07.009
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
Petrochemical plants and refineries consist of hundreds of pieces of complex equipment and machinery that run under rigorous operating conditions and are subjected to deterioration over time due to aging, wear, corrosion, erosion, fatigue and other reasons. These devices operate under extreme operating pressures and temperatures, and any failure may result in huge financial consequences for the operating company. To minimize the risk and to maintain operational reliability and availability, companies adopt various maintenance strategies. Shutdown or turnaround maintenance is one such strategy. In general, shutdown for inspection and maintenance is based on the original equipment manufacturer's (OEM) suggested recommended periods. However, this may not be the most optimum strategy given that operating conditions may vary significantly from company to company. The framework proposed in this work estimates the risk-based shutdown interval for inspection and maintenance. It provides a tool for maintenance planning and decision making by considering the probability of the equipment or system for failure and the likely consequences that may follow. The novel risk-based approach is compared with the conventional fixed interval approach. This former approach, characterized as it is by optimized inspection, maintenance and risk management, leads to extended intervals between shutdowns. The result is the increase in production and the consequent income of millions of dollars. The proposed framework is a cost effective way to minimize the overall financial risk for asset inspection and maintenance while fulfilling safety and availability requirements. (C) 2014 Elsevier Ltd. All rights reserved.
引用
收藏
页码:18 / 29
页数:12
相关论文
共 50 条
  • [1] A risk-based methodology to estimate shutdown interval considering system availability
    Hameed, Abdul
    Khan, Faisal
    Ahmed, Salim
    PROCESS SAFETY PROGRESS, 2015, 34 (03) : 267 - 279
  • [2] A risk-based shutdown inspection and maintenance interval estimation considering human error
    Hameed, Abdul
    Khan, Faisal
    Ahmed, Salim
    PROCESS SAFETY AND ENVIRONMENTAL PROTECTION, 2016, 100 : 9 - 21
  • [3] Risk-based shutdown management of LNG units
    Keshavarz, Ghaffar
    Thodi, Premkumar
    Khan, Faisal
    JOURNAL OF LOSS PREVENTION IN THE PROCESS INDUSTRIES, 2012, 25 (01) : 159 - 165
  • [4] Risk-based optimization of the design of on-shore pipeline shutdown systems
    Medina, Hector
    Arnaldos, Josep
    Casal, Joaquim
    Bonvicini, Sarah
    Cozzani, Valerio
    JOURNAL OF LOSS PREVENTION IN THE PROCESS INDUSTRIES, 2012, 25 (03) : 489 - 493
  • [5] A unified framework for risk-based investing
    Jurczenko, Emmanuel
    Michel, Thierry
    Teiletche, Jerome
    JOURNAL OF INVESTMENT STRATEGIES, 2015, 4 (04): : 1 - 29
  • [6] Risk-based analysis justifies expanding maintenance interval
    Perdomo, Jorge J.
    Medina, Robinson J.
    2000, Gulf Publ Co, Houston, TX, USA (83):
  • [7] A risk-based framework for biomedical data sharing
    Dankar, Fida K.
    Badji, Radja
    JOURNAL OF BIOMEDICAL INFORMATICS, 2017, 66 : 231 - 240
  • [8] Verification of the Framework for Risk-Based Bridge Inspection
    Washer, Glenn
    Connor, Robert
    Nasrollahi, Massoud
    Reising, Rebecca
    JOURNAL OF BRIDGE ENGINEERING, 2016, 21 (04)
  • [9] The risk-based view of trust: A conceptual framework
    Das, TK
    Teng, BS
    JOURNAL OF BUSINESS AND PSYCHOLOGY, 2004, 19 (01) : 85 - 116
  • [10] The Risk-Based View of Trust: A Conceptual Framework
    T. K. Das
    Bing-Sheng Teng
    Journal of Business and Psychology, 2004, 19 : 85 - 116