摘要
Shutdown probabilistic safety assessment is a method for assessment and improvement of nuclear power plant safety for the periods of their shutdown. It is developed similarly as the power probabilistic safety assessment with several similarities and some differences representing the realistic plant behavior within the safety models. The method is developed and starts with definition of representative plant operating states. For each of representative plant operating states, which have different durations, separate model is prepared. The model preparation includes: definition and analysis of initiating events, accident sequence development analysis, success criteria analysis, system analysis, human reliability analysis, parameter estimation analysis, quantification and results interpretation. Each model for each plant operating state can consider either one or more sets of initiating event sets such as internal events, fires, floods, earthquakes and other external events. The results for every plant operating state are obtained by evaluation of the respective model. The results have been obtained for all plant operating states and they show the risks related with respective plant operating states. Their comparison with the results of plant full power operation show reduced and identifies the plant operating states with larger and smaller risks in terms of core damage frequency, which is selected as the main risk measure.
引用
收藏
页码:723 / 727
页数:5
相关论文
共 50 条
  • [31] ADVANCES IN PROBABILISTIC SAFETY ASSESSMENT
    APOSTOLAKIS, G
    KAFKA, P
    NUCLEAR ENGINEERING AND DESIGN, 1992, 134 (01) : 141 - 148
  • [32] UNCERTAINTY IN PROBABILISTIC SAFETY ASSESSMENT
    APOSTOLAKIS, GE
    NUCLEAR ENGINEERING AND DESIGN, 1989, 115 (01) : 173 - 179
  • [33] JEM probabilistic safety assessment
    Fukatsu, T
    Takeuchi, N
    Seike, T
    Oga, K
    Sato, Y
    PROBABILISTIC SAFETY ASSESSMENT AND MANAGEMENT, VOL I AND II, PROCEEDINGS, 2002, : 949 - 955
  • [34] Probabilistic safety assessment of components
    Roos, E.
    Wackenhut, G.
    Lammert, R.
    Schuler, X.
    INTERNATIONAL JOURNAL OF PRESSURE VESSELS AND PIPING, 2011, 88 (01) : 19 - 25
  • [35] LIVING PROBABILISTIC SAFETY ASSESSMENT
    BALFANZ, HP
    BOHME, E
    FUHRMANN, C
    MUSEKAMP, W
    RUMPF, J
    KERNTECHNIK, 1995, 60 (2-3) : 110 - 116
  • [36] WWER-1000 shutdown probabilistic risk assessment: An introductory insight
    Hadavi, S. Mohammad Hadi
    ANNALS OF NUCLEAR ENERGY, 2008, 35 (02) : 196 - 208
  • [37] Neural network method for probabilistic safety assessment of flawed weld structures
    He, L
    Chen, GH
    ENVIRONMENT EFFECTS ON FRACTURE AND DAMAGE, 2004, : 273 - 277
  • [38] Seismic probabilistic safety assessment based on probability density evolution method
    Ning, Chaolie
    Tongji Daxue Xuebao/Journal of Tongji University, 2015, 43 (03): : 325 - 331
  • [39] Probabilistic safety assessment method for spent nuclear fuel road transportation
    Tao, Longlong
    Wang, Jin
    Long, Pengcheng
    Wang, Dagui
    Wang, Fang
    Zhou, Baichang
    Chen, Jun
    ANNALS OF NUCLEAR ENERGY, 2020, 137
  • [40] Probabilistic Safety Assessment of the French PWR 900 MWe series - Results and insights
    Corenwinder, F
    Bertrand, V
    Dupuy, P
    Gomane, C
    Mattei, JM
    Pichereau, F
    PROBABILISTIC SAFETY ASSESSMENT AND MANAGEMENT, VOL I AND II, PROCEEDINGS, 2002, : 1 - 5