The paper presents a case history of a 5-storey building, seriously damaged during construction of a nearby structure. Founded on spread footings on soft clayey soil, the building was functional for nearly 30 years. When construction of an adjacent 4-storey RC building begun, its infill walls sustained shear failure. The shear cracks were inclined at 45 degrees, being characteristic of differential settlements, and the neighboring construction was deemed to be the cause of failure. During the present forensic investigation, additional cracks were detected, also inclined at 45 degrees but towards the opposite direction. Internal floor measurements were conducted, revealing that the maximum differential settlement of 5 cm is accompanied by 2.4 cm of differential settlement to the opposite direction. A number of construction defects were detected, with the most important being the superficial foundation of the building and the absence of tie beams. To quantify the contribution of each factor to the observed failure, the neighboring structures are simulated through finite elements, modeling nonlinear soil response with a Cam-clay model, validated against the conducted measurements. It is shown, that the shear failure of the infill walls is primarily due to construction defects, with the neighboring construction playing a secondary role. (C) 2013 Elsevier Ltd. All rights reserved.
引用
收藏
页码:252 / 267
页数:16
相关论文
共 50 条
  • [41] A circuit model of electrical wiring nearby building structure for lightning surge analysis
    Dei, Hideyuki
    Ikeda, Yoki
    Nagaoka, Naoto
    [J]. ELECTRICAL ENGINEERING IN JAPAN, 2024, 217 (01)
  • [42] Seismic design of diaphragm wall nearby building to minimize the differential displacement during an earthquake
    Saadi, Riadh
    Khennouf, Abdelaziz
    Baheddi, Mohamed
    [J]. INNOVATIVE INFRASTRUCTURE SOLUTIONS, 2024, 9 (05)
  • [43] Determining shark size from forensic analysis of bite damage
    Dayv Lowry
    Andrey Leonardo Fagundes de Castro
    Kyle Mara
    Lisa B. Whitenack
    Bryan Delius
    George H. Burgess
    Philip Motta
    [J]. Marine Biology, 2009, 156 : 2483 - 2492
  • [44] A Circuit Model of Electrical Wiring Nearby Building Structure for Lightning Surge Analysis
    Dei H.
    Ikeda Y.
    Nagaoka N.
    [J]. IEEJ Transactions on Power and Energy, 2023, 143 (11) : 593 - 600
  • [45] Analysis of the Influence of Lateral Deformation of Soft Soil Embankment on Nearby Building Foundation
    [J]. Chai, Chun-Yang, 1600, Editorial Department of Journal of Railway Engineering Society, China (34):
  • [46] FORENSIC TEXTILE DAMAGE ANALYSIS: PRACTICAL ISSUES AND METHODOLOGICAL PERSPECTIVES
    Romeo, Marco
    Salerno, Monica
    Casella, Filomena
    Colosimo, Federica
    Piscopo, Amalia
    Gentile, Claudio
    Feola, Alessandro
    Di Mizio, Giulio
    [J]. ROMANIAN JOURNAL OF LEGAL MEDICINE, 2021, 29 (01): : 65 - 68
  • [47] Determining shark size from forensic analysis of bite damage
    Lowry, Dayv
    Fagundes de Castro, Andrey Leonardo
    Mara, Kyle
    Whitenack, Lisa B.
    Delius, Bryan
    Burgess, George H.
    Motta, Philip
    [J]. MARINE BIOLOGY, 2009, 156 (12) : 2483 - 2492
  • [48] Building assessment and monitoring during the construction of an underground railway
    Forth, RA
    Thorley, CBB
    [J]. TUNNELS AND METROPOLISES, VOLS 1 AND 2, 1998, : 1181 - 1186
  • [49] POSSIBILITIES OF DIGITIZATION IN CONSTRUCTION DURING THE BUILDING LIFE CYCLE
    Skoda, Zbynek
    [J]. PROCEEDINGS OF THE 9TH BUSINESS & MANAGEMENT CONFERENCE, PRAGUE, 2019, : 94 - 102
  • [50] Integrated management of the construction project during the building phase
    Wu, Yun Na
    Yao, Na
    [J]. Proceedings of CRIOCM 2006 International Research Symposium on Advancement of Construction Management and Real Estate, Vols 1 and 2, 2006, : 184 - 190