Major overhaul of the Geesthacht Weir on the River Elbe

被引:1
|
作者
Luehr, Stefan [1 ]
Jaeppelt, Ulrich [2 ]
机构
[1] Wasserstrassen & Schifffahrtsamt Lauenburg, Dornhorster Weg 52, D-21481 Lauenburg, Germany
[2] WTM Engineers GmbH, Johannisbollwerk 6-8, D-20459 Hamburg, Germany
关键词
condition analysis; planning requirements; weir lock; stilling basin; overhaul of the solid structure;
D O I
10.1002/bate.201800025
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Geesthacht Weir is located some 140 km upstream from the mouth of the River Elbe, southwest of the town of Geesthacht. It was built between 1957 and 1960 as a four-section weir forming part of the dam at Geesthacht, each section measuring 50 m. The complex was designed for an envisaged dam at an upstream height of 5.65 m above sea level, and in addition to the weir there were originally also plans for the construction of a run-of-the-river power plant to the north of and adjacent to the fourth section of the weir. In the course of the planning approval process, the permissible upstream height of the dam was limited to 4.00 m above sea level, in other words 1.65 m lower than envisaged. As a result, the run-of-the-river power plant would have been uneconomical and was never built. Nowadays there is a fixed overflow sill where it would have stood. The weir's pillars provide the foundations for a road bridge where a main road, the Bundesstra beta e 404, crosses the River Elbe. Operation of the weir has led in some cases to considerable damage to the solid structure and the steel closing mechanisms. A major overhaul is necessary to ensure the durability and operational safety of the weir.
引用
收藏
页码:355 / 362
页数:8
相关论文
共 50 条
  • [21] New findings on the situation of the fish fauna of the Elbe in the area of the Geesthacht pumped-storage power plant
    Kühne, René
    WasserWirtschaft, 2016, 106 (12)
  • [22] Sediment retention in the floodplains of the river Elbe
    Krueger, Frank
    Scholz, Mathias
    Kreibich, Madlen
    Baborowski, Martina
    HYDROLOGIE UND WASSERBEWIRTSCHAFTUNG, 2015, 59 (06): : 380 - 395
  • [23] Xenoestrogens in the River Elbe and its tributaries
    Stachel, B
    Ehrhorn, U
    Heemken, OP
    Lepom, P
    Reincke, H
    Sawal, G
    Theobald, N
    ENVIRONMENTAL POLLUTION, 2003, 124 (03) : 497 - 507
  • [24] Reorganization - Dupont embarks on major overhaul
    Tullo, A
    CHEMICAL & ENGINEERING NEWS, 2002, 80 (07) : 9 - 9
  • [25] Pharmaceuticals in the river Elbe and its tributaries
    Wiegel, S
    Aulinger, A
    Brockmeyer, R
    Harms, H
    Löffler, J
    Reincke, H
    Schmidt, R
    Stachel, B
    von Tümpling, W
    Wanke, A
    CHEMOSPHERE, 2004, 57 (02) : 107 - 126
  • [26] CMA RECOMMENDS MAJOR OVERHAUL IN MEDICARE
    GEEKIE, D
    CANADIAN MEDICAL ASSOCIATION JOURNAL, 1981, 125 (04) : 380 - &
  • [27] The effects of nutrient concentrations in the, river Elbe
    Guhr, H
    Spott, D
    Bormki, G
    Baborowski, M
    Karrasch, B
    ACTA HYDROCHIMICA ET HYDROBIOLOGICA, 2004, 31 (4-5): : 282 - 296
  • [28] METAL POLLUTION IN THE TIDAL ELBE RIVER
    FORSTNER, U
    SCHOER, J
    KNAUTH, HD
    SCIENCE OF THE TOTAL ENVIRONMENT, 1990, 97-8 : 347 - 368
  • [29] Medicaid at 50: Time for a Major Overhaul
    Butler, Stuart M.
    JAMA-JOURNAL OF THE AMERICAN MEDICAL ASSOCIATION, 2015, 314 (04): : 326 - 329
  • [30] Decadal variability of the Elbe River streamflow
    Ionita, M.
    Rimbu, N.
    Lohmann, G.
    INTERNATIONAL JOURNAL OF CLIMATOLOGY, 2011, 31 (01) : 22 - 30