Management of rock bursts during excavation of the deep tunnels in Jinping II Hydropower Station

被引:84
|
作者
Shan, Zhi-gang [1 ]
Yan, Peng [1 ]
机构
[1] CHECC, E China Invest & Design Inst, Hangzhou 310014, Zhejiang, Peoples R China
关键词
Jinping II Hydropower Station; Deep-lying tunnel; High in situ stress breakage;
D O I
10.1007/s10064-010-0266-2
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Rock mass breakage induced by high in situ stresses during excavation of deep tunnels is one of the key problems in the construction of the Jinping II Hydropower Station. It is not only a threat to the safety of workers, but also seriously affects the construction process. This paper discusses where the rock bursts occur, how they occur and how to reduce their effect.
引用
收藏
页码:353 / 363
页数:11
相关论文
共 50 条
  • [1] Management of rock bursts during excavation of the deep tunnels in Jinping II Hydropower Station
    Zhi-gang Shan
    Peng Yan
    [J]. Bulletin of Engineering Geology and the Environment, 2010, 69 : 353 - 363
  • [2] Effect of excavation schemes of tbm on risk of rock burst of long tunnels at jinping ii hydropower station
    Wu, Shiyong
    Zhou, Jifang
    Chen, Bingrui
    Huang, Manbin
    [J]. Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering, 2015, 34 (04): : 728 - 734
  • [3] Rock mechanical problems and optimization for the long and deep diversion tunnels at Jinping II hydropower station
    Wu, Shiyong
    Wang, Ge
    [J]. JOURNAL OF ROCK MECHANICS AND GEOTECHNICAL ENGINEERING, 2011, 3 (04) : 314 - 328
  • [4] Rock burst and slabbing failure and its influence on TBM excavation at headrace tunnels in Jinping II hydropower station
    Gong, Q. M.
    Yin, L. J.
    Wu, S. Y.
    Zhao, J.
    Ting, Y.
    [J]. ENGINEERING GEOLOGY, 2012, 124 : 98 - 108
  • [5] Excavation damaged zone characteristics in deep tunnel of Jinping II hydropower station
    [J]. Liu, N. (liu_n@ecidi.com), 1600, Academia Sinica (32):
  • [7] Microseismic Monitoring of Energy Changes in Deep Tunnels during the TBM Tunneling of the Jinping II Hydropower Station
    Zhuang, Duanyang
    Ma, Ke
    Tang, Chunan
    Liang, Zhengzhao
    Wang, Zhenwei
    [J]. ADVANCES IN CIVIL ENGINEERING, 2018, 2018
  • [8] Microseismic Monitoring of Strainburst Activities in Deep Tunnels at the Jinping II Hydropower Station, China
    N. W. Xu
    T. B. Li
    F. Dai
    R. Zhang
    C. A. Tang
    L. X. Tang
    [J]. Rock Mechanics and Rock Engineering, 2016, 49 : 981 - 1000
  • [9] Microseismic Monitoring of Strainburst Activities in Deep Tunnels at the Jinping II Hydropower Station, China
    Xu, N. W.
    Li, T. B.
    Dai, F.
    Zhang, R.
    Tang, C. A.
    Tang, L. X.
    [J]. ROCK MECHANICS AND ROCK ENGINEERING, 2016, 49 (03) : 981 - 1000
  • [10] Characteristics of Microseismicity during Breakthrough in Deep Tunnels: Case Study of Jinping-II Hydropower Station in China
    Feng, Guang-Liang
    Feng, Xia-Ting
    Chen, Bing-Rui
    Xiao, Ya-Xun
    Liu, Guo-Feng
    Zhang, Wei
    Hu, Lei
    [J]. INTERNATIONAL JOURNAL OF GEOMECHANICS, 2020, 20 (02)