Effect of foulant on temperature and steam quality profiles in once-through steam generator tubes

被引:0
|
作者
Sivagnanam, Mohan [1 ]
Mehrotra, Anil K. [1 ]
Gates, Ian D. [1 ]
机构
[1] Univ Calgary, Schulich Sch Engn, Dept Chem & Petr Engn, Calgary, AB T2N 1N4, Canada
基金
加拿大自然科学与工程研究理事会;
关键词
Once-through steam generators; Foulant; Heat transfer; Steam Generation; Oil Sands;
D O I
10.1016/j.tsep.2024.103059
中图分类号
O414.1 [热力学];
学科分类号
摘要
Once-through steam generators (OTSGs) are commonly used in the oil sands industry for steam generation for in- situ thermal recovery of extra heavy oil. These are expensive operations with challenges associated with the deposition of foulants, arising from solids and hydrocarbons in the boiler feed water, on the inner tube wall that leads to a decreased heat transfer rate. The foulant deposition also causes elevated tube-wall temperatures, which may lead to tube failure. This study examines the impact of foulant on the tube-wall temperature profile and vapor-to-liquid ratio in an OTSG. A three-dimensional finite volume model of multiphase flow and heat transfer in a single pass of a field-scale OTSG unit is described. Detailed flow behavior and heat transfer characteristics of water and steam from the CFD model were compared to field data. Thereafter, fouling was added to the model to explore overheating and erosion zones in the OTSG tubes. Velocity, temperature distribution, and steam generation in the OTSG tubes in the convection section and radiant section were investigated for areas prone overheating. It was found that the CFD model simulation results closely matched the bulk fluid temperature of the field unit. In the presence of fouling, the outer skin temperature from the model was well within the range of the thermocouple data from the field unit, enabling the application of the model to identify the foulant thickness based on the outer skin temperature. Lastly, the model demonstrated that the bends are the most likely sites for erosion within the pass.
引用
收藏
页数:13
相关论文
共 50 条
  • [21] Model Predictive Control of Once Through Steam Generator Steam Quality
    Qi, Fei
    Shukeir, Eliyya
    Kadali, Ramesh
    IFAC PAPERSONLINE, 2015, 48 (08): : 716 - 721
  • [22] Study on flow instability in annular tube once-through steam generator
    Wu, Ge-Ping
    Qiu, Sui-Zheng
    Su, Guang-Hui
    Jia, Dou-Nan
    Yuanzineng Kexue Jishu/Atomic Energy Science and Technology, 2007, 41 (03): : 325 - 330
  • [23] Research on Active Disturbance Rejection Control of Once-through Steam Generator
    Cheng Y.
    Ma Z.
    Wang M.
    Zhang Y.
    Hedongli Gongcheng/Nuclear Power Engineering, 2022, 43 (06): : 146 - 150
  • [24] Variable universe fuzzy control of once-through steam generator feedwater
    Liu, Junfeng
    Wang, Chenglong
    Qiu, Suizheng
    Dong, Lining
    ANNALS OF NUCLEAR ENERGY, 2024, 207
  • [25] Dynamic simulation of once-through steam generator with concentric annuli tube
    Zhu Jingyan
    Guo Yun
    Zhang Zhijian
    ANNALS OF NUCLEAR ENERGY, 2012, 50 : 185 - 198
  • [26] REVIEW OF ONCE-THROUGH STEAM GENERATORS
    FANARITIS, JP
    KIMMEL, JD
    JOURNAL OF PETROLEUM TECHNOLOGY, 1965, 17 (04): : 409 - +
  • [27] QUALIFICATION OF A MODEL FOR ONCE-THROUGH STEAM-GENERATOR LOFW TRANSIENTS
    KERN, RC
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1984, 46 : 823 - 824
  • [28] A MOVABLE BOUNDARY MODEL FOR ONCE-THROUGH STEAM-GENERATOR ANALYSIS
    TZANOS, CP
    NUCLEAR TECHNOLOGY, 1988, 82 (01) : 5 - 17
  • [29] Modelling and simulation study on a supercritical once-through boiler steam generator
    Southeast Univ, Nanjing, China
    Zhongguo Dianji Gongcheng Xuebao, 5 (350-356):
  • [30] SIMULATION STUDY OF DYNAMIC CHARACTERISTIC OF ONCE-THROUGH STEAM GENERATOR FOR CEFR
    Ye Shangshang
    Yang Hongyi
    Wang Xiaokun
    PROCEEDINGS OF THE 24TH INTERNATIONAL CONFERENCE ON NUCLEAR ENGINEERING, 2016, VOL 2, 2016,