Parameter determination and effect evaluation of gob-side entry retaining by directional roof cutting and pressure releasing

被引:4
|
作者
Huang, Xuanhao [1 ]
Zhang, Cun [1 ,2 ,3 ]
Ren, Zhaopeng [1 ]
机构
[1] China Univ Min & Technol Beijing, Sch Energy & Min Engn, Beijing 100083, Peoples R China
[2] Anhui Univ Sci & Technol, Joint Natl Local Engn Res Ctr Safe & Precise Coal, Huainan 232001, Anhui, Peoples R China
[3] China Univ Min & Technol, Minist Educ, Sch Energy & Min Engn, Engn Res Ctr Green Intelligent Min Thick Coal Seam, Beijing 100083, Peoples R China
基金
中国国家自然科学基金;
关键词
Gob-side entry; Roof cutting and pressure releasing; Cutting roof parameters; Flexible formwork concrete wall; Roadway deformation; HARD ROOF; DESIGN; MODEL;
D O I
10.1016/j.engfailanal.2023.107847
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
Cutting the roof and releasing pressure to form a roadway is a crucial technical measure to guarantee the stability of the gob-side entry, and the parameters for cutting the roof are the core issue that requires consideration in the technique. This paper studies the engineering case of the gob-side entry on the 3405 working face of the Danyang coal mine. Theoretical calculation and analysis were conducted to obtain the range of roof cutting heights and roof cutting angles, numerical simulation method was used to simulate different roof cutting parameters. It is found that the roof cutting and pressure releasing technique can sever the cantilever beam structure of the main roof, segregate stress transmission between rock bodies, diminish deformation of the roadway, alleviate stress on the flexible formwork concrete wall, and enhance the stability of the gob-side entry. Furthermore, the appropriate height and angle of the roof cutting were verified to be 15 m and 15 degrees in the case and the effect of cutting was checked by using borehole viewer. On the basis, flexible formwork concrete wall stress and roadway deformation in uncut and cut roof were measured and analyzed in field test. The results show that the maximum stress on the flexible formwork concrete wall is reduced from 160 kN to 20 kN after the roof cutting, total roadway deformation reduced by around 40 %, the stability of the gob-side entry is effectively ensured. Meanwhile, the transformation laws of stress on the flexible formwork concrete wall were changed by cutting roof. It is transitioning from a three-stage pattern of rapid rise, slow rise, and stabilization before the roof cutting to a three-stage pattern of rapid rise, gradual decrease, and stabilization after the roof cutting.
引用
收藏
页数:16
相关论文
共 50 条
  • [1] Study on the Support System Mechanism of Entry Roof with Roof Cutting Pressure Releasing Gob-Side Entry Retaining Technology
    Ma, Xingen
    Li, Guihe
    Cao, Haitao
    Wang, Haijun
    Shi, Xiangyuan
    Zhao, Qingquan
    Han, Zhengcan
    Zhang, Tianyi
    Dai, Weiping
    Zhang, Jiangling
    ADVANCES IN CIVIL ENGINEERING, 2022, 2022
  • [2] Analysis of Roof Deformation Mechanism and Control Measures with Roof Cutting and Pressure Releasing in Gob-Side Entry Retaining
    Sun, Bing-Jun
    Hua, Xin-Zhu
    Zhang, Yan
    Yin, Jiadi
    He, Kai
    Zhao, Chengxing
    Li, Yingfu
    Shock and Vibration, 2021, 2021
  • [3] Analysis of Roof Deformation Mechanism and Control Measures with Roof Cutting and Pressure Releasing in Gob-Side Entry Retaining
    Sun, Bing-Jun
    Hua, Xin-Zhu
    Zhang, Yan
    Yin, Jiadi
    He, Kai
    Zhao, Chengxing
    Li, Yingfu
    SHOCK AND VIBRATION, 2021, 2021
  • [4] Research on the Design of Roof Cutting Parameters of Non Coal Pillar Gob-side Entry Retaining Mining with Roof Cutting and Pressure Releasing
    Ma Xingen
    He Manchao
    Sun Jiandong
    Hu Jie
    Zhang Xingyu
    Zhang Jiabin
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2019, 37 (03) : 1169 - 1184
  • [5] Research on the Design of Roof Cutting Parameters of Non Coal Pillar Gob-side Entry Retaining Mining with Roof Cutting and Pressure Releasing
    Ma Xingen
    He Manchao
    Sun Jiandong
    Hu Jie
    Zhang Xingyu
    Zhang Jiabin
    Geotechnical and Geological Engineering, 2019, 37 : 1169 - 1184
  • [6] Technology of Gob-Side Entry Retaining by Presplitting Blasting and Roof Cutting Pressure Relief
    Xu Zaigang
    Zhang Huiyuan
    Xie Hongfei
    Ji Ming
    ELECTRONIC JOURNAL OF GEOTECHNICAL ENGINEERING, 2016, 21 (07): : 1725 - +
  • [7] Research on Roof Cutting Pressure Relief of the Gob-Side Entry Retaining With Roadside Backfilling
    Zhang, Kun
    Liu, Changyou
    Zhang, Hanrui
    Yue, Xin
    Liu, Huaidong
    FRONTIERS IN EARTH SCIENCE, 2022, 10
  • [8] Fracture characteristics of the roof in gob-side entry retaining withroof cutting and pressure release
    Yang J.
    Wang H.
    Wang Y.
    Gao Y.
    Wang J.
    Liu H.
    Caikuang yu Anquan Gongcheng Xuebao/Journal of Mining and Safety Engineering, 2019, 36 (06): : 1137 - 1144
  • [9] Analysis of Strata Behavior Process Characteristics of Gob-Side Entry Retaining with Roof Cutting and Pressure Releasing Based on Composite Roof Structure
    He, Manchao
    Ma, Xingen
    Yu, Bin
    SHOCK AND VIBRATION, 2019, 2019
  • [10] Gob-side entry retaining formed by roof cutting without roadside support
    Yin, Dawei
    Meng, Xiangxi
    Zhang, Zhaoyi
    Liu, Baocheng
    INTERNATIONAL JOURNAL OF OIL GAS AND COAL TECHNOLOGY, 2018, 18 (3-4) : 467 - 484