Solving an Industrial Shop Scheduling Problem Using Genetic Algorithm

被引:2
|
作者
Moghadam, Ali Mokhtari [1 ]
Wong, Kuan Yew [1 ]
Piroozfard, Hamed [1 ]
Asl, Ali Derakhshan [1 ]
Hutajulu, Tiurmai Shanty
机构
[1] Univ Teknol Malaysia, Fac Mech Engn, Dept Mfg & Ind Engn, Utm Skudai 81310, Johor, Malaysia
关键词
Scheduling; genetic algorithm; industrial shop; flexible job shop; FLEXIBLE JOB-SHOP;
D O I
10.4028/www.scientific.net/AMR.845.564
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Spool fabrication shop is an intermediate phase in the piping process for construction projects. The delivery of pipe spools at the right time in order to be installed in the site is very important. Therefore, effective scheduling and controlling of the fabrication shop has a direct effect on the productivity and successfulness of the whole construction projects. In this paper, a genetic algorithm (GA) is developed to create an active schedule for the operational level of pipe spool fabrication. In the proposed algorithm, an enhanced solution coding is used to suitably represent a schedule for the fabrication shop. The initial population is generated randomly in the initialization stage and precedence preserving order-based crossover (PDX) and uniform crossover are used appropriately. In addition, different mutation operators are used. The proposed algorithm is applied with the collected data that consist of operations processing time from an industrial fabrication shop. The results showed that by using GA for scheduling the fabrication processes, the productivity of the spool fabrication shop has increased by 88 percent.
引用
收藏
页码:564 / 568
页数:5
相关论文
共 50 条
  • [31] A tabu search and a genetic algorithm for solving a bicriteria general job shop scheduling problem
    Vilcot, Geoffrey
    Billaut, Jean-Charles
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 190 (02) : 398 - 411
  • [32] A Genetic Algorithm for Solving Flexible Flow Shop Scheduling Problem with Autonomous Guided Vehicles
    Wang, Miao
    Xin, Bin
    [J]. 2019 IEEE 15TH INTERNATIONAL CONFERENCE ON CONTROL AND AUTOMATION (ICCA), 2019, : 922 - 927
  • [33] Flexible Job Shop Scheduling Problem Solving Based on Genetic Algorithm with Model Constraints
    Du, Xuan
    Li, Zongbin
    Xiong, Wei
    [J]. IEEM: 2008 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-3, 2008, : 1239 - 1243
  • [34] Utilization of modified genetic algorithm (GJOB) for solving classical job shop scheduling problem
    Perinic, M.
    Car, Z.
    Mikac, T.
    [J]. Annals of DAAAM for 2004 & Proceedings of the 15th International DAAAM Symposium: INTELLIGNET MANUFACTURING & AUTOMATION: GLOBALISATION - TECHNOLOGY - MEN - NATURE, 2004, : 341 - 342
  • [35] Solving the Reentrant Permutation Flow-Shop Scheduling Problem with a Hybrid Genetic Algorithm
    Chen, Jen Shiang
    Pan, Jason Chao Hsien
    Lin, Chien Min
    [J]. INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE, 2009, 16 (01): : 23 - 31
  • [36] Solving the Flow-Shop Scheduling problem using Grover's Algorithm
    Saiem, Malak
    Arbaoui, Taha
    Hnaien, Faicel
    [J]. PROCEEDINGS OF THE 2023 GENETIC AND EVOLUTIONARY COMPUTATION CONFERENCE COMPANION, GECCO 2023 COMPANION, 2023, : 2250 - 2253
  • [37] Solving the flexible job shop scheduling problem using an improved Jaya algorithm
    Caldeira, Rylan H.
    Gnanavelbabu, A.
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2019, 137
  • [38] Solving fuzzy flexible job shop scheduling problems using genetic algorithm
    Lei, De-Ming
    Guo, Xiu-Ping
    [J]. PROCEEDINGS OF 2008 INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND CYBERNETICS, VOLS 1-7, 2008, : 1014 - +
  • [39] Solving the Flexible Job Shop Scheduling Problem With Makespan Optimization by Using a Hybrid Taguchi-Genetic Algorithm
    Chang, Hao-Chin
    Chen, Yeh-Peng
    Liu, Tung-Kuan
    Chou, Jyh-Horng
    [J]. IEEE ACCESS, 2015, 3 : 1740 - 1754
  • [40] A new heuristic algorithm for solving the job shop scheduling problem
    Yin, Aihua
    Zhang, Shousheng
    [J]. COMPUTATION IN MODERN SCIENCE AND ENGINEERING VOL 2, PTS A AND B, 2007, 2 : 1412 - 1416