A survey on production planning system in construction projects based on Last Planner System

被引:15
|
作者
Ha Duy Khanh [1 ]
Kim, Soo Yong [2 ]
机构
[1] Ho Chi Minh City Univ Technol & Educ, Dept Civil Engn & Appl Mech, Ho Chi Minh 700000, Vietnam
[2] Pukyong Natl Univ, Dept Civil Engn, Busan 608739, South Korea
关键词
lean construction; last planner; planning and control; production; workflow; Vietnam;
D O I
10.1007/s12205-015-1412-y
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Production planning has a critical role in obtaining project success through improving the reliability of workflow. Previous studies have shown the effectiveness of production planning in construction projects. This study aims to examine the current practice of production planning system in Vietnam Construction Industry (VCI) based on the Last Planner System (LPS). An assessment framework for production planning procedures has been employed according to the previous studies. Questionnaire survey, case study and expert survey were employed in this study. The results of analysis have indicated that most of production planning procedures at team workshop step and weekly work plan step in VCI are well performed; whereas most of procedures at lookahead plan step are superficially performed. Master schedule and weekly work plan are the most used plans when executing a construction project. Tool for constraints analysis and tool for measurement of percent plan completed are highly employed. 'Low understanding of the concepts of LPS' and 'language and culture issues' are the largest and smallest barriers respectively. 'Indirect cost savings' is the most beneficial factor if the present barriers are removed. This study then proposed some relevant solutions to enhance the performance of production planning processes in VCI.
引用
收藏
页码:1 / 11
页数:11
相关论文
共 50 条
  • [21] Application of Last Planner System to Modular Offshore Wind Construction
    Lerche, Jon
    Neve, Hasse H.
    Ballard, Glenn
    Teizer, Jochen
    Wandahl, Soren
    Gross, Allan
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2020, 146 (11)
  • [22] Last planner system oriented to lean construction: A literature review
    Han, Mei-Gui
    Wang, Zhuo-Fu
    Jin, De-Zhi
    Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2012, 32 (04): : 721 - 730
  • [23] WORKFORCE INFORMATION DATABASE SYSTEM TO SUPPORT PRODUCTION PLANNING IN CONSTRUCTION PROJECTS
    Kim, Sang-Chul
    Kim, Yong-Woo
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2012, 18 (06) : 867 - 878
  • [24] BIM-based Last Planner System tool for improving construction project management
    Heigermoser, Daniel
    de Soto, Borja Garcia
    Abbott, Ernest Leslie Sidney
    Chua, David Kim Huat
    AUTOMATION IN CONSTRUCTION, 2019, 104 : 246 - 254
  • [25] Last Planner System Framework to Assess Planning Reliability in Architectural Design
    Shehab, Lynn
    Al Hattab, Malak
    Khalife, Salam
    El Samad, Ghali
    Abbas, Yara
    Hamzeh, Farook
    BUILDINGS, 2023, 13 (11)
  • [26] Key requirements of an IT tool based on last planner® system
    Cortes, M. J.
    Herrera, R. F.
    Munoz-La Rivera, F. C.
    Avila-Eca de Matos, B.
    REVISTA INGENIERIA DE CONSTRUCCION, 2020, 35 (02): : 126 - 134
  • [27] Predicting construction schedule performance with last planner system and machine learning
    Lagos, Camilo I.
    Herrera, Rodrigo F.
    Cawley, Alejandro F. Mac
    Alarcon, Luis F.
    AUTOMATION IN CONSTRUCTION, 2024, 167
  • [28] Development of Approach to Support Construction Stakeholders in Implementation of the Last Planner System
    Daniel, Emmanuel Itodo
    Pasquire, Christine
    Dickens, Graham
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2019, 35 (05)
  • [29] Adoption of the digitalised last planner system in infrastructure projects: an Australian case study
    Gao, Shang
    Chan, Toong-Khuan
    Hendy, Phil
    CONSTRUCTION INNOVATION-ENGLAND, 2023,
  • [30] Improving construction management practice with the Last Planner System: a case study
    AlSehaimi, Abdullah
    Fazenda, Patricia
    Koskela, Lauri
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2014, 21 (01) : 51 - +