THE TIME-COST TRADE-OFF ANALYSIS IN CONSTRUCTION PROJECT USING COMPUTER SIMULATION AND INTERACTIVE PROCEDURE

被引:20
|
作者
Blaszczyk, Tomasz [1 ]
Nowak, Maciej [1 ]
机构
[1] Karol Adamiecki Univ Econ, Dept Operat Res, PL-40287 Katowice, Poland
关键词
project planning; multi-criteria decision aiding; time-cost trade-off; interactive approach; simulation; STOCHASTIC-DOMINANCE; ALGORITHM; NETWORKS; MODELS;
D O I
10.3846/1392-8619.2009.15.523-539
中图分类号
F [经济];
学科分类号
02 ;
摘要
Several criteria must be considered while preparing the schedule of a construction project. The completion time and project cost are analyzed in most cases. Additionally, the risk related to the criteria has to be taken into account as well. Thus, project planning problem can be defined as a multicriteria decision problem under risk. In this paper, a project scheduling problem including time-cost trade-offs is analyzed. We assume that various resource allocations can be considered. A new technique based on computer simulation and interactive approach is proposed. In the first step, simulation experiments are performed to evaluate decision alternatives with respect to the criteria. An interactive technique INSDECM is employed for generating the final solution of the problem. The procedure uses stochastic dominance rules for comparing decision alternatives with respect to the criteria. A numerical example is presented to illustrate the applicability of the technique.
引用
收藏
页码:523 / 539
页数:17
相关论文
共 50 条
  • [31] TIME-COST TRADE-OFF ANALYSIS IN SOME CONSTRAINED ASSIGNMENT PROBLEMS
    GEETHA, S
    VARTAK, MN
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1989, 40 (01) : 97 - 101
  • [32] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES
    REDA, R
    CARR, RI
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (03): : 475 - 486
  • [33] Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach
    Azaron, Amir
    Tavakkoli-Moghaddam, Reza
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 180 (03) : 1186 - 1200
  • [34] TIME-COST TRADE-OFF IN A SOLID TRANSPORTATION PROBLEM
    BHATIA, HL
    PURI, MC
    [J]. ZEITSCHRIFT FUR ANGEWANDTE MATHEMATIK UND MECHANIK, 1977, 57 (10): : 616 - 619
  • [35] Multiobjective Optimization of Time-Cost Trade-Off Using Harmony Search
    Geem, Zong Woo
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2010, 136 (06): : 711 - 716
  • [36] Time-cost trade-off in PERT networks using a genetic algorithm
    Azaron, A
    Perkgoz, C
    Kato, K
    Katagiri, H
    Sakawa, M
    [J]. 2004 47TH MIDWEST SYMPOSIUM ON CIRCUITS AND SYSTEMS, VOL III, CONFERENCE PROCEEDINGS, 2004, : 57 - 60
  • [37] Time-cost trade-off analysis of a priority based assignment problem
    Kaur, Prabhjot
    Dahiya, Kalpana
    Verma, Vanita
    [J]. OPSEARCH, 2021, 58 (02) : 448 - 482
  • [38] Time-cost trade-off analysis of a priority based assignment problem
    Prabhjot Kaur
    Kalpana Dahiya
    Vanita Verma
    [J]. OPSEARCH, 2021, 58 : 448 - 482
  • [39] A Microsoft Project add-in for time-cost trade off analysis
    Anagnostopoulos, KP
    Kotsikas, L
    Roumboutsos, A
    [J]. SYSTEM-BASED VISION FOR STRATEGIC AND CREATIVE DESIGN, VOLS 1-3, 2003, : 2209 - 2214
  • [40] Using machine learning and GA to solve time-cost trade-off problems
    Li, Heng
    Cao, J.-N.
    Love, P.E.D.
    [J]. Journal of Construction Engineering and Management, 125 (05): : 347 - 353