Time Series Prediction on Settlement of Metro Tunnels Adjacent to Deep Foundation Pit by Clustering Monitoring Data

被引:2
|
作者
Zhang, Qi [1 ,2 ]
Ma, Yanning [1 ]
Zhang, Bin [1 ]
Tian, Longgang [1 ]
Zhang, Guozhu [3 ]
机构
[1] Southeast Univ, Sch Civil Engn, Nanjing 211189, Peoples R China
[2] China Univ Min & Technol, State Key Lab Geomech & Deep Underground Engn, Xuzhou 221116, Peoples R China
[3] Southeast Univ, Sch Transportat, Nanjing 211189, Peoples R China
基金
中国国家自然科学基金; 国家重点研发计划;
关键词
Settlement of metro tunnels; Improved data clustering method; Time series prediction; Adjacent to the deep foundation pit; Gaussian Mixture model; SIMILARITY SEARCH; ALGORITHM;
D O I
10.1007/s12205-023-0274-y
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
High requirements are put forward for the settlement control of metro tunnel to ensure the normal and safe operation of adjacent metro line during the process of deep foundation pit construction. Monitoring and predicting could constantly monitor the settlement of the tunnel and make safety early-warning, and massive data to be processed is collected by sensors in this process. In the study, an improved clustering method based on Gaussian mixture model (GMM) is proposed to deal with a large amount of monitoring data. Four initial eigenvalues are defined and the initial core points of clustering are selected by grouping monitoring sensors based on the characteristics of the project site and sensors. An improved method is utilized to the metro tunnel of Metro Line 9 near Xujiahui station. Compared with the traditional clustering method, the improved method has more reliable results, and reduces the operation time by 57.9%. Representative monitoring sensors are selected from each cluster to predict based on Long Short-Term Memory (LSTM) neural network. The prediction results well agree with the measured value and the prediction accuracy is reaching to 99.3%. Compared with other sensor selection ways, the data of representative sensors exhibits good representativeness and effectiveness. Finally, the prediction result after data update is more consistent with the monitoring data than the prediction result without data update. Increasing the data update frequency improves the accuracy of the prediction results in practical engineering application.
引用
收藏
页码:2180 / 2190
页数:11
相关论文
共 50 条
  • [1] Time Series Prediction on Settlement of Metro Tunnels Adjacent to Deep Foundation Pit by Clustering Monitoring Data
    Qi Zhang
    Yanning Ma
    Bin Zhang
    Longgang Tian
    Guozhu Zhang
    KSCE Journal of Civil Engineering, 2023, 27 : 2180 - 2190
  • [2] Settlement prediction for a metro tunnel adjacent to a deep large-scale foundation pit
    Chen, Xifeng
    Liu, Ling
    Huang, Teng
    Modern Tunnelling Technology, 2014, 51 (06) : 94 - 100
  • [3] Influence of foundation pit excavation on adjacent metro tunnels
    Wang Li-feng
    Pang Jin
    Xu Yun-fu
    Yang Kai-fang
    ROCK AND SOIL MECHANICS, 2016, 37 (07) : 2004 - 2010
  • [4] Automatic monitoring and control of excavation disturbance of an ultra-deep foundation pit extremely adjacent to metro tunnels
    Zhao, Yanru
    Chen, Xiangsheng
    Hu, Biao
    Huang, Liping
    Lu, Guohua
    Yao, Hongliang
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2023, 142
  • [5] Influence of construction of deep foundation pit on tunnels of metro
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2000, 22 (03): : 284 - 288
  • [7] Prediction of Buildings' Settlement Induced by Metro Station Deep Foundation Pit Construction
    Xu, Shuting
    Xu, Jinming
    APPLIED SCIENCES-BASEL, 2024, 14 (05):
  • [8] Analysis on settlement monitoring of historical protective buildings adjacent to deep foundation pit excavation
    University of Shanghai for Science and Technology, Shanghai
    200093, China
    不详
    610059, China
    Tumu Gongcheng Xuebao, (137-142):
  • [9] Calculation method of additional load of adjacent metro tunnels due to foundation pit excavation
    Wei G.
    Zhao C.
    1600, Academia Sinica (35): : 3408 - 3417
  • [10] Design and computation of deep foundation pit adjacent to shield tunnel of metro
    Chu, Zhen-Huan, 1600, Chinese Society of Civil Engineering (36):