Optimal scheduling of track maintenance activities for railway networks

被引:9
|
作者
Su, Zhou [1 ]
De Schutter, Bart [1 ]
机构
[1] Delft Univ Technol, Delft Ctr Syst & Control, NL-2628 CD Delft, Netherlands
来源
IFAC PAPERSONLINE | 2018年 / 51卷 / 09期
关键词
maintenance; railway infrastructure; arc routing problem; logistics; scheduling; ARC-ROUTING-PROBLEMS; FORMULATION; CONSTRAINTS;
D O I
10.1016/j.ifacol.2018.07.063
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
We consider optimal scheduling of track maintenance activities for a railway network divided into sections. The goal is to find an optimal time schedule for the maintenance activities and optimal routes for the maintenance crew (including all necessary equipment and technicians) that minimize the total setup costs and the travel costs over the whole planning horizon. The maintenance time budget, which can be the same, different, or flexible for each period, and the minimum time to maintain a section are also taken into account. We recast the track maintenance scheduling problem with three different settings as three variants of the Capacitated Arc Routing Problem with Fixed cost (CARPF), which are solved by transforming them into three node routing problems. The proposed approach is demonstrated using a case study of a part of the Dutch regional network. (C) 2018, IFAC (International Federation of Automatic Control) Hosting by Elsevier Ltd. All rights reserved.
引用
收藏
页码:386 / 391
页数:6
相关论文
共 50 条
  • [1] Scheduling of railway track maintenance activities and crews
    Higgins, A
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1998, 49 (10) : 1026 - 1033
  • [2] Optimal Scheduling of Track Maintenance on a Railway Network
    Zhang, Tao
    Andrews, John
    Wang, Rui
    [J]. QUALITY AND RELIABILITY ENGINEERING INTERNATIONAL, 2013, 29 (02) : 285 - 297
  • [3] Risk-based optimal scheduling of maintenance activities in a railway network
    Consilvio, Alice
    Di Febbraro, Angela
    Meo, Rossella
    Sacco, Nicola
    [J]. EURO JOURNAL ON TRANSPORTATION AND LOGISTICS, 2019, 8 (05) : 435 - 465
  • [4] A heuristic approach to railway track maintenance scheduling
    Quiroga, L. M.
    Schnieder, E.
    [J]. COMPUTERS IN RAILWAYS XII: COMPUTER SYSTEM DESIGN AND OPERATION IN RAILWAYS AND OTHER TRANSIT SYSTEMS, 2010, 114 : 687 - 699
  • [5] Minimising costs in scheduling railway track maintenance
    Lake, M
    Ferreira, L
    Murray, M
    [J]. COMPUTERS IN RAILWAYS VII, 2000, 7 : 895 - 902
  • [6] Scheduling preventive railway maintenance activities
    Budai, G.
    Huisman, D.
    Dekker, R.
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2006, 57 (09) : 1035 - 1044
  • [7] Scheduling preventive railway maintenance activities
    Budai, G
    Huisman, D
    Dekker, R
    [J]. 2004 IEEE INTERNATIONAL CONFERENCE ON SYSTEMS, MAN & CYBERNETICS, VOLS 1-7, 2004, : 4171 - 4176
  • [8] Integrated condition-based track maintenance planning and crew scheduling of railway networks
    Su, Zhou
    Jamshidi, Ali
    Nunez, Alfredo
    Baldi, Simone
    De Schutter, Bart
    [J]. TRANSPORTATION RESEARCH PART C-EMERGING TECHNOLOGIES, 2019, 105 : 359 - 384
  • [9] Optimal opportunistic tamping scheduling for railway track geometry
    Khajehei, Hamid
    Haddadzade, Mohammad
    Ahmadi, Alireza
    Soleimanmeigouni, Iman
    Nissen, Arne
    [J]. STRUCTURE AND INFRASTRUCTURE ENGINEERING, 2021, 17 (10) : 1299 - 1314
  • [10] OPTIMIZING RAILWAY TRACK MAINTENANCE SCHEDULING TO MINIMIZE CIRCULATION IMPACTS
    Bueno, Paulo M. S.
    Vilela, Plinio R. S.
    Christofoletti, Luciano M.
    Vieira, Anderson P.
    [J]. PROCEEDINGS OF THE ASME JOINT RAIL CONFERENCE, 2019, 2019,