RISK ANALYSIS OF THE BRENNER BASE TUNNEL PROJECT

被引:0
|
作者
Alfreider, Daniel [1 ]
Tamparopoulos, Alexios [2 ]
Bergmeister, Konrad
机构
[1] BBT SE, Galleria Base Brennero Brenner Basistunnel, Project Planning Cost Management, Piazza Stn 1, I-39100 Bolzano, Italy
[2] Univ Bodenkultur Wien, Dept Struct Engn & Nat Hazards, A-1190 Vienna, Austria
关键词
Risk assessment; Uncertainty modelling; Cost estimation;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the case of complex and innovative structural systems, proper modelling of uncertainty holds a key role in the design procedure. Uncertainties, either of aleatory or epistemic nature, stemming from materials, processes, mechanical, traffic and financial models or even human perception towards the various project components, have to be treated effectively in an integrated design framework. Over the last years, through a Risk Analysis and Management approach, realisation of intricate and sensitive structures has been made possible. In the present work, some aspects of the Risk Analysis of the Brenner Base Tunnel (Brenner Basistunnel - Galleria di Base del Brennero), one of the most important construction projects today in Europe, are being presented. The complexity of the project is being explained through evidence from the actual work in progress. Methods to assess and quantify risk amount in infrastructure projects are being discussed. Finally an analogy to structural analysis is proposed for considering a risk analysis under its global "stress field" of cost, time and risk.
引用
收藏
页码:895 / 898
页数:4
相关论文
共 50 条
  • [41] 15 km TBM exploratory tunnel excavation in the construction Lot H33 of the Brenner Base Tunnel
    Lussu, Andrea
    Grüllich, Sebastian
    Kaiser, Christian
    Fontana, Adrian
    Geomechanik und Tunnelbau, 2019, 12 (05): : 595 - 603
  • [42] Gotthard base tunnel - A project of a quarter century
    Schär, René
    Steinmann, Nicolas
    Wiederkehr, Roger
    eb - Elektrische Bahnen, 2015, 113 (6-7): : 298 - 305
  • [43] TBMs for the Brenner Base Tunnel – design, developments and experience from the manufacturer's perspective
    Wehrmeyer, Gerhard
    Geomechanik und Tunnelbau, 2024, 17 (06): : 613 - 621
  • [44] Brenner Base Tunnel – Tunnelling in the immediate vicinity of existing structures on the Tulfes–Pfons contract
    Mössmer S.
    Sulzbacher G.
    Jedlitschka G.
    Holzleitner W.
    Geomechanik und Tunnelbau, 2019, 12 (06): : 708 - 715
  • [45] BRENNER,ROBERT IN THE TUNNEL OF TIME
    BLAUT, JM
    ANTIPODE, 1994, 26 (04) : 351 - 374
  • [46] Hydrogeology of the Brenner Base Tunnel in the Italian section: Observed inflows and forward monitoring procedures
    Perello, P.
    Skuk, S.
    Spaziani, A.
    Voza, A.
    PROCEEDINGS OF THE ITA-AITES WORLD TUNNEL CONGRESS 2023, WTC 2023: Expanding Underground-Knowledge and Passion to Make a Positive Impact on the World, 2023, : 351 - 359
  • [47] Concept, design and testing of an innovative geothermal heat exchanger installed at the Brenner Base Tunnel
    Spaggiari, Chiara
    Tinti, Francesco
    Lanconelli, Matteo
    Voza, Antonio
    Boldini, Daniela
    GALLERIE E GRANDI OPERE SOTTERRANEE, 2022, (141): : 27 - 41
  • [48] Brenner Base Tunnel & Isarco River Underpass Section: several technical and operational solutions
    Lunardi, Giuseppe
    Cassani, Giovanna
    Gatti, Martino
    Bellardo, Luca
    Palomba, Alberto
    GALLERIE E GRANDI OPERE SOTTERRANEE, 2018, (125): : 33 - 44
  • [49] Brenner base tunnel, construction lot H41 Sill Gorge–Pfons: challenges based on previous construction lots in the project area
    Insam R.
    Mössmer S.
    Radončić N.
    Priller A.
    Staffel O.
    Reith M.
    Geomechanik und Tunnelbau, 2023, 16 (04): : 353 - 369
  • [50] Factors influencing overbreak volumes in drill-and-blast tunnel excavation. A statistical analysis applied to the case study of the Brenner Base Tunnel - BBT
    Fodera, G. M.
    Voza, A.
    Barovero, G.
    Tinti, F.
    Boldini, D.
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2020, 105