Project Performance of Public-Private Partnership Projects Based on Various Contract Agreements and Correlation with Funding Mechanism

被引:0
|
作者
Fathi, Medya [1 ]
Shrestha, Pramen P. [1 ]
机构
[1] Univ Nevada, Civil & Environm Engn & Construct Dept, Howard R Hughes Coll Engn, Las Vegas, NV 89154 USA
关键词
Public-private partnership; infrastructure transportation; cost performance; schedule performance; funding sources;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the past, the state department of transportations (DOTs) used to build the highways and bridges through the traditional delivery method, design-bid-build (DBB). However, in the last couple of decades, alternative delivery methods, design-build (DB), and general contractor/construction management (GC/CM) were widely used in the construction of highways and bridges. These alternative delivery methods were employed when the state had a hundred percent funding available for the design and construction of the projects. Due to the scarcity of the public fund for highways and bridges, recently the public-private partnership (PPP) delivery method has been developed, so that the state can benefit from private funding to build the public projects. There are various types of PPP contract agreements, e.g., design-build-finance-operate-maintenance (DBFOM), design-build-finance-operate (DBFO), design-build-finance-maintenance (DBFM), and build-operate-transfer (BOT). Considering the recent use of different PPPs in highway and bridge projects, no study has been conducted to determine whether the type of PPP contract agreements has any effect on the cost and schedule performance of the projects. Therefore, this study has collected 10 PPP projects with two types of contract agreements, DBFOM and DBFM, to determine if there is any project performance difference in PPP projects. Through a data analysis, the results showed a slightly better cost performance and a significantly better schedule performance for DBFOM projects. Investigating funding and finance sources revealed the considerable difference in public funding and private finance between these two PPP agreements, which may be attributable to the difference found in cost and schedule performance. There have been some limitations in the number of projects, first due to the number of existing projects, and second, the available data to collect for the analysis. Similar to any new adoption, this limitation will be eliminated over time.
引用
收藏
页码:1081 / 1090
页数:10
相关论文
共 50 条
  • [31] The optimal debt ratio of public-private partnership projects
    Chen, Borliang
    Mao, Chi-Kuo
    Hu, Jin-Li
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2015, 15 (03) : 239 - 253
  • [32] Risk Misallocation in Public-Private Partnership Projects in China
    Ke, Yongjian
    Wang, Shouqing
    Chan, Albert P. C.
    INTERNATIONAL PUBLIC MANAGEMENT JOURNAL, 2013, 16 (03) : 438 - 460
  • [33] Bundling in public-private partnership projects - a conceptual framework
    Dolla, Tharun
    Laishram, Boeing
    INTERNATIONAL JOURNAL OF PRODUCTIVITY AND PERFORMANCE MANAGEMENT, 2020, 69 (06) : 1177 - 1203
  • [34] REAL OPTIONS IN PUBLIC-PRIVATE PARTNERSHIP PROJECTS: AN OVERVIEW
    Ben Abdallah, Skander
    ACTUALITE ECONOMIQUE, 2019, 95 (2-3): : 323 - 346
  • [35] The attractiveness of public-private partnership for road projects in India
    Malek, Mohammed Shakil
    Zala, Laxmansinh
    JOURNAL OF PROJECT MANAGEMENT, 2022, : 111 - 120
  • [36] STATE AND BUSINESS INTERESTS IN PUBLIC-PRIVATE PARTNERSHIP PROJECTS
    Porovskaya, Anna Ya
    TOMSK STATE UNIVERSITY JOURNAL, 2009, (328): : 131 - +
  • [37] PERFROMANCE MEASUREMENT AND MANAGEMENT OF PUBLIC-PRIVATE PARTNERSHIP PROJECTS
    Augustinova, Edita
    Daubner, Michal
    GEOCONFERENCE ON ECOLOGY, ECONOMICS, EDUCATION AND LEGISLATION, SGEM 2013, VOL II, 2013, : 239 - 246
  • [38] Managing risks in public-private partnership formation projects
    Keers, Bianca B. M.
    van Fenema, Paul C.
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2018, 36 (06) : 861 - 875
  • [39] Risk-based integrated performance assessment framework for public-private partnership infrastructure projects
    Fatima, Anam
    Mubin, Sajjad
    Masood, Rehan
    ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2024, 16 (01): : 251 - 274
  • [40] Synthesis of Innovation Research in Public-Private Partnership Projects
    Gonzalez, Edwin E.
    Garvin, Michael J.
    CONSTRUCTION RESEARCH CONGRESS 2016: OLD AND NEW CONSTRUCTION TECHNOLOGIES CONVERGE IN HISTORIC SAN JUAN, 2016, : 428 - 437