Robust Optimization Based Heuristic Approach for Solving Stochastic Multi-Mode Resource Constrained Project Scheduling Problem

被引:0
|
作者
Chakrabortty, R. K. [1 ]
Ryan, M. J. [1 ]
机构
[1] UNSW Canberra, Capabil Syst Ctr, Sch Engn & IT, Canberra, ACT, Australia
关键词
Multi-mode RCPSPs; Stochastic MRCPSP; Robust Optimization; Uncertain activity duration; Heuristic; SEARCH; MODEL;
D O I
10.1109/ieem45057.2020.9309878
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
To deal with uncertain or stochastic durations in a Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem (SMRCPSP), this paper proposes a robust optimization (RO) approach, which is claimed as the second research work in this similar research paradigm. When compared with the only other available approach in the literature, the applicability and uniqueness of the proposed RO approach are clearly demonstrated by the solution methodology and uncertainty considerations. Depending on different uncertainty characteristics of stochastic durations, different deterministic constraints or equivalent counterparts are generated in a RO framework, which is later solved by an updated modified variable neighbourhood search heuristic (MVNSH). Several standard instances and a real-life case study are solved to demonstrate the efficacy of the proposed solution approach. After a careful observation among different uncertainty types, several key strategical decision points are also highlighted for managerial implications.
引用
收藏
页码:1157 / 1161
页数:5
相关论文
共 50 条
  • [1] A robust optimization approach for the multi-mode resource-constrained project scheduling problem
    Balouka, Noemie
    Cohen, Izack
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2021, 291 (02) : 457 - 470
  • [2] A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
    Roslon, Jerzy Hubert
    Kulejewski, Janusz Edward
    [J]. OPEN ENGINEERING, 2019, 9 (01): : 7 - 13
  • [3] Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with SMT
    Bofill, Miquel
    Coll, Jordi
    Suy, Josep
    Villaret, Mateu
    [J]. 2016 IEEE 28TH INTERNATIONAL CONFERENCE ON TOOLS WITH ARTIFICIAL INTELLIGENCE (ICTAI 2016), 2016, : 239 - 246
  • [4] A matheuristic approach to the multi-mode resource constrained project scheduling problem
    Fernandes, Gustavo Alves
    de Souza, Sergio Ricardo
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2021, 162
  • [5] A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem
    Bold, Matthew
    Goerigk, Marc
    [J]. OPERATIONS RESEARCH LETTERS, 2022, 50 (05) : 581 - 587
  • [6] Solving the multi-mode resource-constrained project scheduling problem with genetic algorithms
    Alcaraz, J
    Maroto, C
    Ruiz, R
    [J]. JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2003, 54 (06) : 614 - 626
  • [7] Estimation of distribution algorithm for solving the multi-mode resource constrained project scheduling problem
    Mahdi, Gaafar Sadeq S.
    Quintana, Julio Madera
    Pérez, Pedro Piñero
    Al-Subhi, Salah Hassan
    [J]. EAI Endorsed Transactions on Energy Web, 2020, 7 (27)
  • [8] Resource-constrained project scheduling: a heuristic for the multi-mode case
    Heilmann, R
    [J]. OR SPEKTRUM, 2001, 23 (03): : 335 - 357
  • [9] A MODIFIED MODELING APPROACH AND A HEURISTIC PROCEDURE FOR THE MULTI-MODE RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM WITH ACTIVITY SPLITTING
    Faghih-Mohammadi, Fatemeh
    Seifi, Abbas
    Khalighi-Sikaroudi, Mohammad
    [J]. RAIRO-OPERATIONS RESEARCH, 2016, 50 (01) : 91 - 118
  • [10] A HYBRID META-HEURISTIC ALGORITHM FOR MULTI-MODE RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
    Fu, Fang
    Zhou, Hong
    [J]. ICIM 2008: PROCEEDINGS OF THE NINTH INTERNATIONAL CONFERENCE ON INDUSTRIAL MANAGEMENT, 2008, : 145 - 150