Stochastic Earned Duration Analysis for Project Schedule Management

被引:0
|
作者
Fernando Acebes [1 ]
David Poza [1 ]
José Manuel González-Varona [1 ]
Adolfo López-Paredes [1 ]
机构
[1] GIR INSISOC-Department of Business Organization and CIM, School of Industrial Engineering, University of Valladolid
关键词
D O I
暂无
中图分类号
TU722 [施工计划];
学科分类号
1201 ;
摘要
Earned duration management(EDM) is a methodology for project schedule management(PSM) that can be considered an alternative to earned value management(EVM). EDM provides an estimation of deviations in schedule and a final project duration estimation. There is a key difference between EDM and EVM: In EDM, the value of activities is expressed as work periods; whereas in EVM, value is expressed in terms of cost. In this paper, we present how EDM can be applied to monitor and control stochastic projects. To explain the methodology, we use a real case study with a project that presents a high level of uncertainty and activities with random durations. We analyze the usability of this approach according to the activities network topology and compare the EVM and earned schedule methodology(ESM) for PSM.
引用
收藏
页码:148 / 161
页数:14
相关论文
共 50 条
  • [1] Stochastic Earned Duration Analysis for Project Schedule Management
    Fernando Acebes
    David Poza
    José Manuel González-Varona
    Adolfo López-Paredes
    [J]. Engineering, 2022, 9 (02) : 148 - 161
  • [2] Stochastic Earned Duration Analysis for Project Schedule Management
    Acebes, Fernando
    Poza, David
    Gonzalez-Varona, Jose Manuel
    Lopez-Paredes, Adolfo
    [J]. ENGINEERING, 2022, 9 : 148 - 161
  • [3] Using real project schedule data to compare earned schedule and earned duration management project time forecasting capabilities
    de Andrade, Paulo Andre
    Martens, Annelies
    Vanhoucke, Mario
    [J]. AUTOMATION IN CONSTRUCTION, 2019, 99 : 68 - 78
  • [4] Project Duration Forecasting by Effective Earned Schedule
    Nie Xiangtian
    Liu Yingjie
    [J]. 2010 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE AND ENGINEERING (MSE 2010), VOL 1, 2010, : 321 - 323
  • [5] Project Management Model: Integrating Earned Schedule, Quality, and Risk in Earned Value Management
    Miguel, Angelimarie
    Madria, Wira
    Polancos, Ronaldo
    [J]. 2019 IEEE 6TH INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND APPLICATIONS (ICIEA), 2019, : 622 - 628
  • [6] Dangers in using earned duration and other earned value metrics to measure a project's schedule performance
    Wendell, Richard E.
    Lowe, Timothy J.
    Gordon, Mike M.
    [J]. CENTRAL EUROPEAN JOURNAL OF OPERATIONS RESEARCH, 2023, 31 (02) : 665 - 680
  • [7] Dangers in using earned duration and other earned value metrics to measure a project’s schedule performance
    Richard E. Wendell
    Timothy J. Lowe
    Mike M. Gordon
    [J]. Central European Journal of Operations Research, 2023, 31 : 665 - 680
  • [8] Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control
    Song, Jie
    Martens, Annelies
    Vanhoucke, Mario
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2022, 297 (02) : 451 - 466
  • [9] EDM: Earned Duration Management, a new approach to schedule performance management and measurement
    Khamooshi, Homayoun
    Golafshani, Hamed
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (06) : 1019 - 1041
  • [10] Forecasting project duration using risk-based earned duration management
    Roghabadi, Mohammadjavad Arabpour
    Moselhi, Osama
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (16) : 3077 - 3087