Critical factors affecting schedule performance: Evidence from Indian construction projects

被引:134
|
作者
Iyer, K. C.
Jha, K. N.
机构
[1] Indian Inst Technol, Dept Management Studies, New Delhi 110016, India
[2] Indian Inst Technol, Dept Civil Engn, New Delhi 110016, India
关键词
D O I
10.1061/(ASCE)0733-9364(2006)132:8(871)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Over 40% of Indian construction projects are facing time overrun ranging from I to 252 months; the reasons for which are being studied by researchers to suggest possible remedial measures. This paper identifies 55 attributes responsible for impacting performance of the projects. These attributes were then presented to Indian construction professionals in the form of a questionnaire. Statistical analysis of responses on the attributes segregated them into distinct sets of success attributes and failure attributes. Factor analysis of sets of success attributes and failure attributes separately grouped them into six critical success factors and seven critical failure factors. In order to understand the extent of contribution these factors have on the outcome of a construction project, a second stage questionnaire survey was also undertaken. The analyses of responses of the second stage questionnaire led us to conclude that two success factors and one failure factor: commitment of project participants; owner competence; and conflict among project participants contribute significantly in enhancement of current performance level of the project. The extent of their contribution has, however, been observed to vary for a given level of project performance. The analyses results are expected to help project professionals to focus on a few factors and get the optimum results rather than giving attention to all the factors and not getting the proportionate results.
引用
收藏
页码:871 / 881
页数:11
相关论文
共 50 条
  • [21] Prediction of schedule performance of Indian construction projects using an artificial neural network
    Jha, Kumar Neeraj
    Chockalingam, Ct
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2011, 29 (09) : 901 - 911
  • [22] Identifying the Critical Factors Affecting the Operational Performance of Characteristic Healthcare Town PPP Projects: Evidence from China
    Pan, Haize
    Pan, Yongwei
    Liu, Xing
    [J]. JOURNAL OF INFRASTRUCTURE SYSTEMS, 2023, 29 (04)
  • [23] Builders Perceptions on the Factors to be Monitored at Tendering and Mobilization Stage Affecting the Performance of South Indian Construction Projects
    Divakar K.
    [J]. Journal of The Institution of Engineers (India): Series A, 2019, 100 (01) : 33 - 39
  • [24] Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
    Larsen, Jesper Kranker
    Shen, Geoffrey Qiping
    Lindhard, Soren Munch
    Brunoe, Thomas Ditlev
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (01)
  • [25] Study of factors affecting the performance of construction projects in AEC industry
    Dixit, Saurav
    [J]. ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2020, 12 (01): : 2275 - 2282
  • [26] Factors Affecting Safety Performance of Construction Projects: A Literature Review
    Abas, N. H.
    Yusuf, N.
    Suhaini, N. A.
    Kariya, N.
    Mohammad, H.
    Hasmori, M. F.
    [J]. 2ND GLOBAL CONGRESS ON CONSTRUCTION, MATERIAL AND STRUCTURAL ENGINEERING, 2020, 713
  • [27] Structural equation model for investigating factors affecting delay in Indian construction projects
    Doloi, Hemanta
    Sawhney, Anil
    Iyer, K. C.
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2012, 30 (10) : 869 - 884
  • [28] Evaluation of Critical Factors Influencing Resource Allocation in Indian Construction Projects
    Venkatesh, M. P.
    Renuka, S. M.
    Malathi, Balasubramanian
    Umarani, C.
    [J]. ADVANCED BUILDING MATERIALS AND SUSTAINABLE ARCHITECTURE, PTS 1-4, 2012, 174-177 : 2774 - 2777
  • [29] Critical factors affecting the performance of large construction projects in developing countries A case study of Sri Lanka
    San Santoso, Djoen
    Gallage, Polwatta Gallage Madusha Piumal
    [J]. JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2019, 18 (03) : 531 - 556
  • [30] STUDY ON FACTORS AFFECTING THE PERFORMANCE OF CONSTRUCTION PROJECTS IN THE DEMOCRATIC REPUBLIC OF THE CONGO
    Bitamba, B. F.
    An, S. H.
    [J]. SOUTH AFRICAN JOURNAL OF INDUSTRIAL ENGINEERING, 2020, 31 (01) : 12 - 25