Structural response of existed metro tunnels to adjacent large-section pipe jacking construction

被引:12
|
作者
Liu, Bo [1 ]
Zhang, Dingwen [1 ]
Fang, Lei [1 ]
机构
[1] Southeast Univ, Sch Transportat, 2 Sipailou, Nanjing 210096, Jiangsu, Peoples R China
关键词
Structural response; Metro tunnel; Pipe jacking; Field Monitoring; SOIL; SLURRY;
D O I
10.1016/j.proeng.2017.05.003
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
A rectangular pedestrian underpass of 94.5m long, 7m wide and 4.3m high was constructed across the existed metro tunnels using pipe jacking method. The minimum distance from underpass bottom to tunnel crown was 4.5m. In order to investigate the effects of pipe jacking on existed underlying tunnels, the instruments were installed in the tunnels and structural responses were extensively monitored. Based on the field observations, the vertical displacement, horizontal displacement and diameter convergence of the tunnel were analyzed. The results indicate that in the whole pipe jacking process, the tunnel vertical displacement mainly goes through three different stages, namely, initial settlement stage, quick heave stage and steady heave stage. The horizontal displacement of ballast bed is much smaller than that of tunnel crown and is almost negligible. The tunnel was horizontally compressed and vertically stretched after pipe jacking construction. Pipe jacking construction has a greater effect on the tunnel structures just below the underpass than that beyond the width scope of underpass, whether it is vertical displacement, horizontal displacement or diameter convergence of the tunnel. (C) 2017 The Authors. Published by Elsevier Ltd.
引用
收藏
页码:11 / 17
页数:7
相关论文
共 50 条
  • [31] Research on the ring strain of the segment for large-section underwater shield tunnels
    Xing, Rongjun
    Tang, Chao
    He, Chuan
    Feng, Kun
    Xu, Shengya
    He, Zhengshu
    Zhu, Daiqiang
    Xu, Pai
    JOURNAL OF CIVIL STRUCTURAL HEALTH MONITORING, 2024, : 1207 - 1229
  • [32] Instability failure modes and construction mechanics of large-section multi-arch tunnels in fly ash deposits
    Yu, Tao
    Liao, Hang
    Zhu, Ningbo
    Yao, Zhigang
    Fang, Yong
    Li, Xiwen
    Tian, Qingfeng
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2024, 46 (09): : 1909 - 1918
  • [33] Investigation of response of metro tunnels due to adjacent large excavation and protective measures in soft soils
    Chen, Renpeng
    Meng, Fanyan
    Li, Zhongchao
    Ye, Yuehong
    Ye, Junneng
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 58 : 224 - 235
  • [34] Floor heave failure mechanism of large-section tunnels in sandstone with shale stratum after construction: A case study
    Ma, Kaimeng
    Zhang, Junru
    Zhang, Jichun
    Dai, Yi
    Zhou, Ping
    ENGINEERING FAILURE ANALYSIS, 2022, 140
  • [35] Optimization of Construction Parameters and Deformation Characteristics of Large-Section Loess Tunnel: A Case Study from Xi'an Metro
    Zhao, Mingji
    Cheng, Yun
    Song, Zhanping
    Wang, Tong
    Zhang, Yuwei
    Liulian, Baichao
    ADVANCES IN CIVIL ENGINEERING, 2021, 2021
  • [36] Study on Mechanical Properties of Composite Pipe Jacking with a Super-Large Rectangular Section During Construction
    Liu H.
    Zhang G.
    Pan W.
    Wen S.
    Cui Q.
    Tianjin Daxue Xuebao (Ziran Kexue yu Gongcheng Jishu Ban)/Journal of Tianjin University Science and Technology, 2023, 56 (11): : 1115 - 1124
  • [37] Floor heave failure mechanism of large-section tunnels in sandstone with shale stratum after construction: A case study
    Ma, Kaimeng
    Zhang, Junru
    Zhang, Jichun
    Dai, Yi
    Zhou, Ping
    Engineering Failure Analysis, 2022, 140
  • [38] Numerical analysis of stability of surrounding rock for large-section tunnels with small spacing
    Gong, Jian-Wu
    Lei, Xue-Wen
    Yantu Lixue/Rock and Soil Mechanics, 2010, 31 (SUPPL. 2): : 412 - 417
  • [39] Selecting the pipe jacking construction method. Comparison with segmented tunnels of medium diameter
    Rodríguez, Juan José Hoyo
    Romana, Manuel G.
    Revista de Obras Publicas, 2015, 162 (3568): : 65 - 78
  • [40] The effect of post-construction settlement during pipe jacking construction phase on relative displacement of pipe section
    Zhenyu, Gao
    Haihong, Mo
    Jubo, Zeng
    Electronic Journal of Geotechnical Engineering, 2014, 19 (0W): : 7037 - 7048