Critical Factors Affecting Cost Overrun in Foreign Funded Road Construction Projects in Sri Lanka A Case Study of Road Development Authority and Provincial Road Development Authorities

被引:0
|
作者
Dolage, D. A. R. [1 ]
Dasantha, O. M. C. [2 ]
机构
[1] Open Univ Sri Lanka, Civil Engn, Dept Civil Engn, Colombo, Sri Lanka
[2] Rd Dev Author Sri Lanka, Battaramulla, Sri Lanka
关键词
Cost overrun; Road projects; Road construction; Foreign funded project;
D O I
10.4038/engineer.v55i2.7505
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Foreign funded road projects are rampant with cost overrun, and through the identification of critical factors affecting cost overrun, this problem can be mitigated. In this research, a literature review has been carried out to identify 33 factors causing cost overrun in construction, and through interviews with experts, eight significant factors causing cost overrun in road construction projects have been identified. Altogether 37 factors were considered and classified into five groups: Natural conditions, Client and/or consultant, Client, Contractor and 'Beyond the control of all parties'. These were adopted to analyse the cost overrun in the selected 17 foreign funded road projects. The impact of these factors on the increase in BOQ items and Variations were examined using the documentary evidence and interviews with the personnel involved in these projects. The analysis revealed that only 11 factors had an impact on at least one project. Of these factors, the five most significant factors causing cost overrun, in the descending order of significance, are as follows (the number of projects affected by the factor is given in the parenthesis); Price escalation (13), New instructions issued by the client (9), Unforeseen site requirements (8), Items not identified in the BOQ (8) and Estimation errors in the BOQ (6). The study also analyses these factors in detail and makes recommendations.
引用
收藏
页码:21 / 30
页数:10
相关论文
共 18 条
  • [1] Factors Influencing the Duration of Road Construction Projects in Sri Lanka
    Pathiranage, Yasas L.
    Halwatura, Rangika U.
    [J]. ENGINEER-JOURNAL OF THE INSTITUTION OF ENGINEERS SRI LANKA, 2010, 43 (04): : 17 - 30
  • [2] Development of Guidelines for Low Volume Concrete Road Construction in Sri Lanka
    Mampearachchi, W. K.
    Priyantha, N. A. A.
    [J]. ENGINEER-JOURNAL OF THE INSTITUTION OF ENGINEERS SRI LANKA, 2011, 44 (04): : 1 - 9
  • [3] Development of a mathematical model to predict the cost of Ethiopian Roads Authority road projects: the case of Ethiopia
    Belete, Sisay Birhanu
    Meharie, Meseret Getnet
    Ayalew, Girmay Getawa
    [J]. COGENT ENGINEERING, 2024, 11 (01):
  • [4] Evaluation of Risk Factors Causing Cost Overrun in Road Projects in Terrorism Affected Areas Pakistan - a Case Study
    Zafar, Irfan
    Yousaf, Tashfeen
    Ahmed, Sarfraz
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2016, 20 (05) : 1613 - 1620
  • [5] Evaluation of risk factors causing cost overrun in road projects in terrorism affected areas Pakistan – a case study
    Irfan Zafar
    Tashfeen Yousaf
    Dr Sarfraz Ahmed
    [J]. KSCE Journal of Civil Engineering, 2016, 20 : 1613 - 1620
  • [6] Critical factors affecting the performance of large construction projects in developing countries A case study of Sri Lanka
    San Santoso, Djoen
    Gallage, Polwatta Gallage Madusha Piumal
    [J]. JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2019, 18 (03) : 531 - 556
  • [7] Factors Influencing Governance Practices in Rural Development Projects: A Case Study of Rural Road Projects in Malaysia
    Latiff, Abdul Muhaimin Abdul
    Jaapar, Aini
    Isa, Che Maznah Mat
    [J]. JOURNAL OF CONSTRUCTION IN DEVELOPING COUNTRIES, 2022, 27 (02) : 1 - 16
  • [8] Safety cost component development of risk-based standardized work breakdown structure to determine safety cost on road construction project (Case study: At-grade road works)
    Bernessa, R. A.
    Latief, Y.
    [J]. 5TH ANNUAL APPLIED SCIENCE AND ENGINEERING CONFERENCE (AASEC 2020), 2021, 1098
  • [9] Risk analysis of time on road infrastructure development (Case study: Construction industry in Papua)
    Rusim, D. A.
    Parung, H.
    Latief, R. U.
    Tjaronge, W.
    [J]. 1ST INTERNATIONAL CONFERENCE ON GLOBAL ISSUE FOR INFRASTRUCTURE, ENVIRONMENT & SOCIO-ECONOMIC DEVELOPMENT, 2019, 235
  • [10] Accurate estimation of cost and time utilizing risk analysis and simulation (case study: road construction projects in Iran)
    Arjroody, Abdorreza Rezaee
    Hosseini, Seyed Azim
    Akhbari, Mahdieh
    Safa, Ebrahim
    Asadpour, Jafar
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (01) : 19 - 30