Application of reliability-centered maintenance for productivity improvement of open pit mining equipment:Case study of Sungun Copper Mine

被引:4
|
作者
Amin Moniri Morad [1 ]
Mohammad Pourgol-Mohammad [2 ]
Javad Sattarvand [1 ]
机构
[1] Department of Mining Engineering,Sahand University of Technology
[2] Department of Mechanical Engineering,Sahand University of Technology
关键词
operating costs; maintenance; mining dump truck; reliability; availability; uncertainty;
D O I
暂无
中图分类号
TD422 [露天矿采掘机械];
学科分类号
0819 ;
摘要
Equipment plays an important role in open pit mining industry and its cost competence at efficient operation and maintenance techniques centered on reliability can lead to significant cost reduction.The application of optimal maintenance process was investigated for minimizing the equipment breakdowns and downtimes in Sungun Copper Mine.It results in the improved efficiency and productivity of the equipment and lowered expenses as well as the increased profit margin.The field operating data of 10 trucks are used to estimate the failure and maintenance profile for each component,and modeling and simulation are accomplished by using reliability block diagram method.Trend analysis was then conducted to select proper probabilistic model for maintenance profile.Then reliability of the system was evaluated and importance of each component was computed by weighted importance measure method.This analysis led to identify the items with critical impact on availability of overall equipment in order to prioritize improvement decisions.Later,the availability of trucks was evaluated using Monte Carlo simulation and it is revealed that the uptime of the trucks is around 11000 h at 12000 operation hours.Finally,uncertainty analysis was performed to account for the uncertainty sources in data and models.
引用
收藏
页码:2372 / 2382
页数:11
相关论文
共 50 条
  • [41] A Simulation Model for Machine Efficiency Improvement Using Reliability Centered Maintenance: Case Study of Semiconductor Factory
    Supsomboon, Srisawat
    Hongthanapach, Kanthapong
    MODELLING AND SIMULATION IN ENGINEERING, 2014, 2014 (2014)
  • [42] Ore blending planning and green shovel allocation in open-pit mines: a case study in a copper mine
    Coutinho N.S.
    Beneteli T.A.P.
    Pessin G.
    Cota L.P.
    International Journal of Mining and Mineral Engineering, 2023, 14 (02) : 95 - 123
  • [43] Method of reliability assessment of pin joints in undercarriages of open-pit mining machinery-a case study
    Sokolski, P. M.
    RISK, RELIABILITY AND SAFETY: INNOVATING THEORY AND PRACTICE, 2017, : 2472 - 2477
  • [44] A stochastic mine planning approach to determine the optimal open pit to underground mining transition depth - case study at the Geita gold mine, Tanzania
    MacNeil, J.
    Dimitrakopoulos, R.
    Peattie, R.
    MINING TECHNOLOGY-TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY, 2022, 131 (03) : 181 - 190
  • [45] Production control and optimization in open pit mining using a drill monitoring system and an image analysis system - A case study from Aitik copper mine in Sweden
    Schunnesson and Shahram Mozaffari, Lulea University of Technology, Sweden
    J Mines Met Fuels, 2009, 9 (244-251):
  • [46] Evaluation of the overall effectiveness (OEE) of autonomous transportation system (AHS) equipment and its impact on mine design. Open pit mine case study
    Pais Cerna, Gabriel Eugenio
    Coronado Hernandez, Jairo Rafael
    Mojica Herazo, Julio Cesar
    Pineres Castillo, Aurora
    18TH INTERNATIONAL CONFERENCE ON FUTURE NETWORKS AND COMMUNICATIONS, FNC 2023/20TH INTERNATIONAL CONFERENCE ON MOBILE SYSTEMS AND PERVASIVE COMPUTING, MOBISPC 2023/13TH INTERNATIONAL CONFERENCE ON SUSTAINABLE ENERGY INFORMATION TECHNOLOGY, SEIT 2023, 2023, 224 : 468 - 473
  • [47] DEFORMATION CHARACTER AND STABILITY ANALYSIS OF THE LANDSLIDE CAUSED BY THE MINING ACTIVITY: A CASE STUDY IN THE WEST OPEN-PIT MINE, CHINA
    Nie, Lei
    Li, Zechuang
    Zhang, Min
    JOURNAL OF THE BALKAN TRIBOLOGICAL ASSOCIATION, 2016, 22 (1A): : 1001 - 1013
  • [48] Evaluation of groundwater pollution in a mining area using analytical solution: a case study of the Yimin open-pit mine in China
    Li, Tianxin
    Li, Li
    Song, Hongqing
    Meng, Linglong
    Zhang, Shuli
    Huang, Gang
    SPRINGERPLUS, 2016, 5
  • [49] Study on the Process and Mechanism of Slope Failure Induced by Mining under Open Pit Slope: A Case Study from Yanqianshan Iron Mine, China
    Hu, Yingpeng
    Ren, Fengyu
    Ding, Hangxing
    Fu, Yu
    Tan, Baohui
    ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [50] A new approach for evaluation of slope stability in large open-pit mines: a case study at the Dexing Copper Mine, China
    Du, Shi-Gui
    Saroglou, Charalampos
    Chen, Yifan
    Lin, Hang
    Yong, Rui
    ENVIRONMENTAL EARTH SCIENCES, 2022, 81 (03)