The impact of project planning team experience on software project cost estimates

被引:4
|
作者
McDonald, J [1 ]
机构
[1] Monmouth Univ, W Long Branch, Monmouth Jct, NJ USA
关键词
project management; project planning; project cost estimation; software engineering;
D O I
10.1007/s10664-004-6192-9
中图分类号
TP31 [计算机软件];
学科分类号
081202 ; 0835 ;
摘要
Data from 135 teams that have participated in a software project planning exercise are analyzed to determine the relationship between team experience and each learn's estimate of total project cost. The analysis shows that cost estimates are dependent upon two kinds of learn experience: (I) the average experience for the members of each team and (2) whether or not any members of the team have similar project experience. It is shown that if no members of a planning team have had similar project experience then the estimate of cost is correlated with average team experience, with teams having greater average team experience producing higher total cost estimates. If at least one member of the planning team has had similiar project experience then there is a weaker relationship between average learn experience and cost, and cost estimates produced by those teams with similar project experience are close to those produced by teams with the greatest average team experience. A qualitative examination of the project plans produced by all teams indicates that the primary reasons that teams with less experience of either type produce lower cost estimates are that they have failed to include sonic tasks that are included by more experienced teams, and that they have estimated shorter task durations than have the more experienced teams.
引用
收藏
页码:219 / 234
页数:16
相关论文
共 50 条
  • [11] Effect of team diversity on software project performance
    Liang, Ting-Peng
    Liu, Chih-Chung
    Lin, Tse-Min
    Lin, Binshan
    [J]. INDUSTRIAL MANAGEMENT & DATA SYSTEMS, 2007, 107 (5-6) : 636 - 653
  • [12] Managing embedded software project team knowledge
    Kettunen, P.
    [J]. IEE Proceedings: Software, 2003, 150 (06): : 359 - 366
  • [13] LABS JOIN CRAY TEAM IN SOFTWARE PROJECT
    HUGHES, D
    [J]. AVIATION WEEK & SPACE TECHNOLOGY, 1994, 140 (25): : 55 - +
  • [14] Software Engineering Team Project lessons learned
    Hnatkowska, Bogumila
    [J]. E-INFORMATICA SOFTWARE ENGINEERING JOURNAL, 2013, 7 (01) : 77 - 85
  • [15] Team Composition in Software Engineering Project Courses
    Dzvonyar, Dora
    Alperowitz, Lukas
    Henze, Dominic
    Bruegge, Bernd
    [J]. 2018 IEEE/ACM INTERNATIONAL WORKSHOP ON SOFTWARE ENGINEERING EDUCATION FOR MILLENNIALS (SEEM), 2018, : 16 - 23
  • [16] The impact of a project organisational culture and team rewarding on project performance
    Stare, Aljaz
    [J]. JOURNAL FOR EAST EUROPEAN MANAGEMENT STUDIES, 2012, 17 (01): : 40 - 67
  • [17] Planning and scheduling for the teams of the software project
    Zhou, Gang
    Jiang, Yunfei
    Sun, Sujun
    [J]. Journal of Information and Computational Science, 2004, 1 (03): : 459 - 464
  • [18] Software Project Planning Using Agile
    Han, Jianchao
    Ma, Yan
    [J]. PROGRESS IN SYSTEMS ENGINEERING, 2015, 366 : 333 - 338
  • [19] A FORMALISM FOR STRUCTURED PLANNING OF A SOFTWARE PROJECT
    CIMITILE, A
    VISAGGIO, G
    [J]. INTERNATIONAL JOURNAL OF SOFTWARE ENGINEERING AND KNOWLEDGE ENGINEERING, 1994, 4 (02) : 277 - 300
  • [20] Cost Estimates, Cost Overruns, and Project Continuation Decisions
    Bruggen, Alexander