A branch and bound algorithm for the resource-constrained project scheduling problem

被引:177
|
作者
Brucker, P [1 ]
Knust, S [1 ]
Schoo, A [1 ]
Thiele, O [1 ]
机构
[1] Univ Osnabruck, Fachbereich Math Informat, D-49069 Osnabruck, Germany
关键词
branch and bound method; immediate selection; resource-constrained project scheduling problem; disjunctive graph model;
D O I
10.1016/S0377-2217(97)00335-4
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
A branch and bound algorithm is presented for the resource-constrained project scheduling problem (RCPSP). Given are n activities which have to be processed without preemptions. During the processing period of an activity constant amounts of renewable resources are needed where the available capacity of each resource type is limited. Furthermore, finish-start precedence relations between the activities are given. The objective is to determine a schedule with minimal makespan. The branching scheme starts from a graph representing a set of conjunctions (the classical finish-start precedence constraints) and disjunctions (induced by the resource constraints). Then it either introduces disjunctive constraints between pairs of activities or places these activities in parallel. Concepts of immediate selection are developed in connection with this branching scheme. Immediate Selection allows to add conjunctions as well as further disjunctions and parallelity relations. Computational results based on the test data of Kolisch ct al. (Kolisch, R., Sprecher, A., Drexl. A., 1995. Management Science 41, 1693-1703.) and Kolisch and Sprecher (Kolisch, R., Sprecher, A., 1997. PSPLIB - A project scheduling problem library, EJOR 96, pp. 205-216.) are reported. (C) 1998 Elsevier Science B.V. All rights reserved.
引用
收藏
页码:272 / 288
页数:17