Optimal segmentation of projects - Schedule and cost considerations

被引:3
|
作者
Shtub, A [1 ]
Raz, T
机构
[1] TEL AVIV UNIV, SCH ENGN, DEPT IND ENGN, IL-69978 TEL AVIV, ISRAEL
[2] LEON E RECANATI GRAD SCH BUSINESS ADM RAMAT AVIV, FAC MANAGEMENT, IL-69978 TEL AVIV, ISRAEL
关键词
project segmentation; project scheduling; project control; project planning;
D O I
10.1016/0377-2217(95)00260-X
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In certain types of projects, the same sequence of activities is performed throughout the various physical parts of the project (e.g., road construction). By dividing the project into segments and working in parallel, the duration of the project can be reduced, with a resulting increase in direct costs. in this paper we consider the problem of finding the optimal number of segments that minimizes total project cost, for linear cost and duration functions. We begin by formulating and solving a mathematical programming model for homogeneous projects, and, by using the concept of work contents, we extend the solution to non-homogeneous projects.
引用
收藏
页码:278 / 283
页数:6
相关论文
共 50 条
  • [1] Decision Tool for Selecting the Optimal Techniques for Cost and Schedule Reduction in Capital Projects
    Bayraktar, Mehmet Emre
    Hastak, Makarand
    Gokhale, Sanjiv
    Safi, Bhavin
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2011, 137 (09) : 645 - 655
  • [2] Cost, Change Order, and Schedule Performance of Highway Projects
    Shrestha, Bandana
    Shrestha, Pramen P.
    Maharjan, Ruiko
    Gransberg, Douglas
    [J]. JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2022, 14 (01)
  • [3] Analysis of cost and schedule performance of international development projects
    Ahsan, Kamrul
    Gunawan, Indra
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2010, 28 (01) : 68 - 78
  • [4] Reasons for cost and schedule increase for engineering design projects
    Chang, AST
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2002, 18 (01) : 29 - 36
  • [5] Determination of a cost optimal, predetermined maintenance schedule
    Thevik, HJ
    [J]. FORESIGHT AND PRECAUTION, VOLS 1 AND 2, 2000, : 249 - 255
  • [6] The Iron Triangle of Projects Management: Quality, Schedule and Cost of Road Infrastructure Projects in Egypt
    Abu El-Maaty, Ahmed
    Akal, Ahmed Yousry
    El-Hamrawy, Saad A.
    [J]. TOWARDS SUSTAINABLE CITIES IN ASIA AND THE MIDDLE EAST, 2018, : 1 - 14
  • [7] Cost and Schedule Monitoring of Industrial Building Projects: Case Study
    De Marco, Alberto
    Briccarello, Diego
    Rafele, Carlo
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2009, 135 (09): : 853 - 862
  • [8] Cost escalation and schedule delays in road construction projects in Zambia
    Kaliba, Chabota
    Muya, Mundia
    Mumba, Kanyuka
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (05) : 522 - 531
  • [9] An Empirical Analysis of Sources of Cost and Schedule Growth for Facilities Projects
    Shalwani, Amirali
    Lines, Brian
    Smithwick, Jake
    Dodd, Justin
    Kasana, Dipin
    [J]. CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 740 - 749
  • [10] Effect of project complexity on cost and schedule performance in transportation projects
    Nguyen, Long D.
    Long Le-Hoai
    Tran, Dai Q.
    Dang, Chau N.
    Nguyen, Chau V.
    [J]. CONSTRUCTION MANAGEMENT AND ECONOMICS, 2019, 37 (07) : 384 - 399