Study of Schedule Risk for Resource-Constrained Project Based on Improved PERT

被引:0
|
作者
Zhang Yun-ning [1 ]
Sun Xixi [1 ]
机构
[1] Hohai Univ, Sch Business, Project Management, Nanjing 210098, Peoples R China
关键词
schedule risk; PERT; schedule-resource optimization; 0-1 integer program; particle swarm;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Resource availability is limited in most situations.How to schedule under the condition of resource constraints is one of the most complicated subjects in project management field. Based on the views of risk management, this paper uses 0-1 integer programming techniques to establish the schedule-resource optimization model. At the first stage, it demonstrates the advantages of improved PERT model: firstly, the application of Moore method can improve the conventional distribution method of parameters of project activities; secondly, it improves the accuracy of the calculation by applying the restrictive portion of three point estimators method and the formula of expectation and variance for activity times; thirdly, it has considered the impact of non-critical line on key lines. At the second stage, this paper applies the particle swarm algorithm for solving 0-1 integer programming model by using the tool of MATLAB. Then, according to the project duration, the paper caculates the project schedule risk. Finally, a case study is used to demonstrate the model proposed.
引用
收藏
页码:1333 / 1337
页数:5
相关论文
共 50 条
  • [1] Optimized resource-constrained method for project schedule compression
    Elkabalawy, Moaaz
    Moselhi, Osama
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (05) : 2106 - 2129
  • [2] Construction Schedule Management Using Resource-Constrained Project Scheduling Model
    Wang J.
    Zeng S.
    Ju J.
    Tongji Daxue Xuebao/Journal of Tongji University, 2017, 45 (10): : 1561 - 1568
  • [3] Integrating Schedule Risk Analysis with Multi-Skilled Resource Scheduling to Improve Resource-Constrained Project Scheduling Problems
    Isah, Muritala Adebayo
    Kim, Byung-Soo
    APPLIED SCIENCES-BASEL, 2021, 11 (02): : 1 - 16
  • [4] Improved Compact Models for the Resource-Constrained Project Scheduling Problem
    Tesch, Alexander
    OPERATIONS RESEARCH PROCEEDINGS 2016, 2018, : 25 - 30
  • [5] Improved ACO Algorithm for Resource-Constrained Project Scheduling Problem
    Zhou, Yumiao
    Guo, Qingshun
    Gan, Rongwei
    2009 INTERNATIONAL CONFERENCE ON ARTIFICIAL INTELLIGENCE AND COMPUTATIONAL INTELLIGENCE, VOL III, PROCEEDINGS, 2009, : 358 - 365
  • [6] An improved PSO algorithm for resource-constrained project scheduling problem
    Luo, Xinggang
    Wang, Dingwei
    Tang, Jianfu
    Tu, Yiliu
    WCICA 2006: SIXTH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION, VOLS 1-12, CONFERENCE PROCEEDINGS, 2006, : 3514 - +
  • [7] A POLARIZED ADAPTIVE SCHEDULE GENERATION SCHEME FOR THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM
    Zamani, Reza
    RAIRO-OPERATIONS RESEARCH, 2012, 46 (01) : 23 - 39
  • [8] An improved particle swarm optimization for the resource-constrained project scheduling problem
    Jia, Qiong
    Seo, Yoonho
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 67 (9-12): : 2627 - 2638
  • [9] An improved particle swarm optimization for the resource-constrained project scheduling problem
    Qiong Jia
    Yoonho Seo
    The International Journal of Advanced Manufacturing Technology, 2013, 67 : 2627 - 2638
  • [10] Improved differential evolution algorithm for resource-constrained project scheduling problem
    Lianghong Wu1
    2.College of Electrical and Information Engineering
    JournalofSystemsEngineeringandElectronics, 2010, 21 (05) : 798 - 805