Experiment study on continuous commissioning a real VAV system

被引:0
|
作者
Wang, FL [1 ]
Yoshida, H [1 ]
Tsubaki, IMM [1 ]
Itou, K [1 ]
机构
[1] Kyoto Univ, Dept Urban & Environm Engn, Kyoto 6068501, Japan
关键词
automated continuous commissioning; variable air volume (VAV) systems; fault detection and diagnosis (FDD); experiment study;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In order to study the automated continuous commissioning characteristics of VAV systems, a set of experiments were conducted on a real VAV system in the office building of Yamatake Building System Company. Four types faults, which are top problems amenable to automated continuous commissioning, were introduced into the VAV system. The performance data of the VAV system were measured and automatically recorded once a minute using a data logger. From the experiment results, three conclusions can be drawn: 1) Automated continuous commissioning is feasible if simulation analysis and operation records are used for commissioning, and new simulation models suitable for continuous commissioning are need; 2) Operation records are useful for continuous commissioning sensors; 3) If the status of a component changes, the relevant variables, such as supply air volume, air temperature, pressure etc., do not change simultaneously. Some variables change several minutes late. This change delay should be taken into consideration during automated on-line commissioning.
引用
收藏
页码:959 / 966
页数:8
相关论文
共 50 条
  • [1] Improving energy efficiency with the various control sequences for a VAV system through continuous commissioning®
    Cho, Young-Hum
    Liu, Mingsheng
    [J]. INTERNATIONAL JOURNAL OF ENERGY RESEARCH, 2010, 34 (14) : 1291 - 1301
  • [2] Commissioning of the upgraded RICH system at the LHCb experiment
    Okamura, S.
    [J]. JOURNAL OF INSTRUMENTATION, 2022, 17 (11):
  • [3] Real time modelling for control system commissioning
    Besselink, M.A.
    Hoch, D.L.
    [J]. Australian Journal of Instrumentation and Control, 1992, 7 (04):
  • [4] Commissioning, recommissioning, retrocommissioning, and continuous commissioning
    Barich, Mark
    [J]. Engineered Systems, 2007, 24 (09): : 66 - 68
  • [5] Feasibility study of retrofitting VAV system to VAV-DOAS system for outdoor airflow requirement and distribution in multi-zone VAV system
    Zhao, Tianyi
    Wang, Jiaming
    Liu, Chao
    Zhao, Yu
    [J]. SCIENCE AND TECHNOLOGY FOR THE BUILT ENVIRONMENT, 2021, 27 (07) : 892 - 902
  • [6] Improving building energy system performance by continuous commissioning
    Liu, MS
    [J]. ENERGY ENGINEERING, 1999, 96 (05) : 46 - 57
  • [7] Improving building energy system performance by continuous commissioning
    Liu, MS
    Claridge, DE
    Haberl, JS
    Turner, WD
    [J]. IECEC-97 - PROCEEDINGS OF THE THIRTY-SECOND INTERSOCIETY ENERGY CONVERSION ENGINEERING CONFERENCE, VOLS 1-4: VOL.1: AEROSPACE POWER SYSTEMS AND TECHNOL; VOL 2: ELECTROCHEMICAL TECHNOL, CONVERSION TECHNOL, THERMAL MANAGEMENT; VOLS 3: ENERGY SYSTEMS, RENEWABLE ENERGY RESOURCES, ENVIRONMENTAL IMPACT, POLICY IMPACTS ON ENERGY; VOL 4: POST DEADLINE PAPERS, INDEX, 1997, : 1606 - 1612
  • [8] Commissioning the CMS experiment
    Camporesi, Tiziano
    [J]. ASTROPARTICLE, PARTICLE AND SPACE PHYSICS, DETECTORS AND MEDICAL PHYSICS APPLICATIONS, 2008, 4 : 424 - 435
  • [9] Lab experiment or commissioning?
    Ellis, Rebecca T.
    [J]. Engineered Systems, 2019, 36 (12):
  • [10] Commissioning of the GERDA experiment
    Lehnert, B.
    [J]. NEUTRINO PHYSICS AND ASTROPHYSICS, 2012, 182 : 309 - 313