Real-time scheduling of multi-stage flexible job shop floor

被引:24
|
作者
Ham, Myoungsoo [1 ]
Lee, Young Hoon [2 ]
Kim, Sun Hoon [2 ]
机构
[1] Samsung Austin Semicond, Syst Engn, Austin, TX USA
[2] Yonsei Univ, Dept Informat & Ind Engn, Seoul 120749, South Korea
关键词
job shop; integer programming; multi-stage; optimisation; real-time; scheduling; BATCH PLANTS; FORMULATION; ALGORITHMS; MACHINES; MODELS; SYSTEM;
D O I
10.1080/00207543.2010.492797
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper first formulates a binary integer programming (BIP) model that minimises Cmax for a multi-stage flexible job shop floor with machine compatibility. Due to a computational limitation, the exact optimal model is then relaxed as a linear programming model. The output from the relaxation model then turns into the objective of the BIP-based real-time scheduling (RTS) heuristic model. The RTS heuristic requires an iteration to calculate the final Cmax. At each iteration, the RTS heuristic assigns just one job to the earliest available machines. Since the set of jobs and machines included in the RTS model is relatively small, RTS can be solved in a very short computational time. We evaluate an overall effectiveness (in terms of solution quality and run time) of the RTS heuristic by way of computer experiments.
引用
收藏
页码:3715 / 3730
页数:16
相关论文
共 50 条
  • [21] MULTI OBJECTIVE FLEXIBLE JOB SHOP SCHEDULING PROBLEMS
    Kaya, Serkan
    Figlali, Nilgun
    SIGMA JOURNAL OF ENGINEERING AND NATURAL SCIENCES-SIGMA MUHENDISLIK VE FEN BILIMLERI DERGISI, 2013, 31 (04): : 605 - 623
  • [22] RUNNING A JOB SHOP IN REAL-TIME
    不详
    INFOSYSTEMS, 1978, 25 (02): : 102 - &
  • [23] Real-Time Scheduling for Dynamic Partial-No-Wait Multiobjective Flexible Job Shop by Deep Reinforcement Learning
    Luo, Shu
    Zhang, Linxuan
    Fan, Yushun
    IEEE TRANSACTIONS ON AUTOMATION SCIENCE AND ENGINEERING, 2022, 19 (04) : 3020 - 3038
  • [24] Real-Time Scheduling for Flexible Job Shop With AGVs Using Multiagent Reinforcement Learning and Efficient Action Decoding
    Li, Yuxin
    Wang, Qingzheng
    Li, Xinyu
    Gao, Liang
    Fu, Ling
    Yu, Yanbin
    Zhou, Wei
    IEEE TRANSACTIONS ON SYSTEMS MAN CYBERNETICS-SYSTEMS, 2025, 55 (03): : 2120 - 2132
  • [25] Optimal Fixed Priority Scheduling in Multi-Stage Multi-Resource Distributed Real-Time Systems
    Kumar, Niraj
    Gao, Chuanchao
    Easwaran, Arvind
    2024 DESIGN, AUTOMATION & TEST IN EUROPE CONFERENCE & EXHIBITION, DATE, 2024,
  • [26] Heuristics for dynamic job shop scheduling with real-time updated queueing time estimates
    Chang, FCR
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (03) : 651 - 665
  • [27] Multi-level job scheduling in a flexible job shop environment
    Na, Hongbum
    Park, Jinwoo
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2014, 52 (13) : 3877 - 3887
  • [28] Flexible job shop scheduling with multi-level job structures
    Jang, YJ
    Kim, KD
    Jang, SY
    Park, J
    JSME INTERNATIONAL JOURNAL SERIES C-MECHANICAL SYSTEMS MACHINE ELEMENTS AND MANUFACTURING, 2003, 46 (01) : 33 - 38
  • [29] Scheduling in a flexible job shop with continuous operations at the last stage
    Zhang, T.
    Rose, O.
    JOURNAL OF SIMULATION, 2016, 10 (02) : 80 - 88
  • [30] Scheduling in a Flexible Job Shop with Continuous Operations at the Last Stage
    Zhang, Tao
    Rose, Oliver
    SIMULATION IN PRODUKTION UND LOGISTK 2013, 2013, 316 : 611 - 620