FUZZY MULTI-OBJECTIVE RELIABILITY-REDUNDANCY ALLOCATION PROBLEM

被引:0
|
作者
Ashraf, Zubair [1 ]
Muhuri, Pranab K. [1 ]
Lohani, Q. M. Danish [1 ]
Nath, Rahul [1 ]
机构
[1] South Asian Univ, Fac Math & Comp Sci, New Delhi 110021, India
关键词
Reliability; Redundancy; Reliability-Redundancy Allocation Problem; NSGA-II; Fuzzy Reliability; Fuzzy Cost; OPTIMIZATION PROBLEMS;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Reliability is the measure of the result of the quality of the system over a long run. The reliability-redundancy allocation problem (RRAP) aims to ensure high systems reliability in the presence of optimally redundant systems components. This is one of the most important design considerations for the systems designers. Several researchers have addressed this important issue during last few decades. However, due to the embedded uncertainty in the parameters of the system components, reliability as well as the costs of the whole system fits very well to be modeled as fuzzy quantity. We therefore modeled this problem as a fuzzy multi-objective optimization problem (MORRAP) that is addressed using the popular multi-objective evolutionary algorithm, NSGA-II (non-dominated sorting genetic algorithm-II). We have considered the based MORRAP with fuzzy type-2 uncertainty. As far as we know, no research has been reported where MORRAP was considered under type-2 fuzzy uncertainty. A typical numerical example is included and results are compared showing that our approach outperforms other recently reported results.
引用
收藏
页码:2580 / 2587
页数:8
相关论文
共 50 条
  • [1] A multi-objective reliability-redundancy allocation problem with active redundancy and interval type-2 fuzzy parameters
    Pradip Kundu
    [J]. Operational Research, 2021, 21 : 2433 - 2458
  • [2] A multi-objective reliability-redundancy allocation problem with active redundancy and interval type-2 fuzzy parameters
    Kundu, Pradip
    [J]. OPERATIONAL RESEARCH, 2021, 21 (04) : 2433 - 2458
  • [3] Multi-objective reliability-redundancy allocation problem using particle swarm optimization
    Garg, Harish
    Sharma, S. P.
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2013, 64 (01) : 247 - 255
  • [4] Multi-objective optimization of reliability-redundancy allocation problem for multi-type production systems considering redundancy strategies
    Wang, Wei
    Lin, Mingqiang
    Fu, Yongnian
    Luo, Xiaoping
    Chen, Hanghang
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2020, 193
  • [5] Application of multi-objective particle swarm optimization to solve a fuzzy multi-objective reliability redundancy allocation problem
    Ebrahimipour, V.
    Sheikhalishahi, M.
    [J]. 2011 IEEE INTERNATIONAL SYSTEMS CONFERENCE (SYSCON 2011), 2011, : 326 - 333
  • [6] Multi-objective System Reliability-redundancy Allocation in a Power Plant by Considering Three Targets
    Chebouba, Billal Nazim
    Mellal, Mohamed Arezki
    Adjerid, Smail
    Lounici, Yacine
    [J]. 2020 7TH INTERNATIONAL CONFERENCE ON CONTROL, DECISION AND INFORMATION TECHNOLOGIES (CODIT'20), VOL 1, 2020, : 674 - 678
  • [7] Fuzzy reliability-redundancy allocation problem of the overspeed protection system
    Taghiyeh, Sajjad
    Mahmoudi, Morteza
    Fadaie, Saber
    Tohidi, Hossein
    [J]. ENGINEERING REPORTS, 2020, 2 (08)
  • [8] Multi-objective optimization of reliability-redundancy allocation problem with cold-standby strategy using NSGA-II
    Ardakan, Mostafa Abouei
    Rezvan, Mohammad Taghi
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2018, 172 : 225 - 238
  • [9] RELIABILITY-REDUNDANCY ALLOCATION PROBLEM OF PHARMACEUTICAL PLANT
    Garg, Harish
    Sharma, S. P.
    [J]. JOURNAL OF ENGINEERING SCIENCE AND TECHNOLOGY, 2013, 8 (02): : 190 - 198
  • [10] Brain Storm Optimization Algorithm in Objective Space for Reliability-Redundancy Allocation Problem
    Nath, Rahul
    Rauniyar, Amit
    Muhuri, Pranab K.
    [J]. 2019 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC), 2019, : 248 - 253