Tunnel spoil recycling for concrete production at the Brenner Base tunnel in Austria

被引:24
|
作者
Voit, Klaus [1 ]
Murr, Roland [2 ]
Cordes, Tobias [2 ]
Zeman, Oliver [3 ]
Bergmeister, Konrad [3 ]
机构
[1] Univ Nat Resources & Life Sci, Inst Appl Geol, Dept Civil Engn & Nat Hazards, Vienna, Austria
[2] Brenner Basistunnel BBT SE, Innsbruck, Austria
[3] Univ Nat Resources & Life Sci, Inst Struct Engn, Dept Civil Engn & Nat Hazards, Vienna, Austria
关键词
aggregate for concrete; aggregate substitute; Brenner Base tunnel; Bundner schists; calcareous schists; excavation material recycling; material management; quartz phyllite; tunnel spoil;
D O I
10.1002/suco.202000434
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the construction of major tunnel structures, large quantities of rock material are generated by the excavation of, for example, tunnels or caverns out of the in situ rock mass. Excavated rock material was often considered as undesired by-product and from a legal point of view as waste in the past. Nevertheless, there is the need for construction material at the tunnel construction site directly where the rock material is generated. Broad scientific research is conducted concerning the utilization possibilities and optimization of recycling implementation. This article deals with the recycling of tunnel excavation material substituting conventional aggregate for concrete by the example of the Brenner Base Tunnel in Austria. Concrete design, material processing, and concrete production were affected by challenging geological bedrock conditions. This article presents the scientific approach, experimental setup, verification, and the realization on the construction site. The way from preliminary mixing designs to the final product is illustrated for two main rock types: calcareous schists, which successfully were recycled and processed as aggregate for shotcrete, structural and inner lining concrete; and quartz phyllite with unsuitable rock properties for concrete production due to intense foliation and mica-rich mineral composition. The results are demonstrating the need for detailed examination of rock and concrete properties regarding the usability of tunnel excavation material.
引用
收藏
页码:2795 / 2809
页数:15
相关论文
共 50 条
  • [31] ENVIRONMENTAL OPTIMISATION OF SHOTCRETE APPLIED AT THE BRENNER BASE TUNNEL (BBT)
    Cordes, T.
    Gschoesser, F.
    Bergmeister, K.
    EXPANDING BOUNDARIES: SYSTEMS THINKING IN THE BUILT ENVIRONMENT, 2016, : 720 - 724
  • [32] Statistical and Geostatistical Analysis of Drilling Parameters in the Brenner Base Tunnel
    Daniela Boldini
    Roberto Bruno
    Harald Egger
    Daniele Stafisso
    Antonio Voza
    Rock Mechanics and Rock Engineering, 2018, 51 : 1955 - 1963
  • [33] Effects of the geometric position of the Brenner Base Tunnel on rock mass plastification and the tunnel's shotcrete shell
    Bergmeister, Konrad
    Weifner, Tassilo
    Collizzolli, Mara
    BETON- UND STAHLBETONBAU, 2012, 107 (11) : 735 - 748
  • [34] ATG Ceneri Base Tunnel: Driving method and production of concrete aggregates
    Catelli, E.
    Lanfranchi, P.
    PROCEEDINGS OF THE ITA-AITES WORLD TUNNEL CONGRESS 2023, WTC 2023: Expanding Underground-Knowledge and Passion to Make a Positive Impact on the World, 2023, : 14 - 22
  • [35] Aicha-Mauls on the Brenner base tunnel -status of the works and results
    Bergmeister, Konrad
    Facchin, Ezio
    Quick, Hubert
    Michael, Joachim
    Geomechanik und Tunnelbau, 2010, 3 (05): : 520 - 533
  • [36] BRENNER,ROBERT IN THE TUNNEL OF TIME
    BLAUT, JM
    ANTIPODE, 1994, 26 (04) : 351 - 374
  • [37] Planning optimisation for the Brenner Base Tunnel considering both maintenance and sustainability
    Planungsoptimierungen beim Brenner Basistunnel aus Sicht der Instandhaltung und Nachhaltigkeit
    1600, Ernst und Sohn (07):
  • [38] Tunnelling in complex geological structures during the construction of the Brenner Base Tunnel
    Marini, David
    Lussu, Andrea
    Hofmann, Matthias
    Venditti, Giuseppe
    Geomechanik und Tunnelbau, 2024, 17 (06): : 594 - 604
  • [39] Brenner Base Tunnel - description of the work and progress through the periadrial fault
    Zurlo, R.
    Rea, G.
    Roccia, M.
    GALLERIE E GRANDI OPERE SOTTERRANEE, 2014, (109): : 57 - 60
  • [40] 15 km TBM exploratory tunnel excavation in the construction Lot H33 of the Brenner Base Tunnel
    Lussu, Andrea
    Grüllich, Sebastian
    Kaiser, Christian
    Fontana, Adrian