The Cost Monitoring of Construction Projects Through Earned Value Analysis

被引:0
|
作者
Khamidi, Mohd Faris [1 ]
Khan, Waris Ali [1 ]
Idrus, Arazi [1 ]
机构
[1] Univ Teknol PETRONAS, Dept Civil Engn, Tronoh 31750, Perak, Malaysia
来源
关键词
cost monitoring; earned value analysis; construction cost management;
D O I
暂无
中图分类号
F8 [财政、金融];
学科分类号
0202 ;
摘要
In construction industry, the term 'procurement' is considered as a project based job where clients and contractors are always keen to observe performance indicators. These indicators represent financial and non-financial efficiency of project activities. Among these, the monitoring of financial indicators is an important function of project management. Therefore, during the construction phase, it is the prime responsibility of project managers to monitor cost and avoid any overruns to maintain the cost baseline. Cost monitoring is an ongoing process and its importance cannot be undermined during the project life cycle. It can be monitored by using traditional approach of direct reporting of actual cost against budget. However, the comparison of budget versus actual spending does not indicate the worth of the work which is completed at any given time. This approach does not portray the true cost performance of the project. Because of these limitations, this paper discusses the applications of Earned Value Analysis (EVA) for cost management of construction projects in Malaysia. Besides traditional approach, EVA is a three-dimensional technique that compares the budgeted value of work scheduled with the earned value of physical work completed and the actual cost of work completed. Therefore, cost management by EVA is an objective measure of actual work performed. This paper uses a case study, an example application of EVA as a cost monitoring tool. This case study reaffirms the benefits of using EVA for project cash flow analysis and forecasting.
引用
收藏
页码:129 / 133
页数:5
相关论文
共 50 条
  • [31] Cost/Schedule Monitoring and Forecasting for Project Based on Earned Value Management (EVM)
    Huang, Jianwen
    Pan, Huimin
    Li, Yan
    Zhu, Yiting
    Liao, Zaiyi
    ADVANCED CONSTRUCTION TECHNOLOGIES, 2014, 919-921 : 1437 - +
  • [32] MODELING AND SIMULATING THE DYNAMICS IN PROJECT MONITORING AND EARNED VALUE ANALYSIS
    Jigeesh, Nasina
    Bhat, M. S.
    JOURNAL OF ADVANCES IN MANAGEMENT RESEARCH, 2006, 3 (01) : 26 - 43
  • [33] Regression Modeling for Prediction of Earned Value Indexes in Public Building Construction Projects: The case of Ethiopia
    Ayalew, Genet Melkamu
    Meharie, Meseret Getnet
    Ayalew, Girmay Getawa
    COGENT ENGINEERING, 2023, 10 (01):
  • [34] Earned Value as a performance measurement tool for small and large construction projects in a South African environment
    Vertenten, M.
    Pretorius, L.
    Pretorius, J. H. C.
    2009 AFRICON, VOLS 1 AND 2, 2009, : 885 - 889
  • [35] Improving the Results of the Earned Value Management Technique Using Artificial Neural Networks in Construction Projects
    Balali, Amirhossein
    Valipour, Alireza
    Antucheviciene, Jurgita
    Saparauskas, Jonas
    SYMMETRY-BASEL, 2020, 12 (10): : 1 - 17
  • [36] Practical application of Earned Value Method to evaluation of progress status of medium size construction projects
    Czemplik, A.
    3RD INTERNATIONAL CONFERENCE ON INNOVATIVE MATERIALS, STRUCTURES AND TECHNOLOGIES (IMST 2017), 2017, 251
  • [37] Assessing Cost Forecasting Performance in Construction Projects through Data Envelopment Analysis
    Franco-Duran, Diana M.
    Guillermo, Mejia A.
    CONSTRUCTION RESEARCH CONGRESS 2016: OLD AND NEW CONSTRUCTION TECHNOLOGIES CONVERGE IN HISTORIC SAN JUAN, 2016, : 2039 - 2049
  • [38] The Highway Construction Cost Control Model Based On The Improved Earned Value Method Theory
    Ying, Huang
    2016 INTERNATIONAL CONFERENCE ON SMART CITY AND SYSTEMS ENGINEERING (ICSCSE), 2016, : 461 - 464
  • [39] Developing fuzzy-based earned value analysis model for estimating the performance of construction projects. A case of selected public building projects in Ethiopia
    Ayalew, Girmay Getawa
    Ayalew, Genet Melkamu
    COGENT ENGINEERING, 2024, 11 (01):
  • [40] Exploring a recurrent neural network (RNN) earned value based model for predicting lost labour value in construction projects
    Samuel I. Egwunatum
    Opeyemi A. Osadola
    Joel Oboshior
    Discover Civil Engineering, 1 (1):