Design of the power caverns for Pergau hydroelectric project, Malaysia

被引:0
|
作者
Varley, PM [1 ]
Parkin, RJH [1 ]
Taylor, D [1 ]
Patel, R [1 ]
机构
[1] Knight Piesold Ltd, Ashford TN23 1PP, Kent, England
关键词
D O I
暂无
中图分类号
TD [矿业工程];
学科分类号
0819 ;
摘要
A power-generation cavern of 30-m span has been built in hydrothermally altered granite rock at the Pergau hydroelectric project in northern Malaysia. One implication of the fast-track design-and-build nature of the project was that the additional site investigation that was needed to provide specific data for the design had to be undertaken during the early part of the construction work. This execution of the design and construction work in tandem had a major influence on the way in which the design developed and on the design decisions that had to be made. The development of the design is described, from the initial analyses, in which relatively simple numerical programs and limited geotechnical data were employed, to the detailed analyses, in which, principally, the computer program UDEC was used together with discontinuity data acquired during the early construction phases of the project. The intersection of large fissures containing hot water and hydrothermally altered rock had not been predicted from the site investigation undertaken for the project and the solutions that were engineered for these unanticipated ground conditions are explained.
引用
收藏
页码:A1 / A7
页数:7
相关论文
共 50 条
  • [41] Construction of desilting chamber for the Kol dam hydroelectric power project
    Bamane, Nilesh N.
    [J]. Indian Concrete Journal, 2015, 89 (10): : 15 - 27
  • [42] Power increase of Lavey (Switzerland), hydroelectric power scheme, Lavey plus project
    Davalle, Eric
    Quigley, Brendan
    Filliez, Jerome
    [J]. HOUILLE BLANCHE-REVUE INTERNATIONALE DE L EAU, 2015, (06): : 71 - 78
  • [43] Lessons from the failure of the LS Hydroelectric Power Project dam
    Uddin, N
    [J]. FILTRATION AND DRAINAGE IN GEOTECHNICAL/GEOENVIRONMENTAL ENGINEERING, 1998, (78): : 192 - 204
  • [44] Stabilisation of the machinery hall, Uri Hydroelectric Power Project, India
    Brantmark, J
    Heiner, A
    Martna, J
    Stille, H
    [J]. PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON HYDRO POWER DEVELOPMENT IN HIMALAYAS, 1998, : 178 - 192
  • [45] Design of underground caverns for Tehri Hydropower Project, India by numerical modelling
    Dasgupta, B
    Sharma, MKV
    Verman, M
    Sharma, VM
    [J]. NINTH INTERNATIONAL CONGRESS ON ROCK MECHANICS, VOLS 1 & 2, 1999, : 357 - 358
  • [46] Rainfall enhancement for increasing power generation at the Temengor Hydroelectric Power Station, Malaysia - A preliminary assessment
    Choy, FK
    Hamzah, F
    [J]. SUSTAINABLE PLANNING AND DEVELOPMENT, 2003, 6 : 611 - 621
  • [47] ELECTRICAL AND RELATED DESIGN ASPECTS OF ITAIPU HYDROELECTRIC PROJECT.
    de Moraes, Julival
    Villalba, J.Rodriguez
    Salatko, V.F.
    [J]. SAE Preprints, 1981,
  • [48] Framework of systematic sustainability assessment strategy (FSSAS) for hydroelectric power industry in Malaysia
    Johan, Kartina
    Turan, Faiz Mohd
    [J]. INTERNATIONAL RESEARCH AND INNOVATION SUMMIT (IRIS2017), 2017, 226
  • [49] SALIENT ELECTRICAL DESIGN FEATURES OF THE MAGAT HYDROELECTRIC PROJECT.
    Verma, Rajindra
    Samorio, Ricardo V.
    [J]. IEEE Transactions on Energy Conversion, 1987, EC-2 (02) : 201 - 207
  • [50] A Multidisciplinary Hydroelectric Generation Design Project for the Freshman Engineering Experience
    Prairie, Michael W.
    Wight, Gregory
    Kjeer, Peter
    [J]. 2013 ASEE ANNUAL CONFERENCE, 2013,