Dam breach analysis and flood inundation mapping of Dire Dam, using HEC-HMS and HEC-RAS models

被引:1
|
作者
Tessema, Belete Hailemariam [1 ]
Gebremedhn, Abrha Ybeyn [2 ]
Getahun, Yitea Seneshaw [2 ]
机构
[1] Debre Berhan Univ, Dept Civil Engn, Debre Berhan, Ethiopia
[2] Debre Berhan Univ, Dept Nat Resources Management, Debre Berhan, Ethiopia
关键词
Dam breach analysis; Inundation mapping; HEC-RAS; HEC-HMS; Dire Dam; BASIN;
D O I
10.1007/s40899-023-01015-w
中图分类号
TV21 [水资源调查与水利规划];
学科分类号
081501 ;
摘要
Pre-event study of dam breaches is required to predict the amount of outflow and downstream propagation conditions that result in dam breach issues. This study aimed at dam breach analysis and flood inundation mapping of the Dire Dam in Ethiopia. The rainfall-runoff data was analyzed using the hydrological model of HEC-HMS. The hydraulic models of HEC-RAS and HEC-GeoRAS were used in conjunction to investigate the dam breach and flood inundation mapping hazards. In HEC-RAS, the breach parameters were calculated and peak flood was routed through the cross-sections for both overtopping and piping scenarios. Dire Dam is expected to face breaching problems due to overtopping when the flood reaches 7073.02 m3s-1. The peak flood hydrograph obtained for a piping mode of failure immediately downstream of the dam was obtained at 11,021.92 m3s-1, while it decreased to 1418.33 m3s-1 when traveling 33.2 km downstream with a time to peak of 0.4 and 2.4 h, respectively. The flood depth obtained by 1D and 2D downstream of the dam ranges between 0.0078-31.56 and 0.00195-20.45 m respectively. While the corresponding estimated flow velocity values of the 1D and 2D vary from 0.9100-12.5 and 0.0034-8.43 ms-1. Thus, the 1D flood modeling overestimated the depth of the water and flow velocity when compared to the 2D flood modeling. This is because the 2D model uses an implicit finite volume algorithm, which is more precise, accurate, and stable as compared to 1D. The total area that could be at risk because of the flooding hazard downstream of the dam is 358.7 ha. Overall, the study's conclusions showed that the downstream villages face terrible circumstances as a result of the flood risk brought on by the dam break issue and it should be advised that improved flood protection infrastructure be put in place.
引用
收藏
页数:16
相关论文
共 50 条
  • [31] Simulation of one-dimensional dam-break flood routing based on HEC-RAS
    Mo, Chongxun
    Shen, Yue
    Lei, Xingbi
    Ban, Huazhen
    Ruan, Yuli
    Lai, Shufeng
    Cen, Weiyan
    Xing, Zhenxiang
    [J]. FRONTIERS IN EARTH SCIENCE, 2023, 10
  • [32] FLOOD HYDROGRAPH ANALYSIS USING SYNTHETIC UNIT HYDROGRAPH, HEC-HMS, AND HEC-RAS 2D UNSTEADY FLOW PRECIPITATION ON-GRID MODEL FOR DISASTER RISK
    Ansori, Mohamad Bagus
    Lasminto, Umboro
    Kartika, Anak Agung Gde
    [J]. INTERNATIONAL JOURNAL OF GEOMATE, 2023, 25 (107): : 50 - 58
  • [33] The Tamblang Dam break analysis using HEC-RAS 5.0.7 and PenRis hazard classification in Indonesia
    Mawiti Infantri Yekti
    I Kade Edwin Baskara Adityananta
    I Putu Gustave Suryantara Pariartha
    [J]. Arabian Journal of Geosciences, 2023, 16 (6)
  • [34] Dam Breach Size Comparison for Flood Simulations. A HEC-RAS Based, GIS Approach for Dracsani Lake, Sitna River, Romania
    Albu, Liviu-Marian
    Enea, Andrei
    Iosub, Marina
    Breaban, Iuliana-Gabriela
    [J]. WATER, 2020, 12 (04)
  • [35] Dam breach size comparison for flood simulations. A HEC-RAS based, GIS Approach for Dracsani Lake, Sitna river, Romania
    Albu, Liviu-Marian
    Enea, Andrei
    Iosub, Marina
    Breaban, Iuliana-Gabriela
    [J]. Water (Switzerland), 2020, 12 (04):
  • [36] Modeling of water flows through a designed dry dam using the HEC-RAS program
    Gruss, Lukasz
    Glowski, Robert
    Wiatkowski, Miroslaw
    [J]. XLVIII SEMINAR OF APPLIED MATHEMATICS, 2018, 23
  • [37] Investigating the effects of land use change on flood hydrograph using HEC-HMS hydrologic model (case study: Ekbatan Dam)
    Shahla Azizi
    Ali Reza Ilderomi
    Hamid Noori
    [J]. Natural Hazards, 2021, 109 : 145 - 160
  • [38] Comparison of the monthly streamflow forecasting in Maroon dam using HEC-HMS and SARIMA models (vol 8, 158, 2022)
    Ahmadpour, Abbas
    Mirhashemi, SeyedHassan
    Jou, Parviz Haghighat
    Foroughi, Farid
    [J]. SUSTAINABLE WATER RESOURCES MANAGEMENT, 2023, 9 (04)
  • [39] Investigating the effects of land use change on flood hydrograph using HEC-HMS hydrologic model (case study: Ekbatan Dam)
    Azizi, Shahla
    Ilderomi, Ali Reza
    Noori, Hamid
    [J]. NATURAL HAZARDS, 2021, 109 (01) : 145 - 160
  • [40] An Integrated Hydrologic and Hydraulic Flood Modeling Study for a Medium-Sized Ungauged Urban Catchment Area: A Case Study of Tiruchirappalli City Using HEC-HMS and HEC-RAS
    Natarajan S.
    Radhakrishnan N.
    [J]. Journal of The Institution of Engineers (India): Series A, 2020, 101 (2) : 381 - 398