Correlating the chemical engineering plant cost index with macro-economic indicators

被引:176
|
作者
Mignard, Dimitri [1 ]
机构
[1] Univ Edinburgh, Sch Engn, Edinburgh EH9 3JK, Midlothian, Scotland
来源
关键词
Chemical engineering plant cost index; Capital cost estimates; Price of oil; Interest rates; Inflation; Plant cost index forecast;
D O I
10.1016/j.cherd.2013.07.022
中图分类号
TQ [化学工业];
学科分类号
0817 ;
摘要
The chemical engineering plant cost index (CEPCI) is widely used for updating the capital costs of process engineering projects. Typically, forecasting it requires twenty or so parameters. As an alternative, we suggest a correlation for predicting the index as a function of readily available and forecast macro-economic indicators: CEPCI(n) = 0.135 x CEPCI(k(o)) x exp {A x Sigma(n)(k=ko)i(k)} + B x P-oil + C, with k(o) the first year of the period consideration, i(k) the interest rate on US bank prime loans in year k, and P-oil the US domestic oil price in year n. Best fit was obtained when choosing distinct sets of values of the constants A, B and C for each of the three periods 1958 to 1980; 1981 to 1999; and 2000 to 2011. These changes could have resulted from the impact of the oil shocks in the 1970s and very high interest rates in the 1980s, which perhaps heralded changes to the index formula in 1982 and 2002. The error was within 3% in any year from 1958 to 2011, and within 1% from 2004 to 2011 after readjusting the weighting of the price of oil. The correlation was applied to forecast the CEPCI under different scenarios modelled by the Energy Information Administration or predicted from oil futures contracts. (C) 2013 The Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.
引用
收藏
页码:285 / 294
页数:10
相关论文
共 28 条
  • [21] Stochastic analysis of the main macro-economic indicators characterizing higher education in Romania during 2001-2016
    Matei, Ani
    Cristache, Silvia Elena
    Marin, Erika
    Rotaru, Florica Georgeta
    PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON BUSINESS EXCELLENCE, 2017, 11 (01): : 1158 - 1166
  • [22] Causals of Time-Scaled Volatility, Business Cycles and Macro-Economic Indicators: A Wavelet Analysis of Selected Islamic Countries
    Gulzar, Muhammad
    Kalim, Rukhsana
    INTERNATIONAL JOURNAL OF CONTEMPORARY ECONOMICS AND ADMINISTRATIVE SCIENCES, 2022, 12 (01): : 359 - 386
  • [23] Sustainable Economic Development and High Quality Engineering Education: Correlating Factors in Brazil's Macro Regions
    Caldana, Vitor Mendes
    da Silva, Marcia Terra
    ADVANCES IN PRODUCTION MANAGEMENT SYSTEMS: INITIATIVES FOR A SUSTAINABLE WORLD, 2016, 488 : 398 - 405
  • [24] Cost Calculation in Chemical Plant Engineering: A Model for Assessing Competitiveness in the Development Stage
    Horst, Stephan
    Hoefer, Jannik
    Kleine-Moellhoff, Peter
    Wennagel, Fabienne
    Wiech, Nils
    Pfost, Michael
    Atmaca, Bercan
    Gries, Julia
    Epple, Rolf
    CHEMIE INGENIEUR TECHNIK, 2020, 92 (08) : 1033 - 1043
  • [25] Approach to include labor productivity correction in a two-component chemical plant cost index
    Mithani, R.
    Chemical Age of India, 1987, 38 (12): : 655 - 657
  • [26] Engineering and economic indicators and maneuverability characteristics of a PGU-80 double unit and PGU-39 single units at the Sochi thermal power plant
    Radin Yu.A.
    Razogreev V.G.
    Grishin I.A.
    Kuznetsov E.G.
    Power Technology and Engineering, 2011, 45 (3) : 213 - 217
  • [27] LIMIT AND CONTRACT PRICES WORKING OUT - A KEY ELEMENT OF ECONOMIC MECHANISM OF COST REDUCTION IN CHEMICAL-COMPLEX BRANCHES AND SUB-BRANCHES ENGINEERING
    KUVSHINOV, VV
    KHIMICHESKAYA PROMYSHLENNOST, 1991, (02): : 120 - 122