Estimating Cost Discrepancies in Highway Contracts: Multistep Econometric Approach

被引:44
|
作者
Gkritza, Konstantina [1 ]
Labi, Samuel [2 ]
机构
[1] Iowa State Univ, Dept Civil Construct & Environm Engn, Ames, IA 50011 USA
[2] MIT, Sch Civil & Environm Engn, Cambridge, MA 02139 USA
关键词
D O I
10.1061/(ASCE)0733-9364(2008)134:12(953)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper investigates the likelihood of occurrence and quantifies the magnitude and rate of discrepancies in highway project final costs with respect to their contract award amounts. Using data from Indiana, we develop a multistep econometric approach that can be used to estimate the effects of factors associated with the contract bidding process, project type, and the project physical environment on cost discrepancies in highway contracts. Estimation findings indicate that for a given project type and project year, contracts of larger size or longer duration are generally more likely to incur cost overruns. In addition, for contracts that incur cost overruns, the cost overrun rate decreases nonlinearly with increasing contract size up to a certain point after which the cost overrun rate increases with increasing contract size. Our approach allows for the possibility that cost overrun amounts are not linearly related to contract award amounts (contract size), and shows that greater analytical flexibility needs to be incorporated into any investigation of contract cost overruns. Agencies interested in improving their financial forecasts can replicate our proposed methodology using local contract data.
引用
收藏
页码:953 / 962
页数:10
相关论文
共 50 条
  • [1] Estimating the cost of a multistep process
    Hahn, A
    CHEMTECH, 1999, 29 (05) : 58 - 60
  • [2] Estimating worklife expectancy: an econometric approach
    Millimet, DL
    Nieswiadomy, M
    Ryu, H
    Slottje, D
    JOURNAL OF ECONOMETRICS, 2003, 113 (01) : 83 - 113
  • [3] Synthesis of Performance Measures for Highway Cost Estimating
    Harper, Christofer M.
    Molenaar, Keith R.
    Anderson, Stuart
    Schexnayder, Cliff
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2014, 30 (03)
  • [4] Statistical Assessment of the Cost Effectiveness of Highway Pavement Warranty Contracts
    Bardaka, Eleni
    Zhang, Zhibo
    Labi, Samuel
    Sinha, Kumares C.
    Mannering, Fred
    JOURNAL OF INFRASTRUCTURE SYSTEMS, 2016, 22 (03)
  • [5] Estimating the Incremental Cost Per QALY Produced by the Spanish NHS: A Fixed-Effect Econometric Approach
    Vallejo-Torres, Laura
    PHARMACOECONOMICS, 2025, 43 (01) : 109 - 122
  • [6] Further econometric evidence on the extent and sources of cost savings in competitively tendered contracts
    Jorge González Chapela
    José M. Labeaga
    Luis A. Medrano
    Empirical Economics, 2019, 56 : 679 - 701
  • [7] Further econometric evidence on the extent and sources of cost savings in competitively tendered contracts
    Gonzalez Chapela, Jorge
    Labeaga, Jose M.
    Medrano, Luis A.
    EMPIRICAL ECONOMICS, 2019, 56 (02) : 679 - 701
  • [9] The transaction cost approach to agricultural contracts
    Allen, DW
    Lueck, D
    AGRICULTURAL MARKETS: MECHANISMS, FAILURES, AND REGULATIONS, 1996, 234 : 31 - 64
  • [10] Estimating the cost of a multistep process (vol 29, pg 60, 1999)
    Hahn, A
    CHEMTECH, 1999, 29 (06) : 2 - 2