Experimental Study on Stability of Long-Span PC Cable-Stayed Bridge during the Construction Periods

被引:0
|
作者
Zeng, Yong [1 ]
Wang, Yuxiao [2 ]
Shi, Zhenwei [1 ]
Tan, Hongmei [2 ]
Gu, Anbang [2 ]
机构
[1] Chongqing Jiaotong Univ, State Key Lab Mt Bridge & Tunnel Engn, Chongqing, Peoples R China
[2] Chongqing Jiaotong Univ, Mt Bridge & Mat Engn Res Ctr, Minist Educ, Chongqing, Peoples R China
关键词
D O I
10.1155/2022/8578684
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
With the increasing span of cable-stayed bridges, the towers are getting higher and higher, and the stiffening beams are becoming more and more slender. The increase in span causes the axial pressure of the beams and towers to increase rapidly, and the sag effect of the cables, geometric nonlinearity, and material nonlinear e.ects are significantly increased. The influence of these disadvantages greatly reduces the stability of the cable-stayed bridge, and the stability of the cable-stayed bridge becomes prominent. In this paper, the finite element method is used to analyze the first kind of stability problem and the second kind of stability problem of cable-stayed bridges. On this basis, a large-span prestressed concrete (PC) cable-stayed bridge is taken as an example to analyze and compare the two types of stability problems of the bridge during the construction phase and the operation phase. Besides, the model experimental study on the stability of the bridge during the maximum double cantilever construction period was carried out. The theoretical values and the model test results are compared to verify the correctness of the calculation method and design theory, which may provide a reference for the design, construction, and scientific research of cable-stayed bridges.
引用
收藏
页数:10
相关论文
共 50 条
  • [2] Construction Control and Simulation Analysis of Long-Span Cable-stayed Bridge
    Wu, Fangwen
    Xue, Chengfeng
    [J]. ADVANCES IN CIVIL ENGINEERING, PTS 1-6, 2011, 255-260 : 816 - +
  • [3] Aerodynamic characteristics of a long-span cable-stayed bridge under construction
    Ma, Cunming
    Duan, Qingsong
    Li, Qiusheng
    Liao, Haili
    Tao, Qi
    [J]. ENGINEERING STRUCTURES, 2019, 184 : 232 - 246
  • [4] Simulation and analysis of long-span cable-stayed bridge during construction based on ANSYS
    Wu, Fangwen
    Xue, Chengfeng
    [J]. ICMS2010: PROCEEDINGS OF THE THIRD INTERNATIONAL CONFERENCE ON MODELLING AND SIMULATION, VOL 1: ENGINEERING COMPUTATION AND FINITE ELEMENT ANALYSIS, 2010, : 341 - 345
  • [5] Temperature monitoring and analysis of a long-span cable-stayed bridge during construction period
    Mei, Xiudao
    Lu, Yiyan
    Shi, Jing
    [J]. STRUCTURAL MONITORING AND MAINTENANCE, 2021, 8 (02): : 203 - 220
  • [6] Damage Detection for Long-Span Cable-Stayed Bridge
    赵玲
    李爱群
    缪长青
    汪永兰
    [J]. Railway Engineering Science, 2006, (01) : 63 - 72
  • [7] Dynamic Characteristics of a Long-span Cable-stayed Bridge
    Hui, Liu
    [J]. MATERIALS ENGINEERING FOR ADVANCED TECHNOLOGIES, PTS 1 AND 2, 2011, 480-481 : 1496 - 1501
  • [8] AEROSTATIC AND AERODYNAMIC STABILITY ANALYSIS OF SUPER LONG-SPAN CABLE-STAYED BRIDGE UNDER CONSTRUCTION
    Zhang, Xin-Jun
    Xu, Wei-Long
    [J]. PROCEEDINGS OF THE ELEVENTH INTERNATIONAL SYMPOSIUM ON STRUCTURAL ENGINEERING, VOL I AND II, 2010, : 1489 - 1493
  • [9] Cable Health Monitoring System for Long-span Cable-stayed Bridge
    Gao Chao
    Li Xinke
    Guo Yongcai
    He Fuliang
    [J]. DISASTER ADVANCES, 2011, 4 : 130 - 135
  • [10] Study on the Long-span Cable-stayed Bridge Composite Beam Hoisting Construction Technology in China
    Li, Xinxing