Detailed simulation and visualization of crane activities have been recently introduced to help engineers identify potential problems with critical erection tasks; however, the development of real-time erection visualizations for different types of cranes and lifting objects is time-consuming, and usually requires a certain amount of effort in modeling and setting up the environment. This research proposes a configurable model which is reusable, fast-prototyping, and extendable to support real-time visualization of the erection process. The developed model of the crane is divided into three modules which can be reconfigured for different erection tasks. Each module is defined using multiple rigid bodies and the joint constraints of multibody dynamics. The proposed modeling method can also be easily adapted to existing physics engines. To evaluate the feasibility of the proposed method, we observed the processes involved in a common erection activity and compared this with the visualization results obtained using proposed method. We also simulated a cooperative cranes scenario taken from an actual construction project to demonstrate its usability. We found that the proposed modeling method was easily able to visualize various erection activities with different cranes and configurations. (C) 2013 Elsevier Ltd. All rights reserved.
引用
收藏
页码:1 / 11
页数:11
相关论文
共 50 条
  • [11] EVALUATION OF REAL-TIME RIGISCAN MONITORING IN PHARMACOLOGICAL ERECTION
    OGRINC, FG
    LINET, OI
    [J]. JOURNAL OF UROLOGY, 1995, 154 (04): : 1356 - 1359
  • [12] Yard Crane Scheduling with Real-time Reshuffle
    Man, Xiaoyi
    Zheng, Feifeng
    Chu, Feng
    Xu, Yinfeng
    [J]. PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 225 - 230
  • [13] Planning and visualization for automated robotic crane erection processes in construction
    Kang, ShihChung
    Miranda, Eduardo
    [J]. AUTOMATION IN CONSTRUCTION, 2006, 15 (04) : 398 - 414
  • [14] A real-time configurable shader based on lookup tables
    Ohbuchi, E
    Unno, H
    [J]. FIRST INTERNATIONAL SYMPOSIUM ON CYBER WORLDS, PROCEEDINGS, 2002, : 507 - 514
  • [15] Real-Time Visualization of Moving Objects
    Ortal, Patricia
    Kato, Shinpei
    Edahiro, Masato
    [J]. 2015 IEEE 3RD INTERNATIONAL CONFERENCE ON CYBER-PHYSICAL SYSTEMS, NETWORKS, AND APPLICATIONS CPSNA 2015, 2015, : 60 - 65
  • [16] Real-time image visualization for sensors
    Anding, DC
    Szabo, A
    [J]. TECHNOLOGIES FOR SYNTHETIC ENVIRONMENTS: HARDWARE-IN-THE-LOOP TESTING, 1996, 2741 : 232 - 241
  • [17] REAL-TIME VISUALIZATION OF CONCURRENT PROCESSES
    SHARMA, S
    [J]. LECTURE NOTES IN COMPUTER SCIENCE, 1990, 457 : 852 - 862
  • [18] Real-time visualization of dynamic terrain
    Cai, XQ
    Li, FX
    Zhan, SY
    [J]. SYSTEM SIMULATION AND SCIENTIFIC COMPUTING, VOLS 1 AND 2, PROCEEDINGS, 2005, : 450 - 455
  • [19] RNA localization: Visualization in real-time
    Singer, RH
    [J]. CURRENT BIOLOGY, 2003, 13 (17) : R673 - R675
  • [20] Real-time visualization of animated trees
    Wesslén, D
    Seipel, S
    [J]. VISUAL COMPUTER, 2005, 21 (06): : 397 - 405