AN OBSERVATIONAL STUDY OF THE PRODUCTIVITY OF FORMWORK IN BUILDING CONSTRUCTION

被引:0
|
作者
Mine, Naoto [1 ]
Wai, Soon Han [1 ]
Lim, Ting Chuan [1 ]
机构
[1] Univ Tunku Abdul Rahman, Dept Construct Management, Petaling Jaya, Malaysia
关键词
Reinforced concrete construction; Productivity; Work study; Work process; Process analysis; Man-hours; Unit requirement;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Formwork is one of the essential elements of construction work in traditional reinforced concrete building construction. In addition to being complicated work, formwork is labor intensive and requires numerous, highly-skilled formwork carpenters. Labor accounts to over 50% of the cost of formwork, a large percentage relative to other types of basic construction work. To increase formwork efficiency, it is necessary to improve work methods. While productivity of formwork has been the focus of previous studies, effective work data such as detailed work processes or man-hours were not sufficiently obtained. This paper reports on an observational study carried out on fifteen building construction projects using work-study techniques, specifically work processes, man-hours, and number of workers in each work process. It highlights the process analyses of a typical formwork construction project and discusses the results of a statistical analysis of labor productivity related to all construction projects.
引用
收藏
页码:1127 / 1132
页数:6
相关论文
共 50 条
  • [1] Development of a formwork labor productivity forecast model for the Brazilian building construction
    de Araújo, LOC
    de Souza, UEL
    Freire, T
    CONSTRUCTION INNOVATION AND GLOBAL COMPETITIVENESS, VOLS 1 AND 2: THE ORGANIZATION AND MANAGEMENT OF CONSTRUCTION, 2003, : 1415 - 1428
  • [2] Predicting labour productivity for formwork activities in high-rise building construction: a case study
    Bhilwade V.
    Delhi V.S.K.
    Nanthagopalan P.
    Das A.K.
    Modi K.
    Asian Journal of Civil Engineering, 2023, 24 (4) : 959 - 968
  • [3] MEASUREMENT OF CONSTRUCTION LABOR PRODUCTIVITY FOR FORMWORK OF THE HIGH-RISE BUILDING PROJECT
    Phong Thanh Nguyen
    Phuong Thanh Phan
    Phu-Cuong Nguyen
    Ngoc Bich Vu
    Loan Phuc Le
    JOURNAL OF MECHANICS OF CONTINUA AND MATHEMATICAL SCIENCES, 2019, 14 (02): : 112 - 120
  • [4] Advanced planning model of formwork layout for productivity improvement in high-rise building construction
    Lee, Dongmin
    Lim, Hyunsu
    Kim, Taehoon
    Cho, Hunhee
    Kang, Kyung-In
    AUTOMATION IN CONSTRUCTION, 2018, 85 : 232 - 240
  • [5] Analysis of Formwork System Selection Criteria for Building Construction Projects: A Comparative Study
    Terzioglu, Taylan
    Polat, Gul
    Turkoglu, Harun
    BUILDINGS, 2021, 11 (12)
  • [6] Buildability factors affecting formwork labour productivity of building floors
    Jarkas, Abdulaziz M.
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2010, 37 (10) : 1383 - 1394
  • [7] State of Development of Formwork and Scaffolding in Building Construction and Construction Engineering.
    Petzschmann, Eberhard
    1600, (19):
  • [8] Development of formwork automation design software for improving construction productivity
    Lee, Bokyeong
    Choi, Hyeonggil
    Min, Byongwang
    Ryu, Jungrim
    Lee, Dong-Eun
    AUTOMATION IN CONSTRUCTION, 2021, 126
  • [9] LABOR PRODUCTIVITY IN BUILDING CONSTRUCTION
    JAQUITH, LC
    AACE BULLETIN, 1970, 12 (02): : 46 - &
  • [10] Planning gang formwork operations for building construction using simulations
    Huang, RY
    Chen, JJ
    Sun, KS
    AUTOMATION IN CONSTRUCTION, 2004, 13 (06) : 765 - 779