Applying Constraint Programming to the Multi-mode Scheduling Problem in Harvest Logistics

被引:1
|
作者
Bender, Till [1 ]
Wittwer, David [1 ]
Schmidt, Thorsten [1 ]
机构
[1] Tech Univ Dresden, Tech Logist, D-01062 Dresden, Germany
来源
关键词
Harvest logistics; Constraint programming; Resource-constraint project scheduling; TIME;
D O I
10.1007/978-3-030-87672-2_37
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
In this paper, we present a Constraint Programming (CP) based model for scheduling forage harvesters and transport vehicles during corn harvest. The key aspects are the synchronization of the two resource types and a forage harvester utilization depending on the number of transport vehicles supporting the harvester. The process is modelled as a pre-emptive multi-mode resource-constraint project scheduling problem with fast-tracking, sequence-dependent time lags and synchronization. We use the specialized scheduling features of CP Optimizer for modelling and solving the harvest logistics problem. The results show the suitability of the CP-based approach for modelling the problem in terms of representability of its characteristics. In computational experiments, a solution is found for any of the test instances. Proving optimality, however, is found to be difficult, especially for larger instances. Further variants of the model without pre-emption and fast-tracking and with fewer modes per activity are introduced and tested, showing improvements in computation time and the number of optimal solutions found for the prior variant.
引用
收藏
页码:562 / 577
页数:16
相关论文
共 50 条
  • [1] A Constraint Programming Formulation of the Multi-Mode Resource-Constrained Project Scheduling Problem for the Flexible Job Shop Scheduling Problem
    Yuraszeck, Francisco
    Montero, Elizabeth
    Canut-De-Bon, Dario
    Cuneo, Nicolas
    Rojel, Maximiliano
    IEEE ACCESS, 2023, 11 : 144928 - 144938
  • [2] Hybridizing constraint programming and meta-heuristics for multi-mode resource-constrained multiple projects scheduling Problem
    Ahmeti, Arben
    Musliu, Nysret
    JOURNAL OF HEURISTICS, 2025, 31 (01) : 35 - 37
  • [3] Constraint Based Scheduling: Applying Constraint Programming to Scheduling Problems
    Edward Tsang
    Journal of Scheduling, 2003, 6 (4) : 413 - 414
  • [4] Learning agents for the multi-mode project scheduling problem
    Wauters, T.
    Verbeeck, K.
    Vanden Berghe, G.
    De Causmaecker, P.
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2011, 62 (02) : 281 - 290
  • [5] Some appraisal criteria for multi-mode scheduling problem
    Abdel-Basset, Mohamed
    Atef, Asmaa
    Hussein, Abdel-Nasser
    JOURNAL OF AMBIENT INTELLIGENCE AND HUMANIZED COMPUTING, 2019, 10 (04) : 1641 - 1654
  • [6] Some appraisal criteria for multi-mode scheduling problem
    Mohamed Abdel-Basset
    Asmaa Atef
    Abdel-Nasser Hussein
    Journal of Ambient Intelligence and Humanized Computing, 2019, 10 : 1641 - 1654
  • [7] A Critical Chain Project Scheduling Problem with Multi-mode
    Peng, W. L.
    Jiao, Q. J.
    ADVANCES IN MATERIALS MANUFACTURING SCIENCE AND TECHNOLOGY XIV, 2012, 697-698 : 541 - 545
  • [8] The Multi-Mode Resource-Constrained Multi-Project Scheduling Problem
    Wauters, Tony
    Kinable, Joris
    Smet, Pieter
    Vancroonenburg, Wim
    Vanden Berghe, Greet
    Verstichel, Jannes
    JOURNAL OF SCHEDULING, 2016, 19 (03) : 271 - 283
  • [9] Constraint Programming Applied to the Multi-Skill Project Scheduling Problem
    Young, Kenneth D.
    Feydy, Thibaut
    Schutt, Andreas
    PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING (CP 2017), 2017, 10416 : 308 - 317
  • [10] Fuzzy linear programming approach to multi-mode distribution planning problem
    Bilgen, Bilge
    Ozkarahan, Irem
    KNOWLEDGE-BASED INTELLIGENT INFORMATION AND ENGINEERING SYSTEMS, PT 1, PROCEEDINGS, 2006, 4251 : 37 - 45