Stability analysis of surrounding rock of large underground powerhouse cavern group

被引:0
|
作者
School of Water Resources and Hydropower, Wuhan University, Wuhan 430072, China [1 ]
不详 [2 ]
不详 [3 ]
机构
来源
Yanshilixue Yu Gongcheng Xuebao | 2008年 / SUPPL.卷 / 2864-2872期
关键词
Elastoplasticity - Numerical models - Rocks - Arch dams - Finite element method - Caves - Geomechanics;
D O I
暂无
中图分类号
学科分类号
摘要
Jinping first stage hydropower station is a concrete double-curvature arch dam with a maximum height of 305 m. It has a total capacity of 360 × 104 kW, the total reservoir capacity is 77.6 × 108 m3, and the regulating capacity is 49.1 × 108 m3. It is the highest in the world, and its design complexity is at the worlds top level. In response to the low surrounding rock classification, developed structure planes, high geostress and massive underground cavern group, the 3D nonlinear elastoplastic damage finite element method is applied to analyze and compute the stability of underground cavern groups to make certain the rationality of the layout of underground cavern group, the sequence of construction and support parameters of surrounding rock. By analyzing and comparing the numerical simulation results and geomechanical model experimental data, it is indicated that the numerical simulation results agree well with the experimental data. The stability of the underground cavern group satisfies the requests of design.
引用
收藏
相关论文
共 50 条
  • [41] Research on country rock stability of underground cavern group of Dachaoshan Hydroelectric Station
    Shen, J
    Gu, JC
    Zhang, XY
    Chen, AM
    PROGRESS IN SAFETY SCIENCE AND TECHNOLOGY, VOL 4, PTS A and B, 2004, 4 : 731 - 737
  • [42] Three dimensional numerical analysis of stability of surrounding rocks of Shuibuya underground powerhouse
    Zhang, Lian
    Ding, Xiu-Li
    Fu, Jing
    Yantu Lixue/Rock and Soil Mechanics, 2003, 24 (SUPPL.): : 120 - 123
  • [43] Visualization and early warning analysis of damage degree of surrounding rock mass in underground powerhouse
    Sun, Yuepeng
    Su, Haijian
    Xiao, Peiwei
    Li, Peng
    Li, Biao
    Zhou, Xiang
    Bian, Kaiqi
    Xu, Nuwen
    INTERNATIONAL JOURNAL OF MINING SCIENCE AND TECHNOLOGY, 2023, 33 (06) : 717 - 731
  • [44] A simplified analysis method of block stability in large underground powerhouse
    Zhou Yang-yi
    Feng Xia-ting
    Xu Ding-ping
    He Ming-wu
    ROCK AND SOIL MECHANICS, 2016, 37 (08) : 2391 - 2398
  • [46] Numerical stability analysis of a large cavern in weak rock
    Fowell, RJ
    Ma, SJ
    ENVIRONMENTAL AND SAFETY CONCERNS IN UNDERGROUND CONSTRUCTION, VOLS, 1 AND 2, 1997, : 293 - 298
  • [47] Large deformation evolution and failure mechanism analysis of the multi-freeface surrounding rock mass in the Baihetan underground powerhouse
    Wang, Meng
    Li, Hai-bo
    Han, Jin-qi
    Xiao, Xin-hong
    Zhou, Jia-wen
    ENGINEERING FAILURE ANALYSIS, 2019, 100 : 214 - 226
  • [48] Stability analysis of huge underground cavern group in jointed rockmass
    Wang Gang
    Li Shu-cai
    Wang Shu-gang
    Sui Bin
    Wang Zhe-chao
    ROCK AND SOIL MECHANICS, 2008, 29 (01) : 261 - 268
  • [49] A comparative study on the performance of back analysis procedures for identification of nonlinear deformational behavior of a rock mass around a large underground powerhouse cavern
    Akutagawa, S
    Takeuchi, K
    Shimura, T
    Sakurai, S
    PACIFIC ROCKS 2000: ROCK AROUND THE RIM, 2000, : 1035 - 1041
  • [50] Stability analysis of huge underground cavern group in jointed rockmass
    Wang, Gang
    Li, Shu-Cai
    Wang, Shu-Gang
    Sui, Bin
    Wang, Zhe-Chao
    Yantu Lixue/Rock and Soil Mechanics, 2008, 29 (01): : 261 - 268