Neural network models for actual duration of Greek highway projects

被引:6
|
作者
Titirla, Magdalini [1 ]
Arctoulis, Gcorgios [2 ]
机构
[1] Univ Claude Bernard Lyon 1, Fac Sci & Technol, Villeurbanne, France
[2] Aristotle Univ Thessaloniki, Dept Civil Engn, Thessaloniki, Greece
关键词
Neural networks; Attribute selection; Highway construction; Predicting models; Project actual duration; WEKA; CONSTRUCTION; SUPPORT; IMPACT; COST;
D O I
10.1108/JEDT-01-2019-0027
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data available at the bidding stage. Design/methodology/approach Relevant literature review is presented that highlights similar research approaches. Thirty-seven highway projects, constructed in Greece, with similar type of available data, were examined. Considering each project's characteristics and the actual construction duration, correlation analysis is implemented, with the aid of SPSS. Correlation analysis identified the most significant project variables toward predicting actual duration. Furthermore, the WEKA application, through its attribute selection function, highlighted the most important subset of variables. The selected variables through correlation analysis and/or WEKA and appropriate combinations of these are used as input neurons for a neural network. Fast Artificial Neural Network (FANN) Tool is used to construct neural network models in an effort to predict projects' actual duration. Findings Variables that significantly correlate with actual time at completion include initial cost, initial duration, length, lanes, technical projects, bridges, tunnels, geotechnical projects, embankment, landfill, land requirement (expropriation) and tender offer. Neural networks' models succeeded in predicting actual completion time with significant accuracy. The optimum neural network model produced a mean squared error with a value of 6.96E-06 and was based on initial cost, initial duration, length, lanes, technical projects, tender offer, embankment, existence of bridges, geotechnical projects and landfills. Research limitations/implications - The sample size is limited to 37 projects. These are extensive highway projects with similar work packages, constructed in Greece. Practical implications - The proposed models could early in the planning stage predict the actual project duration. Originality/value The originality of the current study focuses both on the methodology applied (combination of Correlation Analysis, WEKA, FannTool) and on the resulting models and their potential application for future projects.
引用
收藏
页码:1323 / 1339
页数:17
相关论文
共 50 条
  • [1] Hazard-Based Duration Models for Predicting Actual Duration of Highway Projects Using Nonparametric and Parametric Survival Analysis
    Qiao, Yu
    Labi, Samuel
    Fricker, Jon D.
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2019, 35 (06)
  • [2] Neural network model for parametric cost estimation of highway projects
    Hegazy, T
    Ayed, A
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (03): : 210 - 218
  • [3] A Comparative Study of Models for the Construction Duration Prediction in Highway Road Projects of India
    Velumani, P.
    Nampoothiri, N. V. N.
    Urbanski, M.
    SUSTAINABILITY, 2021, 13 (08)
  • [4] Application of BP Neural Network Algorithm in Sustainable Development of Highway Construction Projects
    Li, Mingshun
    Chen, Wencui
    INTERNATIONAL CONFERENCE ON SOLID STATE DEVICES AND MATERIALS SCIENCE, 2012, 25 : 1212 - 1217
  • [5] Use of a Feedforward Neural Network for Predicting the Development Duration of Software Projects
    Lopez-Martin, Cuauhtemoc
    Chavoya, Arturo
    Elena Meda-Campana, Maria
    2013 12TH INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND APPLICATIONS (ICMLA 2013), VOL 2, 2013, : 156 - 159
  • [6] Forecasting final budget and duration of highway construction projects
    Pewdum, Wichan
    Rujirayanyong, Thammasak
    Sooksatra, Vanee
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2009, 16 (06) : 544 - +
  • [7] CONCEPTUAL ESTIMATION OF CONSTRUCTION DURATION AND COST OF PUBLIC HIGHWAY PROJECTS
    Mohamed, Basma
    Moselhi, Osama
    JOURNAL OF INFORMATION TECHNOLOGY IN CONSTRUCTION, 2022, 27 : 595 - 618
  • [8] CONCEPTUAL ESTIMATION OF CONSTRUCTION DURATION AND COST OF PUBLIC HIGHWAY PROJECTS
    Mohamed, Basma
    Moselhi, Osama
    Journal of Information Technology in Construction, 2022, 27 : 595 - 618
  • [9] Sequential forecast of incident duration using Artificial Neural Network models
    Wei, Chien-Hung
    Lee, Ying
    ACCIDENT ANALYSIS AND PREVENTION, 2007, 39 (05): : 944 - 954
  • [10] PREDICTING INDEX TO COMPLETE SCHEDULE PERFORMANCE INDICATOR IN HIGHWAY PROJECTS USING ARTIFICIAL NEURAL NETWORK MODEL
    Jasim, Nidal A.
    Maruf, Shelan M.
    Aljumaily, Hadi S. M.
    Al-Zwainy, Faiq M. S.
    ARCHIVES OF CIVIL ENGINEERING, 2020, 66 (03) : 541 - 554