Failure Mechanism of Primary Support for a Shallow and Asymmetrically Loaded Tunnel Portal and Treatment Measures

被引:32
|
作者
Yang, Chao [1 ]
Hu, Zhangxin [1 ]
Huang, Da [2 ]
Guo, Fei [3 ]
机构
[1] China Three Gorges Univ, Key Lab Geol Hazards Three Gorges Reservoir Area, Minist Educ, Yichang 443002, Peoples R China
[2] Hebei Univ Technol, Sch Civil & Transportat Engn, Tianjin 300401, Peoples R China
[3] China Three Gorges Univ, Hubei Key Lab Disaster Prevent & Mitigat, Yichang 443002, Peoples R China
基金
中国国家自然科学基金;
关键词
Shallow and asymmetrically loaded tunnel; Primary support; Failure mechanism; Treatment measures; MODEL TEST; SURROUNDING ROCK; BIAS TUNNELS; INVESTIGATE; PRESSURE;
D O I
10.1061/(ASCE)CF.1943-5509.0001385
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Shallow and asymmetrically loaded tunnels are very common in mountain tunnel portals, and localized excessive deformation, cracking, or even collapse often occur during the construction process. In this study, a shallow and asymmetrically loaded tunnel entrance is used as an example to discuss the primary support failure mechanism by means of field observations and monitoring and three-dimensional (3D) numerical simulation. Asymmetrical loading, rainfall, and mismanagement were the three main triggers of failure events. The continuous rainfall infiltration significantly reduced the quality of the surrounding rock, resulting in an increase in the initially high asymmetrical loading. The retaining wall and surrounding rock failed to provide sufficient counterpressure on the shallowly buried side, leading to large deformation of the primary support at the beginning of excavation. The deformation increased continuously and quickly exceeded the allowable value; however, the project was not stopped in time, and further excavation occurred due to a communication failure between the monitoring and construction crews. Thus, severe damage to the primary support occurred when the tunnel face reached a distance of 24 m from the entrance. To avoid more hazardous damage, a temporary support mainly composed of 20b I-steel was installed immediately to prevent deformation; 30 days later, a cutting slope was created on the deeply buried side to reduce the asymmetrical loading, and the excavated rock mass was stacked at the shallow buried side to increase the counterpressure. Then, the temporary support was removed, and a secondary lining was applied in a timely fashion. The monitoring data showed that good results had been achieved. This study provides useful recommendations for the construction safety of shallow and asymmetrically loaded tunnel portals. (C) 2019 American Society of Civil Engineers.
引用
收藏
页数:13
相关论文
共 50 条
  • [31] Model research on failure mechanism and lining stress characteristics of shallow buried tunnel under unsymmetrical pressure
    Lei, Mingfeng
    Peng, Limin
    Shi, Chenghua
    Wang, Lichuan
    Liu, Zhengchu
    Shi, C. (csusch@163.com), 1600, Central South University of Technology (44): : 3316 - 3325
  • [32] Study on failure mechanism and treatment measures of floor heave of high-speed railway tunnel in the interbedded surrounding rock with high geostress
    Feng, Jiaqi
    Gong, Lun
    Wang, Lichuan
    Zhou, Ping
    Zhang, Peng
    Li, Yang
    Liu, Zhiqiang
    ENGINEERING FAILURE ANALYSIS, 2023, 150
  • [33] Deformation mechanism and collapse treatment of the rock surrounding a shallow tunnel based on on-site monitoring
    Hong-zhi Qiu
    Xiao-qing Chen
    Qi-hong Wu
    Ren-chao Wang
    Wan-yu Zhao
    Ke-jiang Qian
    Journal of Mountain Science, 2020, 17 : 2897 - 2914
  • [34] Deformation mechanism and collapse treatment of the rock surrounding a shallow tunnel based on on-site monitoring
    QIU Hong-zhi
    CHEN Xiao-qing
    WU Qi-hong
    WANG Ren-chao
    ZHAO Wan-yu
    QIAN Ke-jiang
    Journal of Mountain Science, 2020, 17 (12) : 2897 - 2914
  • [35] Deformation mechanism and collapse treatment of the rock surrounding a shallow tunnel based on on-site monitoring
    Qiu Hong-zhi
    Chen Xiao-qing
    Wu Qi-hong
    Wang Ren-chao
    Zhao Wan-yu
    Qian Ke-jiang
    JOURNAL OF MOUNTAIN SCIENCE, 2020, 17 (12) : 2897 - 2914
  • [36] Deformation and failure mechanism and support measures of the soft rock roadway in the air return laneway
    Yang, Xiao-Jie
    Pang, Jie-Wen
    Zhang, Bao-Tong
    Meng, Fan-Yi
    Jiang, Wen-Feng
    Fan, Li-Peng
    Niu, Xiang
    Meitan Xuebao/Journal of the China Coal Society, 2014, 39 (06): : 1000 - 1008
  • [37] Type Selection of Arches in Primary Support of Loess Tunnel with Small Interval under Shallow Buried & Unsymmetrical Pressure
    Su, Zhongming
    Wang, Xiaofeng
    Liu, Rui
    PROGRESS IN CIVIL ENGINEERING, PTS 1-4, 2012, 170-173 : 1656 - 1659
  • [38] REINFORCEMENT MECHANISM AND MECHANICAL ANALYSIS FOR PIPE ROOF SUPPORT USED IN SUBWAY STATION WITH SHALLOW TUNNEL CONSTRUCTION METHOD
    Zhao, Yanfa
    Zhou, Peng
    Xie, Gaohong
    KEY TECHNOLOGIES OF RAILWAY ENGINEERING - HIGH SPEED RAILWAY, HEAVY HAUL RAILWAY AND URBAN RAIL TRANSIT, 2010, : 842 - 847
  • [39] Support mechanism and effect analysis of an umbrella arch in a super shallow-buried large-span tunnel
    Zhao, Jinpeng
    Tan, Zhongsheng
    Liang, Wenguang
    Gao, Junpeng
    Tumu Gongcheng Xuebao/China Civil Engineering Journal, 2021, 54 : 87 - 96
  • [40] Reinforcement mechanism and mechanical analysis for pipe roof support used in subway station with shallow tunnel construction method
    Guo, Yan-Jing
    Fang, Qian
    Li, Bing
    Beijing Gongye Daxue Xuebao / Journal of Beijing University of Technology, 2010, 36 (01): : 40 - 45