Energetic and exergetic analysis of a multi-stage turbine, coal-fired 173 MW power plant

被引:9
|
作者
Clay, Joshua [1 ]
Mathias, James [1 ]
机构
[1] Southern Illinois Univ Carbondale, Mech Engn & Energy Proc Dept, 1230 Lincoln Dr, Carbondale, IL 62901 USA
关键词
exergy; power generation; heat exchangers; turbines;
D O I
10.1504/IJEX.2018.096000
中图分类号
O414.1 [热力学];
学科分类号
摘要
This paper reports the results of an energy and exergy audit of a 173 MW pulverised coal fired, subcritical steam power plant unit in the Midwestern USA. Energy and exergy analysis determined the thermal efficiency and identified the greatest sources of irreversibilities and also mapped the flow of energy and exergy throughout the plant. The overall plant energetic and exergetic efficiencies were found to be 32.8% and 33.7%, respectively. The largest source of exergy destruction in the cycle was found to be within the steam generator. Options explored to increase the exergetic efficiency were to improve the steam turbines to operate with higher temperature steam, to bring water into the condenser from the lake that is closer to the ambient temperature, and to replace a valve after the boiler feedwater pump with a hydro-turbine to produce some power.
引用
收藏
页码:419 / 436
页数:18
相关论文
共 50 条
  • [21] Exergoeconomic and exergoenvironmental analysis of a coal-fired thermal power plant
    Abdullah Duzcan
    Yusuf Ali Kara
    Journal of the Brazilian Society of Mechanical Sciences and Engineering, 2021, 43
  • [22] Analysis of Particulate Dispersion in Suralaya Coal-fired Power Plant
    Charloth, Vini
    Widodo, Wawan Aries
    Warmadewanthi, Idaa
    INNOVATIVE SCIENCE AND TECHNOLOGY IN MECHANICAL ENGINEERING FOR INDUSTRY 4.0, 2019, 2187
  • [23] Thermodynamic analysis of a solar aided coal-fired power plant
    Wang, W.
    Fu, Y. W.
    Fan, Q. W.
    Huang, J. S.
    Chang, D. F.
    2018 2ND INTERNATIONAL WORKSHOP ON RENEWABLE ENERGY AND DEVELOPMENT (IWRED 2018), 2018, 153
  • [24] Analysis of gas turbine combined heat and power system for carbon capture installation of coal-fired power plant
    Chmielniak, Tadeusz
    Lepszy, Sebastian
    Wojcik, Katarzyna
    ENERGY, 2012, 45 (01) : 125 - 133
  • [25] Performance analysis of a photovoltaics aided coal-fired power plant
    Jiang, Mingkun
    Lv, Yuexia
    Wang, Tiankun
    Sun, Zunqiang
    Liu, Jianmin
    Yu, Xinhai
    Yan, Jinyue
    INNOVATIVE SOLUTIONS FOR ENERGY TRANSITIONS, 2019, 158 : 1348 - 1353
  • [26] Membrane processes applied to carbon capture in coal-fired power plants: From modelling to multi-stage design
    Bocciardo, D.
    Ferrari, M. G.
    Brandani, S.
    EUROMEMBRANE CONFERENCE 2012, 2012, 44 : 1278 - 1280
  • [27] Particle Removal Efficiency Analysis of WESP in a Typical 660MW Coal-fired Power Plant
    Wang, Pei-di
    Wang, Xue-tao
    Liu, Yu
    Ren, Jian-xing
    2016 INTERNATIONAL CONFERENCE ON ENVIRONMENTAL SCIENCE AND ENGINEERING (ESE 2016), 2016, : 682 - 686
  • [28] Repowering a small coal-fired power plant
    Miell, Rick
    POWER ENGINEERING, 2007, 111 (11) : 24 - 24
  • [29] Analysis of the stage group efficiency of steam turbine based on the unified model for coal-fired power unit
    Guo, J. L.
    Chang, H.
    Zhang, R. C.
    Shi, Y.
    2019 INTERNATIONAL CONFERENCE ON NEW ENERGY AND FUTURE ENERGY SYSTEM, 2019, 354
  • [30] 1600 megawatt coal-fired power plant
    不详
    BAUINGENIEUR, 2009, 84 : A14 - A14