A crashing-based time-cost trade-off model considering quality cost and contract clauses

被引:5
|
作者
Akin, Firat Dogu [1 ]
Polat, Gul [1 ]
Turkoglu, Harun [1 ]
Damci, Atilla [1 ]
机构
[1] Istanbul Tech Univ, Dept Civil Engn, Div Construct Management, Istanbul, Turkey
关键词
Contract clauses; project crashing; quality cost; scheduling; time-cost trade-off; PARTICLE SWARM OPTIMIZATION; PROJECT-MANAGEMENT; GENETIC ALGORITHM; DISCRETE-TIME; CONSTRUCTION PROJECTS; RISK;
D O I
10.1080/15623599.2021.1946899
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The success of a construction project is often evaluated by time, cost, and quality performances, which are interdependent. Shortening the project duration does not only increase the direct cost but also affects the project's quality cost positively or negatively. In addition, the contract clauses in terms of penalty cost and early finish bonus have a significant impact on project duration and cost. This study proposes a crashing-based model, which simultaneously considers quality cost and contract clauses, to solve time-cost trade-off problems. The applicability of the proposed model is demonstrated with an illustrative example. The results of the proposed model were also compared with the results of two meta-heuristic algorithms, namely Particle Swarm Optimization (PSO) and Genetic Algorithm (GA), in order to validate the effectiveness of the model. The results revealed that the proposed model provides better solutions than these algorithms in terms of total project cost corresponding to different durations.
引用
收藏
页码:954 / 963
页数:10
相关论文
共 50 条
  • [1] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    [J]. JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222
  • [2] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    [J]. PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [3] Integrating Quality and Safety in Construction Scheduling Time-Cost Trade-Off Model
    Panwar, Abhilasha
    Jha, Kumar Neeraj
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (02)
  • [4] New Time-Cost Trade-Off Model Considering the Sequence of Alternatives Between Activities
    Kang, Namuk
    Son, Jaeho
    Lee, Seunghyun
    [J]. JOURNAL OF ASIAN ARCHITECTURE AND BUILDING ENGINEERING, 2015, 14 (02) : 379 - 386
  • [5] A New Idea to LP Model for Time-cost Trade-off in Networks
    ZHAO Guohao
    JING Shentu and ZHANG Yaguang(Scanxi Institute of Economic Management
    [J]. Journal of Systems Science and Systems Engineering, 1995, (03) : 250 - 255
  • [6] Stochastic construction time-cost trade-off analysis
    Feng, CW
    Liu, L
    Burns, SA
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) : 117 - 126
  • [7] A GENERALIZED TIME-COST TRADE-OFF TRANSPORTATION PROBLEM
    PRASAD, VR
    NAIR, KPK
    ANEJA, YP
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1993, 44 (12) : 1243 - 1248
  • [8] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES
    REDA, R
    CARR, RI
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (03): : 475 - 486
  • [9] AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY
    Lin, Chien-Liang
    Lai, Yu-Che
    [J]. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2020, 26 (02) : 113 - 130
  • [10] TIME-COST TRADE-OFF IN A SOLID TRANSPORTATION PROBLEM
    BHATIA, HL
    PURI, MC
    [J]. ZEITSCHRIFT FUR ANGEWANDTE MATHEMATIK UND MECHANIK, 1977, 57 (10): : 616 - 619