Hybrid Approach of Constraint Programming and Integer Programming for Solving Resource-constrained Project-scheduling Problems

被引:0
|
作者
Cheng Zhao [1 ]
Murata, Tomohiro [1 ]
机构
[1] Waseda Univ, Grad Sch Informat Prod & Syst, Tokyo, Japan
关键词
Terms constraint programming (CP); cumulative resource problem (CRP); integer programming (IP); project scheduling problem (PSP); resource-constrained project scheduling problems (RCPSP);
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Resource constrained project scheduling problem (RCPSP) is a well known NP hard problem. This paper proposes a hybrid approach of constraint programming (CP) and integer programming (IP) which could solve RCPSP with ideal efficiency and quality. Constraint propagation is key element of constraint programming and is widely used in cumulative resource problem (CRP). CRP can be taken as a relaxed problem of RCPSP. This paper discussed how to eliminate the resource constraint, and transform RCPSP to project scheduling problem (PSP) so that the problem will became easier. Experiment shows this hybrid approach has certain efficient advantage compared with traditional CP method.
引用
收藏
页码:1574 / 1577
页数:4
相关论文
共 50 条
  • [1] A Constraint Integer Programming Approach for Resource-Constrained Project Scheduling
    Berthold, Timo
    Heinz, Stefan
    Luebbecke, Marco E.
    Moehring, Rolf H.
    Schulz, Jens
    [J]. INTEGRATION OF AI AND OR TECHNIQUES IN CONSTRAINT PROGRAMMING FOR COMBINATORIAL OPTIMIZATION PROBLEMS, 2010, 6140 : 313 - +
  • [2] A constraint programming approach for the resource-constrained project scheduling problem
    Liess, Olivier
    Michelon, Philippe
    [J]. ANNALS OF OPERATIONS RESEARCH, 2008, 157 (01) : 25 - 36
  • [3] A constraint programming approach for the resource-constrained project scheduling problem
    Olivier Liess
    Philippe Michelon
    [J]. Annals of Operations Research, 2008, 157 : 25 - 36
  • [4] A Hybrid Programming Framework for Resource-Constrained Scheduling Problems
    Sitek, Pawel
    Wikarek, Jaroslaw
    [J]. INTELLIGENT DATA ENGINEERING AND AUTOMATED LEARNING - IDEAL 2015, 2015, 9375 : 300 - 308
  • [5] Solving resource-constrained project scheduling problem with evolutionary programming
    Sebt, M. H.
    Alipouri, Y.
    Alipouri, Y.
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2013, 64 (09) : 1327 - 1335
  • [6] EFFICIENT INTEGER PROGRAMMING ALGORITHM WITH NETWORK CUTS FOR SOLVING RESOURCE-CONSTRAINED SCHEDULING PROBLEMS.
    Talbot, F.Brian
    Patterson, James H.
    [J]. Management Science, 1978, 24 (11) : 1163 - 1174
  • [7] A Comparative Study of Different Integer Linear Programming Approaches for Resource-Constrained Project Scheduling Problems
    Chakrabortty, Ripon K.
    Sarker, Ruhul
    Essam, Daryl L.
    [J]. DATA AND DECISION SCIENCES IN ACTION, 2018, : 227 - 242
  • [8] An integer programming approach to the multimode resource-constrained multiproject scheduling problem
    Túlio A. M. Toffolo
    Haroldo G. Santos
    Marco A. M. Carvalho
    Janniele A. Soares
    [J]. Journal of Scheduling, 2016, 19 : 295 - 307
  • [9] An integer programming approach to the multimode resource-constrained multiproject scheduling problem
    Toffolo, Tulio A. M.
    Santos, Haroldo G.
    Carvalho, Marco A. M.
    Soares, Janniele A.
    [J]. JOURNAL OF SCHEDULING, 2016, 19 (03) : 295 - 307
  • [10] A multiobjective resource-constrained project-scheduling problem
    Ben Abdelaziz, Fouad
    Krichen, Saoussen
    Dridi, Olfa
    [J]. SYMBOLIC AND QUANTITATIVE APPROACHES TO REASONING WITH UNCERTAINTY, PROCEEDINGS, 2007, 4724 : 719 - +