Evaluation of Maintenance Intervals for Spring-Operated Relief Valves Using a Risk-Based Inspection Technique

被引:2
|
作者
Gross, Robert E. [1 ]
Mitchell, Emily M. [2 ]
Harris, Stephen P. [3 ]
机构
[1] Savannah River Nucl Solut, Aiken, SC 29808 USA
[2] Emory Univ, Atlanta, GA 30322 USA
[3] Savannah River Natl Lab, Aiken, SC 29808 USA
关键词
D O I
10.1115/1.4005940
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
The Savannah River Site (SRS) spring-operated relief valve (SORV) maintenance intervals were evaluated using the American Petroleum Institute's (API) inspection updating approach in API RP 581 for Risk-Based Inspection (RBI) technology. In addition, the impact of extending the inspection schedule was evaluated using Monte Carlo simulation (MCS). The API RP 581 approach is characterized as a Weibull analysis with modified Bayesian updating. Initial Weibull parameter estimates were updated using SRS's historical proof test records contained in the Center for Chemical Process Safety Process Equipment Reliability Database. The API RP 581 methodology was used to estimate the SORV's probability of failing on demand and the annual expected risk. An illustration of the inspection costs versus the associated risks is provided. Current practices are reviewed, and recommendations are made for extending maintenance intervals. A cost-effective maintenance frequency balancing both financial risk and inspection cost is demonstrated. [DOI: 10.1115/1.4005940]
引用
收藏
页数:7
相关论文
共 50 条
  • [1] The Adhesion Failure Mode in Stainless Steel Trim Spring-Operated Pressure Relief Valves
    Bukowski, Julia V.
    Gross, Robert E.
    Goble, William M.
    JOURNAL OF PRESSURE VESSEL TECHNOLOGY-TRANSACTIONS OF THE ASME, 2013, 135 (06):
  • [2] THE EFFECTS OF MAINTENANCE ACTIONS ON THE PFDavg OF SPRING OPERATED PRESSURE RELIEF VALVES
    Bukowski, Julia V.
    Goble, William M.
    Gross, Robert E.
    Harris, Stephen R.
    ASME PRESSURE VESSELS AND PIPING CONFERENCE - 2014, VOL 6B, 2014,
  • [3] A strategy for the risk-based inspection of pressure safety valves
    Chien, Chi-Hui
    Chen, Chun-Hung
    Chao, Yuh J.
    RELIABILITY ENGINEERING & SYSTEM SAFETY, 2009, 94 (04) : 810 - 818
  • [4] An implementation of risk-based inspection for elevator maintenance
    Seung-Tae Park
    Bo-Suk Yang
    Journal of Mechanical Science and Technology, 2010, 24 : 2367 - 2376
  • [5] An implementation of risk-based inspection for elevator maintenance
    Park, Seung-Tae
    Yang, Bo-Suk
    JOURNAL OF MECHANICAL SCIENCE AND TECHNOLOGY, 2010, 24 (12) : 2367 - 2376
  • [6] The Effects of Maintenance Actions on the Average Probability of Failure on Demand of Spring Operated Pressure Relief Valves
    Bukowski, Julia V.
    Goble, William M.
    Gross, Robert E.
    Harris, Stephen P.
    JOURNAL OF PRESSURE VESSEL TECHNOLOGY-TRANSACTIONS OF THE ASME, 2015, 137 (06):
  • [7] ESTIMATION OF IMPACT ENERGY FOR SEAT SEALS IN SPRING-OPERATED PRESSURE RELIEF VALVES DURING THE RESEATING PROCESS UNDER COMPRESSIBLE FLUID SERVICE CONDITIONS
    Schimanowski, Alex
    Schlattmann, Josef
    PROCEEDINGS OF THE ASME PRESSURE VESSELS AND PIPING CONFERENCE, 2019, VOL 3, 2019,
  • [8] Regulatory requirements related to risk-based inspection and maintenance
    Schröder, HC
    Kauer, R
    INTERNATIONAL JOURNAL OF PRESSURE VESSELS AND PIPING, 2004, 81 (10-11) : 847 - 854
  • [9] Risk-based inspection and maintenance systems for steam turbines
    Fujiyama, K
    Nagai, S
    Akikuni, Y
    Fujiwara, T
    Furuya, K
    Matsumoto, S
    Takagi, K
    Kawabata, T
    INTERNATIONAL JOURNAL OF PRESSURE VESSELS AND PIPING, 2004, 81 (10-11) : 825 - 835
  • [10] An evaluation of maintenance strategy using risk based inspection
    Tan Zhaoyang
    Li Jianfeng
    Wu Zongzhi
    Zheng Jianhu
    He Weifeng
    SAFETY SCIENCE, 2011, 49 (06) : 852 - 860