A Case Study on the Application of the Steel Tube Slab Structure in Construction of a Subway Station

被引:45
|
作者
Jia, Peng-jiao [1 ,2 ]
Zhao, Wen [1 ]
Chen, Yang [1 ]
Li, Shen-gang [1 ]
Han, Jian-yong [1 ]
Dong, Jia-chao [1 ]
机构
[1] Northeastern Univ, Sch Resources & Civil Engn, Shenyang 110819, Liaoning, Peoples R China
[2] Univ New South Wales, Sch Civil & Environm Engn, Sydney, NSW 2052, Australia
来源
APPLIED SCIENCES-BASEL | 2018年 / 8卷 / 09期
基金
中国国家自然科学基金;
关键词
large span underground spaces; Steel Tube Slab structure; excavation sequence; ground settlement; structural deformation; BEAM-ARCH METHOD; METRO STATION; TUNNEL; ROOF; EXCAVATION;
D O I
10.3390/app8091437
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
It is an effective approach to use Steel Tube Slab (STS) structure combined with the Pile-Beam-Arch (PBA) method to construct a large-space underground station. Traditional construction methods cannot meet the requirement of construction because of the complicated soil layers and high building densities in urban areas. The STS method can effectively increase the rigidity of the supporting system by using steel tubes. Firstly, the stress of bolts and steel tubes are investigated in the construction process based on the field monitoring data. Subsequently, FLAC3D is used to establish a three-dimensional model, which is verified based on the in-situ monitoring data; the effect of excavation process on ground settlement, deformation of STS structure and bridge pile are studied by numerical results. Moreover, the key parameters such as welding of flanges and the step length are studied. The results show that the stress of the steel tubes and flanges does not exceed the designed strength during the construction process. Based on the numerical simulation data, it is indicated that the STS structure can be a very effective and dependable measure in controlling and reducing the surface settlement and the existing adjacent buildings. The numerical results can be used to guide the later construction.
引用
收藏
页数:29
相关论文
共 50 条
  • [41] Study on Settlement and Deformation of Urban Viaduct Caused by Subway Station Construction under Complicated Conditions
    Luo, Cong-shuang
    Cheng, Yi-hong
    Bai, Zhe
    Shen, Tong
    Wu, Xu-Yang
    Wang, Qing-guo
    ADVANCES IN CIVIL ENGINEERING, 2021, 2021
  • [42] Study on Application of CSG Cofferdam in Hydropower Station Construction
    Peng, Yunfeng
    He, Yunlong
    2009 ASIA-PACIFIC POWER AND ENERGY ENGINEERING CONFERENCE (APPEEC), VOLS 1-7, 2009, : 44 - 47
  • [43] BIM Application and practice with Rhino -A Case Study of Steel Construction in Datong Library
    Li, Huiyong
    Du, Shubo
    Sha, Zhihui
    ADVANCED BUILDING MATERIALS AND SUSTAINABLE ARCHITECTURE, PTS 1-4, 2012, 174-177 : 2052 - 2056
  • [44] Analysis of the Influence of Subway Construction on Urban Development: A Case Study of Changzhou
    Xia, Xiaohan
    Han, Wenjun
    CICTP 2020: ADVANCED TRANSPORTATION TECHNOLOGIES AND DEVELOPMENT-ENHANCING CONNECTIONS, 2020, : 2882 - 2890
  • [45] Experimental study on punching shear failure of flat slab structure with steel column and steel capital in RC slab
    Yamashita Y.
    Ohta Y.
    Journal of Structural and Construction Engineering, 2020, 85 (768): : 299 - 309
  • [46] Study on seismic performance of beam-column-slab interior joints in cross section of assembled monolithic subway station
    Du, Xiuli
    Liu, Hongtao
    Xu, Chengshun
    Jin, Liu
    Luo, Furong
    Li, Songmei
    Jianzhu Jiegou Xuebao/Journal of Building Structures, 2019, 40 (08): : 51 - 60
  • [47] Study on seismic performance of beam-column-slab interior joints in longitudinal section of assembled monolithic subway station
    Du X.
    Liu H.
    Xu C.
    Jin L.
    Luo F.
    Li S.
    Jianzhu Jiegou Xuebao/Journal of Building Structures, 2019, 40 (09): : 95 - 103
  • [48] Standardization Study of Assembly Floor Slab in Steel Frame Structure
    Wang, Yabo
    Dou, Gaofeng
    Xi, Chuanhao
    Qian, Lei
    Liu, Hanting
    Progress in Industrial and Civil Engineering III, Pt 1, 2014, 638-640 : 244 - 249
  • [49] Experimental investigation on cooling load caused by unorganized ventilation in subway station: A case study
    Wang, Jiewei
    Yin, Yusheng
    Wei, Ziqing
    Zhai, Xiaoqiang
    ENERGY AND BUILDINGS, 2024, 320
  • [50] A Case Study on Stratified Settlement and Rebound Characteristics due to Dewatering in Shanghai Subway Station
    Wang, Jianxiu
    Huang, Tianrong
    Sui, Dongchang
    SCIENTIFIC WORLD JOURNAL, 2013,