MODELLING AND SIMULATION OF A MULTI-RESOURCE FLEXIBLE JOB-SHOP SCHEDULING

被引:5
|
作者
Ba, L. [1 ]
Li, Y. [1 ]
Yang, M. S. [1 ]
Gao, X. Q. [1 ]
Liu, Y. [1 ]
机构
[1] Xian Univ Technol, Sch Mech & Precis Instrument Engn, Xian 710048, Shanxi, Peoples R China
关键词
Multi-Resource; Scheduling; Genetic Algorithm; ALGORITHM;
D O I
10.2507/IJSIMM15(1)CO3
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Flexible job-shop scheduling problem (FJSP) in the field of production scheduling presents a quite difficult combinatorial optimization problem. Machines are mostly considered to be the only resource in many research projects dealing with FJSP. In actual production, there are many other factors which influence production scheduling, such as transportation, storage and detection. If machines are considered to be the only resource, the problem may not be in accord with the actual production. Thus, in order to make FJSP more in line with the real production situation, machines, warehouses, vehicles and detection equipment are all considered to be the scheduled resources simultaneously due to the shortage of flexible job shop scheduling problem in resources. A new mathematical model for a multi-resource flexible job-shop scheduling problem (MRFJSP) is proposed. The constraints of the model are presented. The makespan is the main target which will be minimized. A genetic algorithm which includes elitist strategy is proposed to solve the MRFJSP. Due to the complexity of MRFJSP, each key module of the genetic algorithm is redesigned. Finally, the model and algorithm are proved through an application case.
引用
收藏
页码:157 / 169
页数:13
相关论文
共 50 条
  • [21] AN IMPROVED GENETIC ALGORITHM FOR RESOURCE-CONSTRAINED FLEXIBLE JOB-SHOP SCHEDULING
    Wei, F. F.
    Cao, C. Y.
    Zhang, H. P.
    [J]. INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2021, 20 (01) : 201 - 211
  • [22] Modelling and solving a practical flexible job-shop scheduling problem with blocking constraints
    Mati, Yazid
    Lahlou, Chams
    Dauzere-Peres, Stephane
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2011, 49 (08) : 2169 - 2182
  • [23] A general efficient neighborhood structure framework for the job-shop and flexible job-shop scheduling problems
    Tamssaouet, Karim
    Dauzere-Peres, Stephane
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2023, 311 (02) : 455 - 471
  • [24] Flexible job-shop scheduling optimization with dynamic resource and job batch-size constraints
    Zhou, Yaqin
    Lyu, Youlong
    Zheng, Peng
    Zhang, Jie
    [J]. Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2020, 26 (05): : 1257 - 1267
  • [25] Robust scheduling for multi-objective flexible job-shop problems with flexible workdays
    Zhang, Jiae
    Yang, Jianjun
    Zhou, Yong
    [J]. ENGINEERING OPTIMIZATION, 2016, 48 (11) : 1973 - 1989
  • [26] MULTI-OBJECTIVE SCHEDULING SIMULATION OF FLEXIBLE JOB-SHOP BASED ON MULTI-POPULATION GENETIC ALGORITHM
    Zhang, W.
    Wen, J. B.
    Zhu, Y. C.
    Hu, Y.
    [J]. INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2017, 16 (02) : 313 - 321
  • [27] GASP SIMULATION STUDY OF JOB-SHOP SCHEDULING
    ASHOUR, S
    VASWANI, SD
    [J]. SIMULATION, 1972, 18 (01) : 1 - &
  • [28] OPTIMIZATION ALGORITHM SIMULATION FOR DUAL-RESOURCE CONSTRAINED JOB-SHOP SCHEDULING
    Zhong, Q.
    Yang, H.
    Tang, T.
    [J]. INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2018, 17 (01) : 147 - 158
  • [29] JOB-SHOP SCHEDULING
    NEW, C
    [J]. DATA PROCESSING, 1974, 16 (02): : 100 - 102
  • [30] Disruption Management of Multi-objective Flexible Job-Shop Scheduling Problem
    Sun, Jinghua
    Xu, Li
    [J]. PROCEEDINGS OF 2019 IEEE 7TH INTERNATIONAL CONFERENCE ON COMPUTER SCIENCE AND NETWORK TECHNOLOGY (ICCSNT 2019), 2019, : 98 - 102