ASSESSMENT OF CHANGE ORDER IMPACT FACTORS ON CONSTRUCTION PROJECT PERFORMANCE USING ANALYTIC HIERARCHY PROCESS (AHP)

被引:11
|
作者
Gunduz, Murat [1 ]
Mohammad, Khaled Omar [1 ]
机构
[1] Qatar Univ, Dept Civil Engn, POB 2713, Doha, Qatar
关键词
change orders; construction industry; analytic hierarchy process; relative importance index; PRODUCTIVITY;
D O I
10.3846/tede.2019.11262
中图分类号
F [经济];
学科分类号
02 ;
摘要
Complexity is very high in construction project and constrained by money and time. Change orders are commonly required during the execution of construction projects. They may increase, omit or adjust tasks in the project. Change orders affect the performance of construction job because they disturb current jobs and affect their schedule. The motive behind this study is to outline a complete assessment on change orders impacts. A review on past studies was performed to capture change order factors that affect project performance. Literature review and interviews with the industry professionals were used to finalize the factors into 16 critical factors. A questionnaire was distributed to industry specialists to capture the effect of these 16 factors on project performance. Complete answers of 102 surveys were received. Analytic Hierarchy Process (AHP) and Relative Important Index (RII) were utilized to analyze the responses. This study differs from other past studies by studying change order impact factors on three different change order types namely additional, omission and substitutional works. The most important change orders impacts factors as per the analysis outcomes are increased project management efforts, increased project replanning, loss of efficiency due to work interruption, increased reworks/demolition works and delay of payments. This paper would help construction professionals to recognize change order impacts and would assist them in taking proactive actions to limit these impacts.
引用
收藏
页码:71 / 85
页数:15
相关论文
共 50 条
  • [1] Comparison of Analytic Hierarchy Process (AHP) and Fuzzy Analytic Hierarchy Process (f-AHP) for the Sustainability Assessment of a Water Supply Project
    Natarajan N.
    Vasudevan M.
    Dineshkumar S.K.
    Anuja R.
    [J]. Journal of The Institution of Engineers (India): Series A, 2022, 103 (04) : 1029 - 1039
  • [2] Factors Affecting Students' Academic Performance Using Analytic Hierarchy Process (AHP)
    Baharin, Mardhiah
    Ismail, Wan Rosmanira
    Ahmad, Rokiah Rozita
    Majid, Noriza
    [J]. 2015 INTERNATIONAL CONFERENCE ON RESEARCH AND EDUCATION IN MATHEMATICS (ICREM7), 2015, : 169 - 173
  • [3] PIPELINE RISK ASSESSMENT USING ANALYTIC HIERARCHY PROCESS (AHP)
    Yasseri, Sirous F.
    Mahani, R. B.
    [J]. OMAE2011: PROCEEDINGS OF THE ASME 30TH INTERNATIONAL CONFERENCE ON OCEAN, OFFSHORE AND ARCTIC ENGINEERING, VOL 4: PIPELINE AND RISER TECHNOLOGY, 2011, : 1 - +
  • [4] PROJECT RISK ASSESSMENT USING THE ANALYTIC HIERARCHY PROCESS
    MUSTAFA, MA
    ALBAHAR, JF
    [J]. IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, 1991, 38 (01) : 46 - 52
  • [5] Construction of a credit evaluation model using Analytic Hierarchy Process (AHP)
    Analitik Hiyerars¸i Süreci
    [J]. Iç, Y.T. (tanselic@yahoo.com), 2000, Gazi Universitesi Muhendislik-Mimarlik (15): : 1 - 2
  • [6] Analytic hierarchy process (AHP) assessment of Kuwait mega construction projects' complexity
    AlKheder, Sharaf
    Al Otaibi, Hajar
    Al Baghli, Zahra
    Al Ajmi, Shaikhah
    Alkhedher, Mohammad
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023,
  • [7] Review of application of analytic hierarchy process (AHP) in construction
    Darko, Amos
    Chan, Albert Ping Chuen
    Ameyaw, Ernest Effah
    Owusu, Emmanuel Kingsford
    Parn, Erika
    Edwards, David John
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, 19 (05) : 436 - 452
  • [8] Assessment of flood hazard based on natural and anthropogenic factors using analytic hierarchy process (AHP)
    Stefanidis, Stefanos
    Stathis, Dimitrios
    [J]. NATURAL HAZARDS, 2013, 68 (02) : 569 - 585
  • [9] Assessment of flood hazard based on natural and anthropogenic factors using analytic hierarchy process (AHP)
    Stefanos Stefanidis
    Dimitrios Stathis
    [J]. Natural Hazards, 2013, 68 : 569 - 585
  • [10] Safety risk assessment using analytic hierarchy process (AHP) during planning and budgeting of construction projects
    Aminbakhsh, Saman
    Gunduz, Murat
    Sonmez, Rifat
    [J]. JOURNAL OF SAFETY RESEARCH, 2013, 46 : 99 - 105