IMPROVED EIGHT-PROCESS MODEL OF PRECAST COMPONENT PRODUCTION SCHEDULING CONSIDERING RESOURCE CONSTRAINTS

被引:8
|
作者
Ruan, Minhao [1 ]
Xu, Feng [1 ]
机构
[1] Shanghai Jiao Tong Univ, Sch Naval Architecture Ocean & Civil Engn, Shanghai Key Lab Digital Maintenance Bldg & Infra, Shanghai, Peoples R China
关键词
production scheduling; precast concrete components; production resource constraints; enterprise decision-making; transportation scheme; genetic algorithm; MULTIPLE PRODUCTION; DEMAND VARIABILITY; CONSTRUCTION; FABRICATION; LINES;
D O I
10.3846/jcem.2022.16454
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Reasonable production scheduling plays a vital role in the production of precast component factories. However, previous static scheduling models no longer fit actual production. In particular, some factors will cause errors in the actual delivery time of the components, including the lack or redundancy of processes in the model, resource constraints required by the core processes, and differences in transportation schemes. Moreover, the optimization goal of simply pursuing the minimization of fines from order delivery underestimates companies' emphases on reputation. Therefore, this study proposes an improved model for precast component production scheduling considering resource constraints. The number of production processes is adjusted to eight, and three resource constraints for mold, steel, and concrete are added. An enterprise decision-making coefficient is introduced into the optimization object function, and the constraints of the transportation scheme are improved. Finally, a real case study is conducted to verify the applicability of the model. Compared with previous models, the developed model fills the gap in considering production resource constraints and enterprise decisions in precast production, can better meet diverse production conditions and business needs of factories for scheduling, and help give full play to the advantages of prefabricated construction.
引用
收藏
页码:208 / 222
页数:15
相关论文
共 50 条
  • [1] Multi-objective optimization for production scheduling of precast components considering resource constraints
    Qin, Xuan
    Fang, Zihan
    Zhang, Zhaoxin
    [J]. Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2021, 27 (08): : 2248 - 2259
  • [2] Improved Precast Production-Scheduling Model Considering the Whole Supply Chain
    Wang, Zhaojing
    Hu, Hao
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (04)
  • [3] An Improved Production Scheduling Algorithm based on Resource Constraints
    Gao, Yan
    Zhang, Xin
    Xu, Jianzhong
    [J]. MECHANICAL MATERIALS AND MANUFACTURING ENGINEERING III, 2014, 455 : 619 - +
  • [4] Optimized flowshop scheduling for precast production considering process connection and blocking
    Dan, Yiran
    Liu, Guiwen
    Fu, Yan
    [J]. AUTOMATION IN CONSTRUCTION, 2021, 125
  • [5] Optimization model and algorithm of modular garment production process scheduling with resource constraints
    Yan, Weixiong
    Hu, Jueliang
    Han, Shuguang
    [J]. Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2024, 30 (06): : 2148 - 2158
  • [6] A Ga-based model for maximizing precast plant production under resource constraints
    Leu, SS
    Hwang, ST
    [J]. ENGINEERING OPTIMIZATION, 2001, 33 (05) : 619 - 642
  • [7] Process scheduling of precast production using genetic algorithms
    Chan, WT
    Hu, H
    [J]. OPTIMIZATION AND CONTROL IN CIVIL AND STRUCTURAL ENGINEERING, 1999, : 25 - 33
  • [8] Business Process Scheduling with Resource Availability Constraints
    Xu, Jiajie
    Liu, Chengfei
    Zhao, Xiaohui
    Yongchareon, Sira
    [J]. ON THE MOVE TO MEANINGFUL INTERNET SYSTEMS: OTM 2010, PT I, 2010, 6426 : 419 - +
  • [9] An Improved Computer-Aided Process Planning Method Considering Production Scheduling
    Morinaga, Eiji
    Charoenlarpkul, Nattapoom
    Wakamatsu, Hidefumi
    Arai, Eiji
    [J]. ADVANCES IN PRODUCTION MANAGEMENT SYSTEMS: INITIATIVES FOR A SUSTAINABLE WORLD, 2016, 488 : 178 - 186
  • [10] Integrated resource allocation and production scheduling for parallel concrete precast production lines
    Xiong, Fu-Li
    Zhang, Xing
    Cao, Jin-Song
    Yuan, Zi-Yang
    Chu, Meng-Ling
    Du, Yao
    [J]. Kongzhi yu Juece/Control and Decision, 2022, 37 (09): : 2399 - 2406