Problems Causing Delays and Risk Factors in Welding Construction Projects of Thailand

被引:2
|
作者
Prateepasen, Asa [1 ]
Aumpiem, Adisak [2 ]
机构
[1] King Mongkuts Univ Technol Thonburi KMUTT, Fac Engn, Dept Prod Engn, Bangkok, Thailand
[2] King Mongkuts Univ Technol Thonburi KMUTT, Fac Engn, Ind & Mfg Syst Engn, Bangkok, Thailand
来源
ENGINEERING JOURNAL-THAILAND | 2021年 / 25卷 / 05期
关键词
Delay risk; Thailand; fabrication risk; welding risk; construction; MANAGEMENT; INDUSTRY;
D O I
10.4186/ej.2021.25.5.33
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Welding delays are one of the major risks in steel construction industry in Thailand. Therefore, it is essential to study and analyze the risk factors that lead to problems causing welding construction delays. This studied focused on delay risk factors in causes of construction projects collected from literature review having the different construction processes, project period, culture, countries, and amount of delay factors for contribution in welding construction projects. Questionnaire surveys and interviews were conducted on major companies connected to welding works in support of the construction projects in Thailand to survey thought problems causing delays and risk factors. Risk factors related to internal and external risk were rated among the risks identified problems. Issues such as material receiving, performance, qualified and language barriers were also highlighted in the questionnaire and during interviews. Notably, the problem such as "multilingual and multicultural" caused ineffective communication. A case study used the FMEA technique to analyze the severity, occurrences and detection, and evaluate to risk priority number. Significant risks were analyzed and compared between the Modified RPN and WRPN method for finding the "Critical risk". The new finding can contribute additional help for project managers to predict and mitigate welding construction project delays.
引用
收藏
页码:33 / 44
页数:12
相关论文
共 50 条
  • [31] CAUSES OF DELAYS IN IRANIAN CONSTRUCTION PROJECTS
    Khoshgoftar, Mohammad
    Abu Bakar, Abu Hassan
    Osman, Omar
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2010, 10 (02) : 53 - 69
  • [32] Delays in construction projects - Causes and impacts
    Arantes, Amlcar
    da Silva, Pedro Fernandez
    Ferreira, Luis Miguel D. F.
    2015 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM), 2015, : 1105 - 1110
  • [33] CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
    Kazaz, Aynur
    Ulubeyli, Serdar
    Tuncbilekli, Nihan Avcioglu
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2012, 18 (03) : 426 - 435
  • [34] Delays in Building Construction Projects in Ghana
    Fugar, Frank D. K.
    Agyakwah-Baah, Adwoa B.
    CONSTRUCTION ECONOMICS AND BUILDING, 2010, 10 (1-2):
  • [35] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - CLOSURE
    KRAIEM, ZM
    DIEKMANN, JE
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 337 - 338
  • [36] Construction projects: interactions of the causes of delays
    Purushothaman, Mahesh Babu
    San Pedro, Leo Neil Resurreccion
    GhaffarianHoseini, Ali
    SMART AND SUSTAINABLE BUILT ENVIRONMENT, 2024,
  • [37] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - DISCUSSION
    LOGCHER, RD
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 335 - 337
  • [38] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS.
    Kraiem, Zaki M.
    Diekmann, James E.
    Journal of Construction Engineering and Management, 1987, 113 (04) : 591 - 602
  • [39] Economic and Time Risk Factors Influencing the Construction Projects: A Case Study of Lebanese Construction Projects
    Ahmad, Omar
    Nouban, Fatemeh
    JORDAN JOURNAL OF CIVIL ENGINEERING, 2023, 17 (03) : 399 - 407
  • [40] An evaluation of risk factors impacting construction projects in Ghana
    Chileshe, Nicholas
    Yirenkyi-Fianko, Adwoa Boadua
    JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2012, 10 (03) : 306 - 329