Experimental and Numerical Investigation on the Behaviour of Prestressed High Strength Concrete Pile-to-pile Cap Connections

被引:13
|
作者
Yang, Zhijian [1 ]
Wang, Wenjin [2 ]
机构
[1] Shenyang Jianzhu Univ, Sch Civil Engn, Shenyang 110168, Peoples R China
[2] Tianjin Univ, Sch Civil Engn, Tianjin 300072, Peoples R China
关键词
PHC piles; pile-cap connections; hysteretic behaviour; energy dissipation; seismic performance; SEISMIC PERFORMANCE; DECK CONNECTIONS; PRECAST;
D O I
10.1007/s12205-015-0658-8
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Six Prestressed High Strength Concrete (PHC) pile-to-pile cap connections were tested to evaluate their damage process and failure modes under low cyclic loading. The hysteretic behaviour, rotation angle, ductility and bearing capacity were observed and analyzed. In addition, the effect of connecting forms and cutting-off piles on seismic performance of pile-cap connections was considered and investigated. The experimental results showed that flexural bending failure occurred in all connections. There were two main failure modes. One was tensile rupturing of prestressed bars and headings, resulting in loss of bearing capacity of the connections. The other type was more severe damage due to anchor bar yield and appearance of plastic hinge. Moreover, bond-slip failure of anchor bars was not observed in the cap, and the length of anchor bars met requirements. The analysis indicated that the bearing capacity and energy dissipation capacity increased along with the rotation capacity of the pile connections. Nonlinear finite element models were established to analyze the mechanical properties of these connections using OpenSees. The load-displacement curves obtained from the numerical analysis agreed with the experimental results. The effects of various parameters on the behaviour of the connections were conducted based on the numerical model.
引用
收藏
页码:1903 / 1912
页数:10
相关论文
共 50 条
  • [1] Experimental and numerical investigation on the behaviour of prestressed high strength concrete pile-to-pile cap connections
    Zhijian Yang
    Wenjin Wang
    KSCE Journal of Civil Engineering, 2016, 20 : 1903 - 1912
  • [2] Seismic Performance of Prestressed High Strength Concrete Pile to Pile Cap Connections
    Wang, Tiecheng
    Yang, Zhijian
    Zhao, Hailong
    Wang, Wenjin
    ADVANCES IN STRUCTURAL ENGINEERING, 2014, 17 (09) : 1329 - 1342
  • [3] Performance Investigation and Design of Pile-to-Pile Cap Connections Subject to Uplift
    Iekel, Philip P.
    Phares, Brent
    Nop, Michael
    TRANSPORTATION RESEARCH RECORD, 2018, 2672 (52) : 278 - 290
  • [4] Experimental studies on precast prestressed concrete pile to CIP concrete pile-cap connections
    Xiao, Y
    PCI JOURNAL, 2003, 48 (06): : 82 - 91
  • [5] Experimental research on seismic performances of prestressed high-strength concrete pipe piles and pile-pile cap connections
    Wang, T.-C. (wangtiecheng@eyou.com), 1600, Chinese Society of Civil Engineering (35):
  • [6] Seismic Performance of Pile-Cap Connections of Prestressed High-Strength Concrete Pile with Different Details
    Guo, Zhaosheng
    He, Wubin
    Bai, Xiaohong
    Chen, Y. Frank
    STRUCTURAL ENGINEERING INTERNATIONAL, 2017, 27 (04) : 546 - 557
  • [7] Bearing Performance of Prestressed High-Strength Concrete Pipe Pile Cap Connections under Truncated Pile Conditions
    Liu, Yasheng
    Guo, Zhaosheng
    He, Wubin
    Ge, Xinsheng
    Wang, Jingyue
    Zhao, Jing
    BUILDINGS, 2024, 14 (05)
  • [8] Analysis Methods for the Design of Pile-to-Pile Cap Connections Concerning Plain Pile Embedment
    Arvan, Prakash Ankitha
    Arockiasamy, Madasamy
    PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION, 2023, 28 (03)
  • [9] Behavior of precast, prestressed concrete pile to cast-in-place pile cap connections
    Harries, KA
    Petrou, MF
    PCI JOURNAL, 2002, 47 (02): : 101 - 102
  • [10] Behavior of precast, prestressed concrete pile to cast-in-place pile cap connections
    Harries, KA
    Petrou, MF
    PCI JOURNAL, 2001, 46 (04): : 82 - +